Providence Partner Monica R. Nelson Helps Union Carbide Secure Defense Verdict in 1st Rhode Island Asbestos Trial in Nearly 40 Years
December 31, 2024 —
Lewis Brisbois NewsroomProvidence, R.I. (November 22, 2024) - On November 21, 2024, a Providence County jury returned a unanimous defense verdict for Union Carbide Corporation after a nine-day trial presided over by Associate Justice Richard A. Licht. Tim McGowan of Kelley Jasons McGowan Spinelli Hanna & Reber LLP, Eric Cook of Willcox Savage, and Monica R. Nelson of Lewis Brisbois Bisgaard & Smith LLP represented Union Carbide at trial. Elliott Davis of Shook Hardy & Bacon was Union Carbide’s appellate counsel.
The plaintiffs’ lawyers, Vincent L. Greene IV, Nathan D. Finch, and Ashley Hornstein of Motley Rice LLC, represented the family of Mrs. Bonnie Bonito in the first asbestos matter to go to trial in Rhode Island in close to 40 years and requested nearly $25 million in compensatory damages for the death of Mrs. Bonito from her alleged exposure to Union Carbide’s asbestos, among many other asbestos-containing products, through the work clothes of her husband. The plaintiffs’ proffered theory of liability against Union Carbide Corporation is known as a “take-home” exposure claim.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Brief Overview of Rights of Unlicensed Contractors in California
September 10, 2014 —
William M. Kaufman – Construction Lawyers BlogUnder California Contractor’s State License Law enumerated in Business and Professions Code Sections 7000 to 7191, a contractor may not “bring or maintain” any action for compensation for performing any act or contract for which a license is required unless the contractor was duly licensed “at all times” during performance. Bus & Prof Code Section 7031(a).
What does this mean and who does it include?
This is a question that often has to be answered on a case by case basis. Basically, California does not want unlicensed contractors to be able to get paid for work that should be performed by a licensed contractor. The law has set forth some general parameters. General contractors, subcontractors, and master developers must be licensed. However, suppliers, manufacturers, laborers and equipment lessors are exempt and do not need a contractor’s license. Essentially, those parties that merely furnish material or supplies without fabricating them into, or consuming them in the performance of work, do not need to be licensed. Bus & Prof Code Section 7052.
There are sever fines and penalties for those who improperly perform construction work without a license. A contract between any contractor and an unlicensed subcontractor is a misdemeanor. Lack of a license bars all actions in law or in equity for collection of compensation for the performance of work requiring a license. There are very few exceptions to this rule. A “savvy” unlicensed contractor cannot simply avoid these requirements by “subbing” out all the work to licensed contractors. Any person who uses the services of an unlicensed contractor may file a court action or cross-complaint to recover all payments made to the unlicensed contractor. In addition, a person who uses the services of an unlicensed contractor is a victim of a crime and eligible for restitution of economic losses regardless of whether that person had knowledge that the contractor was unlicensed. Bus. & Prof Code Sections 7028, 7028.16. It goes without saying that performing work without a license on projects is a bad idea.
Reprinted courtesy of
William M. Kaufman, Lockhart Park LP
Mr. Kaufman may be contacted at wkaufman@lockhartpark.com, and you may visit the firm's website at www.lockhartpark.com
Read the court decisionRead the full story...Reprinted courtesy of
Three Recent Cases Strike Down Liquidated Damages Clauses In Settlement Agreements…A Trend Or An Aberration?
November 01, 2021 —
Adam M. Tuckman - ConsensusDocsBeginning more than one century ago, owners and contractors generally have adopted the convention of including liquidated damages in their contracts to fix potential liability for delay (and other losses) at the inception of the project. The proliferation of liquidated damages clauses in modern contracts can be attributed to economic and legal factors. From the owner’s standpoint, it may be exceedingly difficult to prove the actual cost impact of a delayed completion of the project. A properly calculated liquidated damages rate would save the owner the significant expense of quantifying its delay damages. On the contractor’s side, a reasonable amount of liquidated damages may be preferable to uncapped or unknown liability, allowing the contractor to more accurately price its bid and efficiently allocate risk.
