Just Decided – New Jersey Supreme Court: Insurers Can Look To Extrinsic Evidence To Deny a Defense
September 05, 2022 —
Randy J. Maniloff - White and Williams LLPLast week, the New Jersey Supreme Court decided Norman International, Inc. v. Admiral Insurance Company, No. 086155 (N.J. Aug. 11, 2022). At issue was coverage for a work-site injury and the interpretation of a policy exclusion for operations or activities performed by an insured in certain counties in New York. The case is significant in terms of addressing causation for purposes of the application of exclusions. But the more wide-reaching issue has nothing to do with the scope of the exclusion.
The real story from Norman is the New Jersey high court’s pronouncement that an insurer, in certain circumstances, can use extrinsic evidence to deny a defense to its insured. New Jersey duty to defend law has been a jungle land and in need of more supreme court guidance.
Read the court decisionRead the full story...Reprinted courtesy of
Randy J. Maniloff, White and Williams LLPMr. Maniloff may be contacted at
maniloffr@whiteandwilliams.com
Project Completion Determines Mechanics Lien Recording Deadline
April 08, 2024 —
William L. Porter - Porter Law GroupThe California mechanics lien is one of the most powerful collection remedies available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California private works construction project. The mechanics lien allows the claimant to actually sell the property where the work was carried out in order to obtain payment, entirely of course, against the wishes of the property owner. There are a number of important steps to follow and timelines to be met in order to pursue this remedy.
First, Understand Your Preliminary Notice Deadline
Working within deadlines is absolutely crucial to preserving mechanics lien rights under California law. The deadlines differ, depending on whether you are a “direct” contractor, also known as “original” or “prime” contractor (one who contracts directly with the property owner) or a subcontractor or material supplier. The process begins with the serving of a “preliminary notice” no later than 20 days after the party serving the preliminary notice begins supplying labor or materials to the project. Direct contractors are only required to serve the preliminary notice on the construction lender (Civil Code section 8200-8216), whereas subcontractors and material suppliers must serve not only the construction lender, but also the owner and direct contractor (see Civil Code section 8200(e)).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Parties Can Agree to Anything In A Settlement Agreement………Or Can They?
October 17, 2023 —
Alexa Stephenson & Ivette Kincaid - Kahana FeldA settlement agreement is a contract. When parties to pending litigation enter into a settlement, they enter into a contract. Such a contract is subject to the general law governing all contracts. (T. M. Cobb Co. v. Superior Court (1984) 36 Cal.3d 273, 280 [204 Cal. Rptr. 143, 682 P.2d 338] [offers by a party to compromise under Code Civ. Proc., § 998].) Courts seek to interpret contracts in a manner that will render them “lawful, operative, definite, reasonable, and capable of being carried into effect’” without violating the intent of the parties. (Robbins v. Pacific Eastern Corp. (1937) 8 Cal.2d 241, 272–273; Kaufman v. Goldman, (2011) 195 Cal. App. 4th 734, 745.
A settlement agreement like a contract is a document that is typically negotiated between the parties to the agreement and it is up to the parties to determine its terms. Settlements take time and sometimes negotiating the settlement terms takes longer. This is especially true in complex litigation and multiparty matters where negotiating the settlement terms is just as contentious as litigating the matter. Just like contracts, in a settlement agreement the parties cannot agree to terms that violate public policy. A contract is thought to be against public policy if it results in a breach of law, harms citizens, or causes injury to the state. Contracts that are voided on public policy grounds carry no legal obligations. For example, an employer cannot force an employee to sign a contract that forbids the worker from joining a union.
Reprinted courtesy of
Alexa Stephenson, Kahana Feld and
Ivette Kincaid, Kahana Feld
Ms. Stephenson may be contacted at astephenson@kahanafeld.com
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
TxDOT, Flatiron/Dragados Mostly Resolve Bridge Design Dispute
March 13, 2023 —
James Leggate - Engineering News-RecordThe Texas Dept. of Transportation and contractor Flatiron/Dragados LLC have “completely satisfied”
four of the five main design safety concerns the state agency raised over the under-construction new Harbor Bridge in Corpus Christi, officials say.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
What to Look for in Subcontractor Warranty Endorsements
February 03, 2020 —
David M. McLain – Colorado Construction LitigationWith increasing frequency in the construction defect cases we defend, we are seeing commercial general liability insurance policies with “subcontractor warranty” endorsements. Also known as contractor or subcontractor special conditions, these endorsements could have severe and negative consequences for builders that do not comply with their requirements. In researching for this article, I reviewed six different endorsements used by six different carriers, all of which contained some or all of the following requirements:
- The builder must have signed subcontract agreements with its subcontractors that require subcontractors to hold harmless, i.e., defend and indemnify, the builder for “bodily injury” or “property damage” claims caused by their negligence.
