Wait! Don’t Sign Yet: Reviewing Contract Protections During the COVID Pandemic
April 13, 2020 —
Danielle S. Ward - Balestreri Potocki & HolmesAs the circumstances of the COVID pandemic change day by day, and we all rush to keep business moving where and when we can, companies should consider hitting the “pause button” before renewing or executing any new contracts. Developing contracts often takes considerable time and expense, and companies are not in the habit of reworking them often. A change in law may prompt a company to revisit their contract terms, but otherwise business is often carried out with a standard form contract for a period of years. With the COVID pandemic affecting nearly every business and industry, life is not business as usual, and companies should make sure their contracts consider what previously seemed like an unforeseeable event.
Force Majeure clauses are included in many contracts to excuse contract performance when made impossible by some unforeseen circumstance. These clauses typically fall under two categories: general and specific. General force majeure clauses excuse performance if performance is prevented by circumstances outside the parties’ control. By contrast, specific force majeure clauses detail the exhaustive list of circumstances (acts of god, extreme weather, war, riot, terrorism, embargoes) which would excuse contract performance. Force majeure clauses are typically interpreted narrowly. If your contract has a specific clause and pandemic or virus is not one of the listed circumstances it may not apply. Whether a particular existing contract covers the ongoing COVID pandemic will vary depending on the language of the contract.
Force majeure clauses previously made headlines when the great economic recession hit in 2008. A number of courts held that simple economic hardship was not enough to invoke force majeure. The inability to pay or lack of desire to pay for the contracted goods or services did not qualify as force majeure. In California, impossibility turns on the nature of the contractual performance, and not in the inability of the obligor to do it. (Kennedy v. Reece (1964) 225 Cal. App. 2d 717, 725.) In other words, the task is objectively impossible not merely impossible or more burdensome to the specific contracting party.
California has codified “force majeure” protection where the parties haven’t included any language or the circumstances in the clause don’t apply to the situation at hand. Civil Code section 1511 excuses performance when “prevented or delayed by an irresistible, superhuman cause, or by the act of public enemies of this state or of the United States, unless the parties have expressly agreed to the contrary.” (Civ. Code § 1511.) What qualifies as a “superhuman cause”? In California, the test is whether under the particular circumstances there was such an insuperable interference occurring without the party's intervention as could not have been prevented by the exercise of prudence, diligence and care. (Pacific Vegetable Oil Corp. v. C. S. T., Ltd. (1946) 29 Cal.2d 228, 238.)
If you find yourself in an existing contract without a force majeure clause, or the statute does not apply, you may consider the doctrine of frustration of purpose. This doctrine is applied narrowly where performance remains possible, but the fundamental reason the parties entered into the contract has been severely or substantially frustrated by an unanticipated supervening circumstance, thus destroying substantially the value of the contract. (Cutter Laboratories, Inc. v. Twining (1963) 221 Cal. App. 2d 302, 314-15.) In other words, performance is still possible but valueless. Note this defense is not likely to apply where the contract has simply become less profitable for one party.
Now that COVID is no longer an unforeseeable event, but rather a current and grave reality, a party executing a contract today without adequate protections may have a difficult time proving unforeseeability. Scientists are not sure whether warm weather will suppress the spread of the virus, as it does with the seasonal flu, but to the extent we get a reprieve during the summer we may see a resurgence of cases this Fall or Winter. Companies should take care in reviewing force majeure clauses, and other clauses tied to timely performance such as delay and liquidated damages before renewing or executing new contracts.
Your contract scenario may vary from the summary provided above. Please contact legal counsel before making any decisions. During this critical time, BPH’s attorneys can be reached via email to answer your questions.
Read the court decisionRead the full story...Reprinted courtesy of
Danielle S. Ward, Balestreri Potocki & HolmesMs. Ward may be contacted at
dward@bph-law.com
July Sees Big Drop in Home Sales
August 27, 2013 —
CDJ STAFFThe Commerce Department reported a 13.9 percent drop in sale of new homes for July. Over the course of the last 12 months, home sales had risen 7 percent. According to economists, an annual rate of about 700,000 homes would be a sign of a healthy economy. The July sales fell well short of that, at an annual rate of 394,000. New home starts were also down.
Experts attribute the decline in sales and building to increases in mortgage rates, even though the rates remain historically low. Despite the slump in home sales in July, builder confidence rose to a high in August.
Read the court decisionRead the full story...Reprinted courtesy of
When Are General Conditions and General Requirements Covered by Builder's Risk
December 18, 2022 —
Michael V. Pepe & Grace V. Hebbel - Saxe Doernberger & VitaGeneral conditions and general requirements are terms of art in the construction industry that describe the indirect costs necessary to complete a construction project. After physical loss or damage to a project, the following question often arises: Are “general conditions” and “general requirements” covered under a builder’s risk policy?
