Working Safely With Silica: Health Hazards and OSHA Compliance
January 17, 2022 —
Rick Pedley - Construction ExecutiveAbout 2.3 million American workers are exposed to silica, including those in construction, oil and gas, agriculture and manufacturing. Silica is commonly found in a range of construction materials and when this material breaks apart, small particles are released into the air, creating what’s known as respirable crystalline silica. These particles can get into a person’s respiratory tract, which can lead to a range of serious and potentially fatal illnesses including silicosis, lung cancer, chronic obstructive pulmonary disease and kidney diseases.
The Occupational Safety and Health Administration has set clear regulations for working with this substance, so construction workers and managers can know the risks of inhaling this substance and protect themselves on the job site.
What is Silica?
Crystalline silica is a mineral that forms naturally in the earth. Raw construction materials such as sand, stone, concrete and mortar often contain deposits of crystalline silica, which can put employees at risk. Silica becomes a danger to workers when it is released into the air and breathed in.
Reprinted courtesy of
Rick Pedley, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
McDermott International and BP Team Arbitrate $535M LNG Site Dispute
April 02, 2024 —
Mary B. Powers - Engineering News-RecordBP and Kosmos Energy are seeking “maximum recoverable damages” of about $535 million in binding arbitration with contractor McDermott International over a claim that it failed to meet contract obligations on subsea pipeline installation for an estimated $4.8 billion liquefied natural gas project off Africa.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Connecticut Court Clarifies Construction Coverage
June 28, 2013 —
CDJ STAFFThe Connecticut Supreme Court has recently ruled on a case in which breach of contract and bad-faith claims were made against an insurer in an construction defect case. Joseph K. Scully of Day Pitney LLP discussed the case in a piece on Mondaq.
Mr. Scully noted that the background of the case was that Capstone Building was the general contractor and project developer of a student housing complex for the University of Connecticut. Unfortunately, the building had a variety of problems, some of which were violations of the building code. Mr. Scully noted that the building had “elevated carbon monoxide levels resulting from inadequate venting, improperly sized flues.” Capstone entered into mediation with the University of Connecticut. Capstone’s insurer, the American Motorists Insurance Company (AMICO), declined involvement in the participation. Afterward, Capstone sued AMICO. The issues the court covered involved the insurance on this project.
The court addressed three questions. The first was “whether damage to a construction project caused by construction defects and faulty workmanship may constitute ‘property damage’ resulting from an ‘occurrence.’” The court concluded that it could “only if it involved physical injury or loss of use of ‘nondefective property.’”
The second question dealt with whether insurers were obligated to investigate insurance claims. The court, “agreeing with the majority of jurisdictions,” did not find “a cause of action based solely on an insurer’s failure to investigate a claim.” Under the terms of the contract, it was up to AMICO to decide if it was going to investigate the claim.
Thirdly, the court examined whether “an insured is entitled to recover the full amount of a pre-suit settlement involving both covered and noncovered claims after an insurer wrongfully disclaims coverage.” The court concluded that the limits are that the settlement be reasonable, the policy limit, and the covered claims.
Mr. Scully concludes that the decision will limit “the scope of coverage for construction defect claims” and “also imposes reasonable requirements on an insured to allocate a settlement between covered and noncovered claims.
Read the court decisionRead the full story...Reprinted courtesy of
Second Circuit Upholds Constitutionality of NY’s Zero Emissions Credit Program
November 21, 2018 —
Anthony B. Cavender - Gravel2GavelOn September 27, the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s ruling that the “Zero Emissions Credit” (ZEC) program of the New York Public Service Commission is not unconstitutional. The case is Coalition for Competitive Electricity, et al. v. Zibelman, Chair of the New York Public Service Commission, et al.
In effect, the ZEC program provides subsidies to qualifying New York nuclear power plants as a way to reduce greenhouse gas emissions. The ZEC program is intended to prevent nuclear plants from being prematurely retired from generating power until suitable replacement facilities are operating.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Price Escalation Impacts
August 22, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogThis Bulletin provides guidance to contractors, subcontractors, suppliers, and others to ensure compliance with contractual change order requirements in the event work on a construction project is impacted by price escalation.