Coinciding with, or perhaps a leading cause of, the industry’s embrace of liquidated damages provisions, was the shift in courts throughout the country from disfavoring such clauses to accepting them (within limits) as an appropriate exercise of contract rights. While some variation exists among the states, courts have generally recognized that liquidated damages clauses are a viable alternative to proof of actual loss so long as (i) actual losses were difficult to quantify, and (ii) the stipulated sum bears a reasonable relationship to the anticipated loss at the time of contracting. See, e.g., Restatement (Second) of Contracts § 356. Conversely, a clause that penalizes the breaching party rather than serving as an estimate of probable loss is likely to be found unenforceable.
Read the court decisionRead the full story...Reprinted courtesy of
Adam M. Tuckman, Watt, Tieder, Hoffar, & Fitzgerald, LLPMr. Tuckman may be contacted at
atuckman@watttieder.com
Client Alert: Court of Appeal Applies Common Interest Privilege Doctrine to HOA Litigation Meetings
March 19, 2014 —
David W. Evans, Steven M. Cvitanovic, and Michael C. Parme - Haight Brown & Bonesteel LLPIn Seahaus La Jolla Owners Assoc. v. Superior Court (No. D064567, March 12, 2014), the California Court of Appeal held a homeowners association’s (“HOA”) litigation meetings related to the HOA’s construction defect lawsuit were subject to protection under the attorney-client privilege. Specifically, the court concluded the common interest doctrine applied to the subject litigation meetings, thereby barring the defendants in the HOA’s lawsuit from seeking discovery related to the content and disclosures made during those meetings.
The plaintiff HOA initiated a construction defect lawsuit against a residential developer and builder, seeking damages for construction defects related to common areas. The defendants took the depositions of individual homeowners and inquired regarding the communications and disclosures made at informational litigation update meetings. The meetings were conducted by the HOA’s counsel with groups of homeowners, some of whom had filed their own, separate lawsuits against the same defendants. Motions to compel were filed after attorney-client privilege objections were asserted by counsel for the HOA. After the court-appointed discovery referee opined that the common interest doctrine applied and that the communications presented at the meetings were subject to the attorney-client privilege, the trial court rejected this recommendation and overruled the HOA’s privilege objections. The HOA filed a petition for a writ of mandate.
The defendants argued the privilege had been waived based on the presence of persons who were not the clients of the HOA’s attorney, that the subject communications were not “confidential communications” and that the individual homeowners and the HOA did not share common interests at the time. After setting forth a comprehensive discussion of the statutory principles underlying the attorney-client privilege and the bases for waiver, as provided in California Evidence Code §§ 912 and 952, and summarizing applicable decisional law, the court specifically analyzed the question of whether the common interest doctrine applied in the context of the disputed HOA litigation meetings. The common interest doctrine protects confidential communications made by counsel to third parties if the third parties are present to further the interest of the client or are those to whom disclosure is reasonably necessary for the transmission of the information or the accomplishment of the purpose for which the lawyer was consulted.
Reprinted courtesy of
David W. Evans,
Steven M. Cvitanovic, and
Michael C. Parme of Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com, Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com, and Mr. Parme may be contacted at mparme@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
11th Circuit Affirms Bad Faith Judgement Against Primary Insurer
July 24, 2023 —
Ashley Kellgren - Traub Lieberman Insurance Law BlogIn American Builders Insurance Co. v. Southern-Owners Ins. Co., 2023 U.S. Dist. LEXIS 15386, No. 21-13496 (11th Cir. June 20, 2023), the Eleventh Circuit affirmed a bad faith judgment against a primary insurer.