General Conditions vs. General Requirements
General conditions are usually described as the cost of managing a construction project. Examples include salaries for personnel like project managers, supervisors, engineers, field office staff, as well as the cost of field trailers, office equipment and supplies, and anything necessary to support the staff.
General requirements are the non-management indirect costs of executing the project, including items such as pre-development costs, permits, security, dumpsters, fences, temporary lighting, worker amenities, and clean-up costs.
Reprinted courtesy of
Michael V. Pepe, Saxe Doernberger & Vita and
Grace V. Hebbel, Saxe Doernberger & Vita
Mr. Pepe may be contacted at MPepe@sdvlaw.com
Ms. Hebbel may be contacted at GHebbel@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to Partner Alex Giannetto for Being Named to San Diego Business Journal’s Top 100 Leaders in Law List
December 03, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to Partner Alexander Giannetto for being selected as a “2024 Leaders of Influence in Law” by the San Diego Business Journal! To read and download the SDBJ publication, please click
here.
Alex Giannetto is a managing partner with Bremer, Whyte, Brown & O’Meara LLP’s San Diego office. He has extensive experience in all aspects of civil litigation handling liability matters including slip and falls, catastrophic injuries, wrongful death, traumatic brain injuries, landslides, and construction claims. He has obtained favorable trial results defending clients on personal injury and premises matters in San Diego and Los Angeles. He also has appellate experience. He is an AV-rated attorney by Martindale-Hubbell who has been voted Best of the Bar in San Diego as well as a Top Lawyer in San Diego.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Florida extends the Distressed Condominium Relief Act
June 17, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Distressed Condominium Relief Act had been poised to expire on July 1st, but has now been extended by two additional years by the Florida legislature, the National Review reported. The act was Part VII of the Condominium Act in 2010, and has been previously extended twice. According to the National Review, “This Legislation attempted to allay the fears of potential investors about incurring developer liability in connection with the purchase of bulk units. The Act created a shield in favor of bulk purchasers from such potential liability, especially construction defects liability.”
Read the court decisionRead the full story...Reprinted courtesy of
Fee Simple!
November 11, 2024 —
Daniel Lund III - LexologyFollowing the grant of summary judgment by a Nebraska federal court on a construction claim, the prevailing subcontractor sought recovery of attorney’s fees, but received pushback from its opponent based upon the Federal Rules of Civil Procedure.
The general contractor urged “that attorney’s fees are ‘special damages’ that must be specifically pleaded within a complaint under Federal Rule of Civil Procedure 9(g).” The GC said that a prayer for “a judgment for… costs, interest, and attorney’s fees be entered” – without further asserting a statutory or factual basis for the recovery – is insufficient. The subcontractor shot back that “it complied with the requirements of Rule 9(g) because its prayer for relief expressly referenced attorney’s fees, and the request for such fees was based on the facts asserted in the pleadings themselves.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Collapse Claim Dismissed
December 04, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe complaint alleged collapse, but the claimed cause of the collapse was not a covered cause under the insured's policy, mandating a dismissal of the complaint. Coonce v. CSSA Fire & Cas. Ins. Co., 2018 U.S. App. LEXIS 25010 (10th Cir. Sept. 4, 2018).
The ceiling in the insured's living and dining areas caved in. An engineering survey determined that the nails used in the construction had failed to hold. The insured made a claim on her policy issued by CSAA. Coverage was denied and the insured sued.
The insured was given two opportunities to amend her complaint by the district court, but the motion to dismiss for failure to state a claim was eventually granted.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Jury Awards Aluminum Company 35 Million in Time Element Losses
September 23, 2019 —
Michael S. Levine & Daniel Hentschel - Hunton Insurance Recovery BlogOn July 3, 2019, a Delaware jury determined that fourteen property insurers for Noranda Aluminum Holding Corp., an aluminum producer that filed for bankruptcy and ceased operations three years ago, owe Noranda over $35 million in time element losses that Noranda sustained as a result of two separate catastrophic incidents that occurred at its aluminum facility in 2015 and 2016.
In August 2015, an aluminum explosion occurred at Noranda’s facility, resulting in substantial property damage and bodily injuries. Though the insurers paid for Noranda’s property damage claim, the insurers only covered $5.64 million of Noranda’s $22 million time element claim. In January 2016, the same facility sustained significant damage as a result of equipment failure. The insurers again paid for Noranda’s property damage claim arising from the equipment failure but declined to pay any of its $22.8 million time element claim.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews & Kurth and
Daniel Hentschel, Hunton Andrews & Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of