Federal Miller Act Payment Bond Claim: Who Gets Paid and Who Does Not? What Are the Deadlines?
September 16, 2019 —
William L. Porter - Porter Law GroupWhen working on federal public works construction projects there are no Stop Payment Notice or Mechanics Lien remedies available to protect subcontractors’ and suppliers’ right to payment. Instead, unpaid subcontractors and suppliers must resort to making a claim for payment under a federal law known as the AMiller Act@ (40 USCS 3131 et seq.). Many claimants however, do not realize that the right to make a Miller Act claim is not available to all subcontractors and suppliers. Before committing to performing work on a federal project it is important for subcontractors and suppliers to understand whether or not a Miller Act claim will be available. For those who have no Miller Act rights, careful consideration must be given to whether it is worth the risk to take on the project. For those who have valid Miller Act claim rights, important deadlines must be considered.
Who Gets Paid Under a Miller Act and Who Does Not
For federal projects in excess of $100,000, contractors who have a contract directly with the Federal Government must obtain Miller Act Payment Bond intended for the protection of Subcontractors, laborers and material suppliers to the project.
As a general rule, every subcontractor, laborer, or material supplier who deals directly with the prime contractor and is unpaid may bring a lawsuit for payment against the Miller Act Payment Bond. Further, every unpaid subcontractor, laborer, or material supplier who has a direct contractual relationship with a first-tier subcontractor may bring such an action. The deadlines for these claims are described below.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Insurer Incorrectly Relies Upon "Your Work" Exclusion to Deny Coverage
June 10, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Eleventh Circuit reversed the district court's determination that there was no coverage based upon the policy's "your work" exclusion. Southern-Owners Ins. Co. v. Mac Contractors of Fla, LLC, 2019 U.S. App. LEXIS 10689 (11th Cir. April 11, 2019).
Mac Contractors contracted with the homeowners to custom build their home. After construction began, Mac left the site before completing the project and before the issuance of a certificate of occupancy. The homeowners sued, alleged damage to wood floors and the metal roof.
Southern-Owners originally agreed to defend under the CGL policy, but later withdrew the defense and filed this action for declaratory relief. The parties cross-filed motions for summary judgment. Southern-Owners argued that the "your work" exclusion applied to bar coverage. The "your work" exclusion barred coverage for "'property damage' to 'your work' arising out of it or any part of it and included in the 'products' completed operations hazard.'" The "products' completed operations hazard" included all "'property damage' occurring away from premises you own or rent and arising out of . . . 'your work' except . . . (1) products that are still in your physical possession; or (2) work that has not yet been completed or abandoned."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Preventing Costly Litigation Through Your Construction Contract
August 17, 2011 —
Douglas Reiser, Builders Council BlogIt’s Tuesday, which means it ’s the middle of your work week. Tuesday is a great time to take an hour to look over your contracts, while the crews are pushing through their scheduled work. Today’s food for thought: How do you use your contract to reduce your litigation burden?
Your contract should do many things. It should discuss the scope of work, scheduling of work, quality of work, coverage for liabilities and conditions and timeliness for payment. But often overlooked is how your contract can lend to dispute resolution.
Commonly, you will see a simple provision that covers governing law, venue for disputes and the awarding of attorneys’ fees. But you can do better. Remember, a contract is enforced to the maximum extent possible in Washington state.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
The New Industrial Revolution: Rebuilding America and the World
March 04, 2019 —
Drew Buechley - Construction ExecutiveConventional thinking says the Industrial Revolution ended more than a century ago. Yet one crucial industry has lagged behind revolutionary changes stemming from the transition from hand production methods to the use of machines and rise of factory systems. In the 1800s, these transitions caused an influx of people to urban centers, where the majority of those changes were centered. The outcome? Not enough capital or time to build adequate housing, pushing low-income newcomers into overcrowded, unsanitary slums, resulting in increased death rates and endemic levels of contagious diseases. While other industries mechanized and surged, construction remained stagnant in comparison to demand.
Fast forward to the 21st century where the U.S .benefits from a developed and industrialized world. Monumental gains in technology, combined with regulations designed to protect communities from polluted waters and disease, have drastically improved quality of life. Yet one similarity remains – the industry still struggles to build enough housing for a growing population. Urban centers have been neglected for decades while the rate of urbanization increases annually. Communities still have no access to clean drinking water and many suffer from crumbling infrastructure. Home ownership is out of reach for an entire generation, with metropolitan areas unable to keep up with demand for housing. At the very center of this lies the staid construction industry. Lagging behind the rest of the industrialized world in terms of technology advances, it has severely impacted the ability to maintain a livable nation and world.
