How to Determine the Deadline for Recording a California Mechanics Lien
September 17, 2015 —
William L. Porter, Esq. – Porter Law Group BulletinThe California Mechanics Lien is one of the most valuable collection devices available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California private works construction project. The mechanics lien allows the claimant to sell the property where the work was performed in order to obtain payment. As noted below, in order to pursue this remedy, certain deadlines must be met.
Know Your Mechanics Lien Filing Deadlines Generally
Working within deadlines is absolutely crucial to preserving mechanics lien rights under California law. The deadlines differ, depending on whether you are a ”direct” contractor, also known as “original” or “prime” contractor (one who contracts directly with the property owner) or a subcontractor or material supplier. The primary differences are that the direct contractor is only required to serve the “Preliminary Notice” on the Construction Lender (Civil Code section 8200-8216), whereas the subcontractor and material supplier must serve not only the Construction Lender, but also the Owner and Direct Contractor (see Civil Code section 8200(e)). Another difference is that a direct contractor has a longer period of time in which to record a mechanics lien after a valid “notice of completion” or a “notice of cessation” has been recorded (Civil Code sections 8180-8190), (60 days for original contractors as compared to 30 days for subcontractors and suppliers – See Civil Code sections 8412 and 8414).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, The Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
No Bad Faith In Filing Interpleader
August 19, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Eighth Circuit determined that filing an interpleader action in the face of multiple claims against the policy holder did not constitute bad faith. Purscell v. Tico Ins. Co., 2015 U.S. App. LEXIS 10438 (8th Cir. June 22, 2015).
Ben Purscell's vehicle collided with another vehicle, in which Tim and Amy Carr were riding. The Carrs were injured, and Purscell's passenger, Amy Priesendorf, was killed. Before the accident, Priesendorf had stretched her leg over and put her foot on the accelerator, on top of Purscell's foot. As the other car approached, Purscell swerved to avoid an accident, but the two vehicles collided.
Purscell had a policy with Infinity Assurance Insurance Company. The policy limited liability to $25,000 per person and $50,000 per accident for bodily injury. Infinity put the full $50,000 per accident limits on reserve, with $25,000 designated to Priesendorf's fatality and $25,000 designated to the Carrs.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Connecticut Reverses Course for Construction Managers on School Projects
August 05, 2024 —
Anand Gupta - Construction Law Zone BlogOn June 6, 2024, Connecticut Governor Ned Lamont signed into law Public Act 24-151 (H.B. 5524) (Bill 5524). Bill 5524 authorized and adjusted bonds of the state and provisions related to state and municipal tax administration, as well as addressed school building projects. Notably, Bill 5524 removed the ban on construction managers self-performing work on public school construction projects, effective July 1, 2024. Allowing construction managers to self-perform certain portions of the work, such as general trades, subject to the standard bidding requirements, is a common industry practice that, theoretically, reduces total project costs by reducing the amount of subcontracted work. However, proponents of banning self-performance argue that construction managers have too much information to bid fairly and competitively.
Reprinted courtesy of
Anand Gupta, Robinson+Cole
Mr. Gupta may be contacted at agupta@rc.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Substitute Materials — What Are Your Duties? What Are Your Risks? (Law Note)
June 27, 2022 —
Melissa Dewey Brumback - Construction Law in North CarolinaIn managing a project as the design professional, you are called upon to wear many hats. One of those hats is that of material specifier and, at times, substitute material approver. What are your duties in looking at substitute materials?
As always, the legal answer is “it depends”. In part, it will depend on your role on the project and what, specifically, the contract says. However, at its most basic, you can be sued for accepting an out of spec substitute material. This is so even if you believed the spec met requirements based on information that the contractor gave you. So, tread carefully in this area.
Do not assume any information that the contractor presents to you– take the time to research for yourself, call the manufacturer, and otherwise ensure that the product will work.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Timely Written Notice to Insurer and Cooperating with Insurer
June 21, 2017 —
David Adelstein - Florida Construction Legal UpdatesI harp on notifying a liability insurer in writing once a claim is asserted against you. As soon as possible. I harp on this because as an insured you want to remove any doubt or argument that the insurer was prejudiced due to a lack of timely notice.
In a recent opinion, Zurich American Insurance Co. v. European Tile and Floors, Inc., 2017 WL 2427172 (M.D.Fla. 2017), the insurer moved for summary judgment in a coverage action arguing that its insured failed to provide it timely written notice. Specifically, the insurer argued that the insured violated the clause in the liability policy that states:
2. Duties in the Event of Occurrence, Offense, Claim or Suit
b. If a claim is made or “suit” is brought against any insured, you must:
- Immediately record the specifics of the claim or “suit” and the date received; and
- Notify us as soon as practicable.
You must see to it that we receive written notice of the claim or “suit” as soon as practicable.
c. You and any other insured must:
- Immediately send us copies of any demands, notices, summonses or legal papers received in connection with the claim or “suit”;
- Authorize us to obtain records and other information;
- Cooperate with us in the investigation, settlement or defense of the claim or “suit”; and
- Assist us, upon our request, in the enforcement of any right against any person or organization which may be liable to the insured because of injury or damage to which this insurance may also apply.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Equipment Costs? It’s a Steal!
July 08, 2011 —
CDJ STAFFKCBD reports on the problems of a Lubbock, Texas contractor. It’s hard to do the job when your tools keep getting stolen. Corey Meadows, owner of Top Cut Interiors, told KCBD that he had chained an air compressor to a table saw. Since the thieves couldn’t cut the chain, they cut the table saw “and just took the air compressor and the chain.” Meadows estimates the thieves cost him $2,000 in damaged or stolen equipment and time lost.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Close Enough Only Counts in Horseshoes and Hand Grenades
March 08, 2021 —
Garret Murai - California Construction Law BlogIn
State Farm General Insurance Company v. Oetiker, Inc., Case No. B302348 (December 18, 2020), a manufacturer sued in subrogation action under the Right to Repair Act almost got away. Almost.
The Oetiker Case
James and Jennifer Philson’s home was substantially completed, and a notice of completion was recorded, in 2004. In 2016, the Philsons tendered a claim to their homeowner’s insurance carrier, State Farm General Insurance Company, after their home experienced significant water damage due to a defective stainless steel ear clamp.
In 2018, after paying the Philson’s claim, State Farm filed a subrogation action against the manufacturer of the ear clamp, Oetiker, Inc. State Farm’s complaint, which included causes of action for negligence, strict products liability and breach of implied warranty, alleged that the home was “damaged by a water leak from the failure of a defective stainless steel ear claim on a water PEX fitting” and that the ear clamp was “defective when it left the control of [Oetiker].”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Worker’s Compensation Exclusivity Rule Gets “Trumped” by Indemnity Provision
October 27, 2016 —
Garret Murai – California Construction Law BlogSorry, I couldn’t help myself with the title.
The next case, Aluma Systems Concrete Construction of California v. Nibbi Bros., Inc., California Court of Appeals for the First District, Case No. A145734 (August 16, 2016), discusses the interplay between indemnity provisions and the worker’s compensation exclusivity rule.
The worker’s compensation exclusivity rule generally provides that worker’s compensation insurance is the exclusive remedy of employees for injuries or death arising out of the course and scope of their employment.
In the Aluma case, the California Court of Appeals, addressed what happens when a subcontractor’s employees are injured on a project, sue the general contractor, and the general contractor, pursuant to an indemnity provision in its subcontract, tenders the claim to the subcontractor whose worker’s compensation insurance has already paid the employees.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at