Despite Misapplying California Law, Federal Court Acknowledges Virus May Cause Physical Alteration to Property
October 26, 2020 —
Scott P. DeVries, Michael S. Levine & Michael L. Huggins - Hunton Insurance Recovery BlogOn August 28, Judge Stephen V. Wilson of the Central District of California, entered the latest ruling in the ongoing saga of the COVID-19 business interruption coverage dispute between celebrity plaintiff’s attorney Mark Geragos and Insurer Travelers.
The case, 10E, LLC v. The Travelers Indemnity Co. of Connecticut, was filed in state court. Travelers removed to federal court, where Geragos sought remand and Travelers moved to dismiss. Judge Wilson denied remand and granted the Motion to Dismiss, finding plaintiff did not satisfactorily allege the actual presence of COVID-19 on insured property or physical damage to its property. This holding is inconsistent with long standing principles of California insurance law and appears to improperly enhance the minimal pleading threshold under Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (To survive a motion to dismiss, a complaint need only allege a claim “that is plausible on its face.”).
After rejecting Geragos’ attempt to have the case remanded based on a finding that Geragos had fraudulently joined a defendant to avoid removal, the Judge proceeded to the Motion to Dismiss which raised three issues: (1) the effect of the Virus Exclusion in the Travelers’ Policy, (2) whether plaintiff failed to allege that the governmental orders prohibited access to its property, and (3) whether plaintiff could “‘plausibly allege that it suffered ‘direct physical loss or damage to property’ as required for civil authority coverage.’” Rather than address the effect of the exclusion, which would be the narrowest issue (this exclusion is not present in all policies), the Court proceeded directly to the third issue, which has the broadest potential application.
Reprinted courtesy of
Scott P. DeVries, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Michael L. Huggins, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Huggins may be contacted at mhuggins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
No Additional Insured Coverage Under Umbrella Policy
March 12, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe additional insured was not covered under a property policy for an injury occurring after work was completed. Lewark v. Davis Door Servs., 2014 Wash. App. LEXIS 341 (Wash. Ct. App. Feb. 10, 2014).
Public Storage, Inc. hired Davis Door Service Inc. to perform work at its facilities. The master agreement required Davis Door to maintain a CGL policy that insured Public Storage "during the entire progress of the work." Davis Door secured a CGL policy with American Economy. It also took out an umbrella liability policy with American States.
After Davis Door completed work on a door, Terrie Lewark injury her back opening the door. She sued Public Storage and Davis Door. Lewar and Public Storage settled. Public Storage assigned to Lewark its rights under the umbrella policy with American States. Lewark then sued Davis Door and American States. The trial court found that Public Storage was not an additional insured under the American States umbrella policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
What are the Potential Damages when a House is a Lemon?
September 01, 2016 —
Haldon L. Greenberg, Esq. – Florida Construction Law NewsIt seems that lemons are front page news these days. Beyonce just released a chart-topping[1] album all about what to do when life hands you lemons. In today’s vernacular, we use the term “Lemon” to describe a person or thing that is unsatisfactory, disappointing, or feeble.[2] In Florida, there is a “Lemon Law” that provides a way for consumers to receive a replacement or full refund for vehicles found to have defects which may affect the vehicle’s safety, value or use.[3] While there is no “Lemon Law” for construction projects, in Gray v. Mark Hall Homes, Inc.,[4] Florida’s Second District Court of Appeal cited to Florida Supreme Court precedent in holding that a home builder was on the hook for the entire contract value of a home he contracted to build for the Plaintiff, when it was revealed the home was a “Lemon”, or as the evidence at trial showed, “valueless.”
Read the court decisionRead the full story...Reprinted courtesy of
Haldon L. Greenberg, Esq., Cole, Scott & Kissane, P.A.Mr. Greenberg may be contacted at
haldon.greenburg@csklegal.com
Do We Really Want Courts Deciding if Our Construction Contracts are Fair?
March 19, 2015 —
Christopher G. Hill – Construction Law MusingsAs I posted recently, the Virginia General Assembly has passed, and I can see no reason why the governor won’t sign, a bill that would
essentially invalidate preemptive contractual waivers of lien rights as they relate to subcontractors and material suppliers. It does not apply to General Contractors, but it is a step in what many (including those attorneys that represent subcontractors and suppliers) believe is the right direction.
Of course, as soon as I posted last week, my friend and colleague
Scott Wolfe (@scottwolfejr) commented on that post and then
gave his two cents worth at his Zlien blog. The gist of the comments here at Musings and the post over at his blog was essentially that these contractual provisions were inherently unfair and therefore should be abolished because of both a relative disparity in leverage between the Owner or GC and the Subcontractor when it comes to negotiations and the fact that subcontractors often don’t read their contracts or
discuss them with a construction attorney prior to signing them. I hear this first of his arguments often when I am reviewing a contract after the fact and a client or potential client acts surprised that a provision will be enforced and the courts of the Commonwealth of Virginia will actually enforce them. As to Scott’s second reason, I have always warned here at Musings that
you should read your contracts carefully because they will be the law of your business relationship in the future.