Reprinted courtesy of
Drew Buechley, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Daily Reports – The Swiss Army Knife of Project Documentation
June 08, 2020 —
Christopher A. Henry - ConsensusDocsProject “Daily Reports” are some of the most important, yet overlooked aspects of a construction project. These reports serve many beneficial roles such as holding parties accountable to their obligations, providing the basis for an as-built schedule, recording manpower, documenting site conditions, and recording any other important and relevant information that happened on the job site that day. Daily reports can also provide information to help with claims or disputes that may arise in the future, such as noting weather delays, providing backup for future delay claims, and providing information to dispute claims made against your company. Finally, daily reports also serve as a useful communication tool during the project and a source of real time information for parties that want to know how the work is commencing on a day to day basis. Because daily reports are the “Swiss army knife” of project documentation, it is extremely important that a contractor puts for its best effort when creating them.
It is no secret that a construction project can become more chaotic as the schedule progresses. Unfortunately, when that is the case, the effort put into creating these reports drops off and sometimes the responsibility of creating such reports is thrown aside altogether. I can speak from experience. Prior to entering the practice of law, I was a project engineer for a general contractor in Atlanta. As an engineer in the field, one of my many responsibilities was to enter the daily reports. Based off this experience, below are some thoughts on how to prepare useful daily reports.
1. Check the contract. The contract you entered may set forth specific requirements for the daily reports, such as where to file them, the required format, and specific information that must be included. Complying with contractual requirements is necessary for a successful project. One word of caution for subcontractors, a subcontract will often incorporate the prime contract. If that is the case, be sure to check the prime contract for any specific language relating to daily reports.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher A. Henry, Jones Walker LLP Mr. Henry may be contacted at
chenry@joneswalker.com
Wells Fargo Shuns Peers’ Settlement in U.S in Mortgage
May 13, 2014 —
Andrew Zajac – BloombergFollowing two years in which its big-bank peers paid almost $2 billion to resolve fraud accusations by the Federal Housing Administration, Wells Fargo & Co. (WFC) has decided it isn’t giving up so easily.
Wells Fargo was one of five banks that agreed in 2012 to a nationwide, $25 billion settlement with the Justice Department over mortgage wrongdoing that included botched foreclosures. The FHA then took additional action against four of the banks, including Wells Fargo, for related housing-crisis wrongdoing. Bank of America Corp., Citigroup Inc. and JPMorgan Chase & Co. decided to settle those matters. San Francisco-based Wells Fargo, which argued the nationwide settlement should have blocked the new FHA claims against it, chose to fight.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew Zajac, BloombergMr. Zajac may be contacted at
azajac@bloomberg.net
Court Calls Lease-Leaseback Project What it is: A Design-Bid-Build Project
August 19, 2015 —
Garret Murai – California Construction Law BlogFirst there was “Prince.”
Then there was “The Artist Formerly Known as Prince.”
Then there was “The Artist Formerly Known as Prince (Because he Changed His Name to a Symbol), But Then Realized That No One Could Pronounce the Symbol (and What Good is a Symbol if Everyone Has to Wave Their Hands Wildly at You to Get Your Attention or Scream ‘Hey You!’), and So Changed His Name Back to Prince Again.”
Whatever name (or symbol) he was going by, everyone knew him as the guy who told us to party like it was 1999 (when 1999 still seemed like the distant future), who sang about a girl with a “pocket full of horses” (which totally flew past my junior high school brain at the time), and gave us such great metaphors as “if the elevator tries to bring you down, go crazy, punch a higher floor!”
Like Prince or his symbol, sometimes it doesn’t matter what label you put on something when everyone knows what that something is. In law, we call it looking at the “substance” rather than its “form.” And, in the next case, Davis v. Fresno Unified School District, the California Court of Appeals for the Fifth District made quick work of a purported “lease-leaseback” project – a project delivery method available to school districts whereby a school district leases property it owns to a developer for a minimum of $1, who in turns builds a school facility on the site and leases the facility and the site back to the school district, who in turn takes ownership of the facility and site at the end of the lease – and called it for what it was: a run-of-the-mill “design-bid-build” project.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Corps Releases Final Report on $29B Texas Gulf Coast Hurricane Defense Plan
October 11, 2021 —
James Leggate - Engineering News-RecordA $28.87 billion plan to protect the Texas Gulf Coast’s residents and infrastructure against hurricanes and storm surge with a series of coastal storm risk management and ecosystem restoration projects took a step closer to reality Sept. 10 with the release of a final feasibility report and final environmental impact statement from the U.S. Army Corps of Engineers and Texas General Land Office (GLO).
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at https://www.enr.com/leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of