Construction projects are being impacted by increased costs for most construction materials. The Producer Price Index shows a 69% increase in the cost of construction materials from March 2020 to March 2022. Many construction contracts do not address escalation or specifically exclude change orders for material escalation, leaving the risk of escalation of construction materials with the contractor, subcontractor, or suppliers.
Bid Protection Tips:
- Keep bids open for less than 30 days with a designated sunset date:
- Keeping your bids open for less than 30 days can help protect you from sudden changes in pricing and help maintain your bids’ competitive status.
- If asked to extend time a bid is open, reconfirm prices before agreeing.
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at
dmotta@grsm.com
Cracked Girders Trigger Scrutiny of Salesforce Transit Center's Entire Structure
November 21, 2018 —
Nadine M. Post - Engineering News-RecordNov. 15, 2018 Update:
After calling on Nov. 8 for a “complete structural evaluation” of San Francisco's 1.2-million-sq-ft SalesForce Transit Center, following the discovery on Sept. 25 of significant, mid-span cracks in the bottom flanges of twin parallel girders spanning 80 ft over Fremont Street, the Transbay Joint Powers Authority now says the problems with girders are localized.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, ENRMs. Post may be contacted at
postn@enr.com
Anti-Assignment Provision Unenforceable in Kentucky
December 20, 2012 —
TRED EYERLY, INSURANCE LAW HAWAIIOn a certified question from the Federal District Court, the Supreme Court of Kentucky decided that an anti-assignment provision in a policy is unenforceable.
Wehr Constructors v. Paducah Div. Assur. Co. of Am., 2012 Ky. LEXIS 183 (Ky. Oct. 25, 2012).
Before building an addition to its hospital, Murray Calloway County Hospital purchased a builder's risk policy from Assurance Company of America.The policy provided, "Your rights and duties under this policy may not be transferred without Assurance's written consent . . . ." The Hospital contracted with Wehr Constructors to install concrete subsurfaces and vinyl floors in order to expand the hospital. After installation, a portion of the floors and subsurface work was damaged. The Hospital submitted a claim to Assurance for $75,000, but the claim was denied.
Wehr sued the Hospital to recover money for its work on the construction project. In settling the case, the Hospital assigned to Wehr any claim or rights the Hospital had against Assurance.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law Hawaii.Mr. Eyerly can be contacted at
te@hawaiilawyer.com
Toolbox Talk Series Recap - Guided Choice Mediation
November 05, 2024 —
Douglas J. Mackin - The Dispute ResolverIn the September 26, 2024 edition of Division 1's Toolbox Talk Series,
Clifford Shapiro presented on Guided Choice Mediation (“GCM”) and how it can lead to better outcomes in construction disputes.
GCM is an approach to mediation that focuses on early and efficient dispute resolution, which prominent mediators created as a public interest project.
Shapiro described his particular variant of GCM based on his experience while acknowledging that other Guided Choice Mediators’ processes may differ from his in various ways. Shapiro’s brand of GCM focuses on ensuring that parties have reasonable expectations and appropriate settlement authority prior to arriving at a mediation. Some of the strategies to help accomplish these noble goals are (i) early mediator engagement, (ii) mediator facilitation of information exchange, (iii) mediator involvement with insurance issues (particularly important in construction defect cases, especially those with multiple defendants), (iii) pre-mediation ex parte meetings, and (iv) mediator participation in risk analysis. These strategies are not typical in the more traditional/historic approach to mediation in which mediation is scheduled based on a scheduling order, mediation statements are sent to the mediator roughly a week before the scheduled mediation (and sometimes not even shared with anyone other than the mediator), and the parties speak with the mediator for the first time on the day of the mediation.
Read the court decisionRead the full story...Reprinted courtesy of
Douglas J. Mackin, Cozen O’ConnorMr. Mackin may be contacted at