The first of his two points is more interesting and in some ways more easily supported. However, where we are speaking of contracts between businesses where both sides are bound by the terms of the contract, it begs the question of whether in seeking to make contracts more “fair” we could add a layer of uncertainty that could cause more problems than it solves. Do we really want courts stepping in after the fact to renegotiate the terms of a deal that was struck months or possibly years before because one judge believes that the deal was too one sided? Do we really need such “Monday morning quarterbacking?” Is one person’s idea of “fair” better than another’s when both parties to the contract had the full ability to read, negotiate and possibly reject the deal long ago? Personally, I think that the answer to these questions is, in all but the most egregious cases or where the legislatures have stepped in adding certainty (whether to the good or bad), “No.”
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Keeping Detailed Records: The Best Defense to Constructive Eviction
October 24, 2023 —
Ben T. Welch & Ken Brown - Snell & WilmerInevitably, commercial property owners and managers will be faced with a claim by a tenant of constructive eviction. This article is intended to describe what constructive eviction is and to suggest what owners and managers can do to prepare for, and ward off, such claims.
Constructive eviction occurs where a tenant’s “right of possession and enjoyment” of the leasehold is disrupted by the landlord in a manner that renders the premises “unsuitable for the purposes intended.”i Put another way, it is interference that is so “substantial nature and so injurious as to deprive the tenant of the beneficial enjoyment of a part or the whole of the demised premises.”ii Although easy to describe in theory, constructive eviction can be devilishly difficult to determine in the real world. In litigation, determining when interference crosses over the line to constructive eviction is intensely fact-sensitive and resists sweeping generalizations.iii
For instance, Utah courts have held that tenants have been constructively evicted when they have been subjected to continual harassment or insults by the landlord or the landlord’s agent,iv prevented or impaired in their access to the leased premises during operating hours,v or when a landlord fails to provide an operable elevator (or other essential commercial amenities) necessary for a tenant’s business operations.vi By contrast, claims of “discomfort” or “inconvenience” have been rejected as a basis for constructive eviction.vii The same goes for claims that a landlord wrongfully served a three-day notice to pay or quit.viii
Generally, constructive eviction is an affirmative defense made in response to a landlord’s lawsuit for nonpayment of rent.ix It is not, as is commonly supposed, a basis for a tenant’s premature abandonment of the premises. In other words, the defense is raised after the tenant has vacated as a result of being effectively “evicted.”x Further, the defense requires the tenant to actually abandon the premises and do so within a “reasonable time” after the alleged interference.xi A tenant cannot stay in possession and simply refuse to pay rent on the basis of constructive eviction.xii
The key consideration in preparing for, and responding to, a claim of constructive eviction is keeping good records. A tenant claiming constructive evicting likely must prove that the issue was raised in a timely manner and, despite multiple entreaties, was never resolved.xiii As such, it is critical that landlords acknowledge tenant complaints as well as document in writing their efforts to ameliorate those complaints. While a landlord does not carry the burden of proof for constructive eviction, detailed documentation can thwart a tenant’s claim that a landlord has been inattentive or unwilling to address the tenant’s concerns.
Detailed records are also useful in disputes where a tenant claims substantial interference. “The whole point of constructive eviction is that the landlord basically drove the tenant out through the landlord’s action or inaction.”xiv As such, a landlord that is unable to document the steps taken in response to complaints will be grossly disadvantaged whereas the tenant, which had control and knowledge of the premises, will have a much easier time describing how the alleged interference deprived them of enjoying the premises.
Even with meticulous records, however, owners and managers may still face claims of construction eviction. In such instances, counsel should be retained to properly advise on compiling, preserving, and employing the evidence necessary to refute the tenant’s claims.
i Gray v. Oxford Worldwide Grp., Inc., 139 P.3d 267, 269 (Utah Ct. App. 2006).
ii Gray, 139 P.3d at 270 (citing Neslen, 254 P.2d at 850) (internal formatting omitted).
iii See Gray, 139 P.3d at 269–70 (citing Thirteenth & Washington Sts. Corp. v. Neslen, 254 P.2d 847, 850 (Utah 1953)); Brugger v. Fonoti, 645 P.2d 647, 648 (Utah 1982).
iv See Gray, 139 P.3d at 270–71.
v Thirteenth & Washington Sts. Corp. v. Neslen, 254 P.2d 847 (Utah 1953).
vi See Richard Barton Enterprises, Inc. v. Tsern, 928 P.2d 368, 375, 378 (Utah 1996) (citing Union City Union Suit Co. v. Miller, 162 A.D.2d 101, 556 N.Y.S.2d 864 (1990)).
vii See Myrah v. Campbell, 163 P.3d 679, 682–84 (Utah Ct. App. 2007).
