Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday readers are in for a treat. Lance Godard, founder of The Godard Group, has provided marketing and business development solutions to global law firms for nearly 20 years. He has particular expertise developing strategies that allow lawyers to identify client opportunities, communicate their messages, and grow their practices. Lance has been called a “provocative and engaging leader in the legal profession and social media” and was named one of the “20 Twitterers Lawyers should follow on Twitter.” He is the founder of 22 Tweets, live Twitter interviews with practicing lawyers, which provides a forum for lawyers to tell their story using social media.
The market appears to be picking up. Clients are getting back to work. New opportunities can’t be far behind. What are you doing to find them? To make sure they show up on your radar? To put yourself in a position to see those opportunities that do present themselves, and to land the work when you pitch for it? Maybe it’s time for a marketing tune-up.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Filing Motion to Increase Lien Transfer Bond (Before Trial Court Loses Jurisdiction Over Final Judgment)
May 15, 2023 —
David Adelstein - Florida Construction Legal UpdatesIf a construction lien is recorded against real property, the lien can be transferred to a lien transfer bond. This transfers the security or collateral of the construction lien from the real property to the lien transfer bond. The lien transfer bond can be a bond posted by a surety company or it can be cash. This is governed by Florida Statute s. 713.24. The amount of the lien does not dictate the amount of the lien transfer bond. Rather, the lien transfer bond needs to be in the amount of the lien, plus interest on that amount for three years, plus $1,000 or 25% of the amount of the lien (whichever is greater so factor in the 25%) to cover attorney’s fees. Fla. Stat. 713.24(1).
If you are looking to transfer a construction lien to a lien transfer bond, make sure to consult with counsel.
Keep in mind there is a statutory mechanism for a lienor to increase the lien transfer bond to cover attorney’s fees and costs and notice the word “must” in the statute below. Pursuant to Florida Statute s. 713.24(3):
Any party having an interest in such security or the property from which the lien was transferred may at any time, and any number of times, file a complaint in chancery in the circuit court of the county where such security is deposited, or file a motion in a pending action to enforce a lien, for an order to require additional security, reduction of security, change or substitution of sureties, payment of discharge thereof, or any other matter affecting said security. If the court finds that the amount of the deposit or bond in excess of the amount claimed in the claim of lien is insufficient to pay the lienor’s attorney’s fees and court costs incurred in the action to enforce the lien, the court must increase the amount of the cash deposit or lien transfer bond. Nothing in this section shall be construed to vest exclusive jurisdiction in the circuit courts over transfer bond claims for nonpayment of an amount within the monetary jurisdiction of the county courts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Negligent Misrepresentation Claim Does Not Allege Property Damage, Barring Coverage
December 20, 2017 —
Tred Eyerly - Insurance Law Hawaii The Tennessee Court of Appeals reversed the trial court's determination that the seller's alleged negligent misrepresentation regarding the propensity of the property to flood was covered. Erie Ins. Exh. v. Maxwell, 2017 Tenn. App. LEXIS 746 (Tenn. Ct. App. Nov. 15, 2017).
The Chapmans purchased a residence from the Maxwells on March 7, 2014. Prior to the sale, the Maxwells completed a residential property disclosure in which they allegedly misrepresented the propensity of the property to flood. Five months after the purchase, the residence sustained damage as a result of two floods within three days. The Chapmans sued, alleging they relied on the Maxwells' representations regarding the propensity of the property to flood. The Chapmans further alleged that they sustained property damage as a result of the Maxwells' negligence and negligent misrepresentations.
Read the court decisionRead the full story...Reprinted courtesy of
Tred Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Limiting Services Can Lead to Increased Liability
December 16, 2019 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday Musings, we welcome Nick Pacella. Nick is an architect licensed in New York, New Jersey and Connecticut. His practice has spanned several economic swings and he has been able to reposition the eggs in his basket to make the most of each recovery. He is currently focusing on adapting existing commercial buildings to take advantage of materials and processes that promote improved energy efficiency for both the owner and the tenants. For a more colorful rendition of projects you can visit his company’s website.
I remember as a kid when the attendant at gas stations would not only clean your windows but also check the oil level of your vehicle as it was filling up with $0.25 per gallon gas. (I did say that I have seen several economic swings) These services have mostly disappeared, and to no great effect to your car since most cars go much longer between oil changes. Other than a slightly dirtier windshield it hasn’t affected your ability to drive and maintain your car.