- The subcontractors must maintain their own insurance with limits equal to or greater than the limits in the builder’s own policy, with limits of at least $1 million per occurrence.
- The subcontractors’ insurance must not exclude the work being performed for the builder, e.g., the excavator’s policy cannot exclude earth movement claims, the subcontractor’s policy cannot exclude residential construction.
- The subcontractors must maintain their own workers’ compensation and/or employer’s liability insurance.
- The subcontractors must provide the builder with an endorsement or a certificate of insurance indicating that the builder has been added to the subcontractors’ insurance as an additional insured.
- The subcontractors must provide the builder with an endorsement or a certificate of insurance indicating that their insurance carriers have agreed to provide waivers of subrogation in favor of the builder.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Insurance Agent Sued for Lapse in Coverage after House Collapses
October 29, 2014 —
Beverley BevenFlorez-CDJ STAFFProperty Casualty 360 reported a Hawaii case where the court ruled that an “insurance brokerage firm is responsible for the wrongful conduct of its employees, agents and independent contractors as long as they give the public the appearance that the individual is working as an agent of the brokerage.”
The case involved a home that collapsed “during an attempted structural renovation.” The original insurance policy had lapsed, and the “application used to procure the second policy stated that there was no renovation work underway on the property, and thus contained a material misrepresentation which voided the second policy, the [homeowners] were left without insurance on the house.”
Read the court decisionRead the full story...Reprinted courtesy of
U.K. High Court COVID-19 Victory for Policyholders May Set a Trend in the U.S.
November 09, 2020 —
Andres Avila & Anastasiya Collins - Saxe Doernberger & VitaOn September 15, 2020, in a matter entitled The Financial Conduct Authority v. Arch & Others1, the High Court of Justice of England and Wales, the equivalent of a trial court in the U.S., issued a ruling on a COVID-19 business interruption insurance case (the “Judgment”). Significantly, the Court sided with policyholders on most key coverage issues under specific non-damage business interruption insurance coverage forms. U.S. policyholders should review whether any of their policies issued by U.K.-based carriers, which may be subject to English law and have the forms discussed below, are impacted by this favorable decision.
The Financial Conduct Authority (“FCA”), the U.K. financial regulatory body, brought the case to establish liability under 21 lead representative sample policy wordings from eight insurer defendants. The case was filed on an expedited basis on June 9, 2020 under the Financial Market Test Case Scheme, which is used for claims of general importance that require authoritative court guidance. Although the Judgment is legally binding only on the carriers who were parties to the action, the FCA estimates the case could affect 700 types of policies across 60 different insurers, and 370,000 small to medium-sized enterprises policyholders (“SME”) in the U.K. While the Judgment may be appealed, it is expected to incentivize insurers to settle their claims before the outcome of an appeal is known.
Reprinted courtesy of
Andres Avila, Saxe Doernberger & Vita and
Anastasiya Collins, Saxe Doernberger & Vita
Mr. Avila may be contacted at AAvila@sdvlaw.com
Ms. Collins may be contacted at ACollins@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (7/10/24) – Strong Construction Investment in Data Centers, Increase Use of Proptech in Hospitality and Effects of Remote-Work on Housing Market
August 05, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, renters stay in their units longer, GenAI change how commercial real estate operates, and banks continue high exposure due to commercial real estate.
- Strong investor interest, particularly in opportunistic and value-add segments, signals a strong market for construction firms specializing in high-yield projects. (Sebastian Obando, Construction Dive)
- A growing number of renters are staying in their units for longer periods of time than they did a decade ago with over one-third of U.S. renters have lived in the same apartment for more than five years. (Mary Salmonsen, Multifamily Dive)
- Several U.S. regional and mid-sized banks continue to face the squeeze from high exposure to the commercial real estate sector that has been shaken by higher-for-longer interest rates and empty office buildings. (Reuters)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team