viii Barton v. MTB Enterprises, 889 P.2d 476, 477 (Utah Ct. App. 1995); see also Brugger, 645 P.2d at 648 (stating that the tenant’s complaints revolved around standard problems commonly associated with building maintenance and did not rise to the level of substantial interference); viv Reid v. Mutual of Omaha Ins. Co., 776 P.2d 896, 898–900 (Utah 1989) (upholding trial court’s findings of fact concerning insufficiency of disruption so as to justify claim for constructive eviction).
ix See Kenyon v. Regan, 826 P.2d 140, 142 (Utah Ct. App. 1992).
x See Kenyon, 826 P.2d at 142.
xi See Kenyon, 826 P.2d at 142; see also Barton v. MTB Enterprises, Inc., 889 P.2d 476, 477 (Utah Ct. App. 1995); Brugger, 645 P.2d at 648.
xii See Kenyon, 826 P.2d at 142 (citing Fernandez v. Purdue, 518 P.2d 684, 686 (Utah 1974)).
xiii See Brugger, 645 P.2d at 648 (noting that while the tenant had raised legitimate issues concerning state of the premises, the landorld had taken steps to remedy the problems within a reasonable time) (citing 49 Am.Jur.2d, Landlord and Tenant, § 617).
xiv Barton, 889 P.2d at 477.
Reprinted courtesy of
Ben T. Welch, Snell & Wilmer and
Ken Brown, Snell & Wilmer
Mr. Welch may be contacted at bwelch@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
How to Lose Your Contractor’s License in 90 Days (or Less): California and Louisiana
November 15, 2021 —
Rafael Boza - Gravel2Gavel Construction & Real Estate Law BlogHaving your Contractor’s License up and running to perform work when needed, where needed, is an indispensable compliance matter that contractors face every year. However, this indispensable process may also be cumbersome and time consuming. Knowing the regulations applicable to your business in each state and what to do, how to do it, and when to do it, is of critical importance to maintain compliance and your ability to work in different states.
In this post we will do a high-level review of reporting obligations in California and Louisiana.
California’s
Contractors’ State License Law, Bus. & Prof. Code §§ 7000 et seq., requires licensees to report various information to the Contractors State License Board (CSLB) “within 90 days” of the effective date or event. Louisiana State
Licensing Laws and Regulations, R.S. §§ 37:24 et seq. and La. Admin. Code tit. 46, XXIX, §§ 101 et seq. also require similar reporting to the Louisiana State Licensing Board for Contractors (LSLBC), sometimes “within 15 days” of the event.
Read the court decisionRead the full story...Reprinted courtesy of
Rafael Boza, PillsburyMr. Boza may be contacted at
rafael.boza@pillsburylaw.com
How VR and AR Will Help in Remote Expert Assistance
June 10, 2019 —
Aarni Heiskanen - AEC BusinessThe speed and quality of maintenance and repair are critical in the modern, technology-packed built environment. Consequently, these were considered in an experimental project that tested how remote expert assistance using VR and AR technologies could help improve the productivity of field service.
I’m in a hall overlooking white mountain tops. It’s snowing. In front of me stands an avatar that explains to me what we can do together in this virtual space. He jumps away but I can still hear his voice from behind me. He fetches a chair and hands it to me. I grab it and inspect it. The next moment, a video starts playing on the wall. Later, my host shows me how to draw in three dimensions, how to make sticky notes, how to share a PC desktop, and how to use other collaboration tools.
This experience took place at FAKE Production, a Helsinki-based digital image, animation, and VR/AR studio. With VR glasses and hand-held controllers, I had tried out Glue, their universal collaboration platform. This is a soon-to-be-released service that you can use with VR/AR gear and on mobile and desktop devices.
Glue is also one of the solutions tested in an experimental project called Expert assistance using VR and AR glasses. In this project, Sovelto, a Finnish educational company, wanted to explore the possibilities of using VR and AR solutions for field service. Over ten organizations took part in the project, which received funding from KIRA-digi, the national built environment digitalization program.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
LAX Construction Defect Suit May Run into Statute of Limitations
December 30, 2013 —
CDJ STAFFCurrent arguments over the claims made by LAX that Runway 25L was built in a defective manner by Tutor-Saliba/O&G Industries are hinging over whether the airport knew the runway was defective less than four years after the construction was completed. The runway was built almost five years ago, and Tutor-Saliba is claiming that Los Angeles World Airports has delayed too long in making a construction defect complaint. Tutor-Saliba is not conceding that the runway is defective, only that if it were, the airport would have known it earlier.
Los Angeles World Airports, which operates LAX, is not commenting on the matter, but Robert Span, an aviation attorney at Steinbrecher & Span, told the Daily Breeze that while “there is a four year statute of limitations for dealing with construction defects, but that’s for what they called patent defects,” and that “there’s a 10-year statute of limitations for construction projects where the defect that is alleged is called latent — something that would not be readily apparent.”
Tim Pierce, a construction attorney at K&L Gates LLP described it as “a common defense,” though he said it is “raised in most cases and only works in some.”
Read the court decisionRead the full story...Reprinted courtesy of