This is not so with professional services. Architects used to include many services that are now sourced to others. Project Management, Owner’s Representatives and Program Managers now populate the landscape. In many cases they came to be because architects either did not provide the service their client’s were looking for or they allowed themselves to be put into an adversarial relationship with their clients. They were likened to foxes watching the chicken coop, especially for project management and owners representative services. Client’s have had others buzzing in their ears “are architects really going to look out for my interests above theirs?’” Of course the clients never ask if the new wave will do any better at rallying behind their interests.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Trends in Project Delivery Methods in Construction
April 03, 2023 —
Sarah B. Biser - ConsensusDocsThe three key measures of a construction project’s success are cost, quality, and time (delays). The project delivery method that the owner of the project selects can affect each of these metrics. Project delivery methods in complex construction projects evolve as technology and processes improve. The traditional methods of design-bid-build (DBB), design-build (DB), and construction management (CM) have been the standard for many years. More recently, however, newer methods such as integrated project delivery (IPD), and public-private partnerships (PPP) have gained traction.
Design – Bid – Build (DBB)
Design-bid-build is the oldest, most commonly used method of project delivery. It involves three distinct phases: design, bid/award, and construction. An owner asks a team of professionals, such as architects, engineers, and contractors, to produce design documents that will be used to solicit bids. After the owner evaluates the bids and chooses a contractor, a construction contract is written. While this method is the most familiar and well-understood, it can lead to disputes during the construction process as changes are made to the original plans.
In DBB, the owner bears the risk for funding increased costs attributed to design changes and related delays – thanks to the Spearin Doctrine, which holds that the owner impliedly warrants the information, plans, and specifications that it provides to a general contractor. See 248 U.S. 132 (1918) Although the owner cannot claim against the contractor, it can make a claim against the design firm.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah B. Biser, Fox Rothschild LLP (ConsensusDocs)Ms. Biser may be contacted at
sbiser@foxrothschild.com
Pollution Exclusion Does Not Apply To Concrete Settling Dust
November 28, 2018 —
Tred R. Eyerly - Insurance Law HawaiiApplying Virginia law, the federal district court determined that the pollution exclusion did not bar coverage. Allied Prop. & Cas. Ins. Co. v. Zenith Aviation, Inc., 2018 U.S. Dist. LEXIS 14727 (E.D. Va. Aug. 29, 2018).
Zenith Aviation, Inc. hired Abby Construction Company to install an elevator at its warehouse. A wet saw was used to cut away concrete, but Abby did not use any water with the wet saw. This created a significant amount of concrete dust to leave the warehouse. Surrounding businesses contacted the fire department because they thought the dust was smoke from a fire. The concrete dust settled inside Zenith's building, damaging airplane parts stored in the warehouse.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Attorneys’ Fees and the American Arbitration Association Rule
September 09, 2024 —
Bill Wilson - Construction Law ZoneA common question from clients, when a dispute arises on a construction project, is whether they can recover their attorney’s fees from the other side if they pursue a case and win. More often than not, such fees are not recoverable. As a general rule (commonly known as the “American Rule”), each party to a dispute must bear their own attorney’s fees unless there is some statutory provision or contractual agreement between the parties allowing otherwise. Since most construction disputes involve claims for breach of contract and/or negligence, no realistic statutory provision often allows for attorney’s fees. Many construction contracts do not typically provide a prevailing party the right to collect attorney’s fees from the other side. However, even if the American Rule applies, there may be another path to recovering attorney’s fees if the parties agree to arbitrate their dispute under the American Arbitration Association (AAA) rules.
Reprinted courtesy of
Bill Wilson, Robinson & Cole LLP
Mr. Wilson may be contacted at wwilson@rc.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Employees Versus Independent Contractors
February 23, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPAre the workers you employ on the job site considered employees or independent contractors? This is an important distinction that contractors and subcontractors must understand for many purposes, including federal taxes. The classification of your workers can affect their federal income, social security, and Medicare taxes, and the type of benefits they can receive.
When determining whether workers should be classified as employees or independent contractors, courts generally look at three key factors: behavioral control, financial control, and the relationship of the parties.
Behavior Control
Behavior control concerns the business’s right to direct or control how the worker does its work. A worker is likely to be considered an employee when the business maintains behavior control. Such control can be exercised by giving instructions. This would include instructions on how, when, or where to do the work, what tools or equipment to use, who to hire to help with the work, or where to purchase the supplies to be used. Behavioral control can also occur through training. If the business provides training to tell the worker to do the work in a certain manner then the worker is more likely to be an employee.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at