On April 1, 2019, Ernest Guthrie fell from a roof, causing him to became paralyzed from the waist down. At the time of the accident, Guthrie was employed by his own subcontracting company and was performing work for Beck Construction. Beck Construction was insured under a general liability policy issued by American Builders and an excess policy issued by Evanston. Each of those policies provided $1 million in liability limits. Guthrie’s company was insured under a policy issued by Southern-Owners, which provided a per occurrence limit of $1 million. Under the Southern-Owners policy, Beck Construction was an additional insured and coverage was provided to Beck Construction on a primary basis.
Read the court decisionRead the full story...Reprinted courtesy of
Ashley Kellgren, Traub LiebermanMs. Kellgren may be contacted at
akellgren@tlsslaw.com
How Finns Cut Construction Lead Times in Half
December 17, 2024 —
Aarni Heiskanen - AEC BusinessRakennustieto organized a Q&A on December 5, 2024, titled “Halving Construction Lead Times—Responsible or Irresponsible?” The discussion focused on speeding up residential construction and renovations.
The experts answering questions were representatives from two Finnish contractors (COfLOW and Fira), a client organization (HOAS), a building materials retailer (STARK), and a research institute.
Can you halve construction lead time without sacrificing quality?
Jaana Matilainen of Rakennustieto asked the panelists whether halving construction time is a realistic goal today, whether they can provide any examples, and if the speed-up has increased or decreased quality.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Attorneys’ Fees Are Available in Arizona Eviction Actions
December 19, 2018 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogThe Arizona Court of Appeals recently held that any successful plaintiff in a forcible detainer action (i.e., an eviction action) may recover an award of its attorneys’ fees and costs incurred at trial under A.R.S. § 12-1178(A). See Bank of New York v. Dodev, 1 CA-CV 17-0652 (Ct. App. Nov. 20, 2018). Prior to this decision, caselaw held that fees were only awardable in actions arising out of the termination of a residential lease. RREEF Mgmt. Co. v. Camex Prods., Inc., 190 Ariz. 75, 945 P.2d 386 (Ct. App. 1997). Changes to the statute, however, rendered the prior caselaw obsolete. Although the holding in Dodev is important, the facts of the case are truly astonishing…and somewhat depressing.
The Facts
In Dodev, Ivaylo Dodev (Dodev) defaulted on his home loan in 2008. He nevertheless “succeeded in remaining on the [p]roperty by filing numerous legal actions that delayed the foreclosure and subsequent trustee’s sale” at least through the date of the opinion—a ten (10) year period.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
OSHA Releases COVID-19 Guidance
June 15, 2020 —
L. Stephen Bowers & Joshua Tumen - White and Williams LLPThe United States Department of Labor’s Occupational Safety and Health Administration (OSHA) ensures safe and healthful working conditions for employees by setting and enforcing standards and by providing training, outreach, education and assistance.
The COVID-19 outbreak has increased demand for N95 filtering face piece respirators (N95 FFRs), limiting availability for workers in healthcare and emergency response. On April 3, 2020, OSHA issued interim guidance for employers to combat the supply shortages of N95 FFRs and to comply with the respiratory protection standard (29 CFR § 1910.134). This guidance will remain in effect until further notice and applies in all industries.
Employers must continue to manage their respiratory protection programs and be mindful of N95 FFR shortages. Specifically, employers should identify and evaluate respiratory hazards in the workplace, and develop and implement written respiratory protection programs. Businesses should reassess their engineering controls, work practices, and administrative controls to identify any changes they can make to decrease the need for N95 FFRs. Some examples provided in the guidance include using portable local exhaust systems or moving operations outdoors. Employers may also consider temporarily suspending non-essential operations, to the extent such operations are not already suspended due to state mandates.
Reprinted courtesy of
L. Stephen Bowers, White and Williams LLP and
Joshua Tumen, White and Williams LLP
Mr. Bowers may be contacted at bowerss@whiteandwilliams.com
Mr. Tumen may be contacted at tumenj@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of