Resolving Subcontractor Disputes with Pass-Through Claims and Liquidation Agreements
May 13, 2024 —
Stephanie Cooksey - Peckar & Abramson, P.C.Imagine a project where you are unable to reach final completion due to an unresolved subcontractor claim. If the project owner is responsible for the claim, and both the owner and subcontractor are entrenched in their positions, how would you resolve this dispute?
The default option is a three-party lawsuit where the subcontractor sues you in your capacity as general contractor. By denying the claim, you bring the owner into the lawsuit as a liable party to the subcontractor’s claim. This option is efficient from the judicial system’s perspective, as it means one lawsuit instead of two. The subcontractor cannot sue the owner since the two have no contract between them. Thus, the subcontractor’s recourse is limited to suing the contractor. In the three-party lawsuit, you argue that if the subcontractor prevails in its claim against you, the owner is liable. If the owner successfully defends against the claim, the subcontractor takes nothing.
Putting judicial economy aside, it may not make economic sense for contractors to have a lawyer involved in litigating a case where they have no skin in the game. Fortunately, there is a better option than the three-party lawsuit on multi-party construction projects.
Read the court decisionRead the full story...Reprinted courtesy of
Stephanie Cooksey, Peckar & Abramson, P.C.Ms. Cooksey may be contacted at
scooksey@pecklaw.com
Contractor Owed a Defense
November 07, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Illinois Appellate Court reversed the lower court and found that the insured contractor was entitled to a defense for alleged construction defects. Acuity v. M/I Homes of Chicago, LLC, 2022 Ill. App. LEXIS 393 (Ill. Ct. App. Sept. 9, 2022).
The owners association (AOAO) sued M/I Homes for breach of contract and the implied warranty of habitability due to alleged defects. The AOAO alleged that the defects caused physical injury to the townhomes. There was resulting property damage such as damage to other building materials, windows and patio doors, and water damage to the interior of units. M/I Homes requested a defense from Acuity, but the request was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Did the Building Boom Lead to a Boom in Construction Defects?
May 10, 2013 —
CDJ STAFFThe height of the building boom is now almost a decade past but some are saying that the results of the rush to get housing built during the profitable market are still with us. The Wall Street Journal reports on the rise of construction defect lawsuits as these homes have aged, some not too gracefully. One couple thought they were hearing acorns falling on their roof. They were less happy to find that the source of the noises was their house slumping on one end, leading to cracks throughout the house. Their neighbors had similar problems and they are now part of a lawsuit against the builder. The expenses to repair the houses could total millions of dollars.
Some have suggested that during the building boom both building and inspection standards were more lax in order to keep up with the pace of building. Criterium Engineers, a building-inspection firm, estimates that 17% of new homes built in 2006 had at least two significant defect, while only 15% of those built in 2003 fit these criteria. Meanwhile others attribute the rise in construction defect lawsuits to home inspector and construction defect attorneys looking for new territories to exploit.
Read the court decisionRead the full story...Reprinted courtesy of
Hurricane Harvey: Understanding the Insurance Aspects, Immediate Actions for Risk Managers
September 07, 2017 —
Gregory D. Podolak - Saxe Doernberger & Vita, P.C.As it’s been more than 10 years since a major hurricane made landfall in the U.S., Hurricane Harvey will test many risk managers’ insurance programs and response plans. Such disasters are complex, and decisive decision-making could mean the difference between staying in business and closing for good.
In this Alert, SDV’s Gregory Podolak and Frank Russo of Procor outline, in clear language, what risk managers need to know about large-scale natural disasters in order to mitigate risks up front and stay sound once they’ve hit.
Read the court decisionRead the full story...Reprinted courtesy of
Gregory D. Podolak, Saxe Doernberger & Vita, P.C.Mr. Podolak may be contacted at
gdp@sdvlaw.com
Design-Build Contracting: Is the Shine Off the Apple?
March 09, 2020 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCThe design-build delivery method offers many benefits to owners. Among the cited benefits are that projects are generally completed faster, at a lower cost, by allowing innovative approaches through early and continual contractor involvement in the design process. The design contractor serves as a single point of contact responsible for both the design and construction of the project.
The Washington State Department of Transportation (“WSDOT”) utilized the design-build procurement method on the largest project ($2 billion) of its type in the state of Washington: the Highway 99 Tunnel, which was finished almost three years late after the tunnel-boring machine (“Bertha”) broke down six years ago. The sorted tale of the SR-99 Tunnel Project was the source of many of this firm’s blog articles.[1] The State of Washington staunchly maintained that the design-build contract protected its taxpayers from covering the repair costs to the tunnel-boring machine when it broke down in 2013. Bertha did not resume tunneling for almost two years, putting on hold removal of the Alaska Way viaduct and rebuilding of the Seattle Waterfront without an elevated highway.
In December 2013, the contractor for the project, Seattle Tunnel Partners (“STP”), contended that a 110-foot long 8” steel pipe which Bertha hit caused the breakdown. That pipe had been installed for groundwater testing by WSDOT in 2002 during its preliminary engineering for the viaduct replacement project. The project’s Dispute Review Board (“DRB”) composed of three tunneling experts found that the pipe constituted a “differing site condition” for which the State was responsible to disclose to contractors. The Board, whose views were non-binding, did not opine about how much damage the undisclosed pipe cost.[2] In other words, the mere fact that a differing site condition occurred did not establish that there was a causal connection between the damages which STP was seeking (in excess of $600 million) and the differing site condition (the 8” steel pipe which WSDOT lawyers at trial derisively referred to as “nothing more than a toothpick for Bertha’s massive cutter head”). STP maintained that Bertha had made steady progress except for three days immediately after hitting the pipe. It didn’t help the contractors’ case that during the discovery phase of the two-month trial, WSDOT lawyers uncovered documents showing that the contractor’s tunnel workers encountered and logged the pipe before digging began.[3]
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
Arbitration Provisions Are Challenging To Circumvent
May 13, 2019 —
David Adelstein - Florida Construction Legal UpdatesArbitration provisions are enforceable and they are becoming more challenging to circumvent, especially if one of the parties to the arbitration agreement wants to arbitrate a dispute versus litigate a dispute. Remember this when agreeing to an arbitration provision as the forum for dispute resolution in your contract. There is not a one-size-fits-all model when it comes to arbitration provisions and how they are drafted. But, there is a very strong public policy in favor of honoring a contractual arbitration provision because this is what the parties agreed to as the forum to resolve their disputes.
By way of example, in Austin Commercial, L.P. v. L.M.C.C. Specialty Contractors, Inc., 44 Fla.L.Weekly D925a (Fla. 2d DCA 2019), a subcontractor and prime contactor entered into a consultant agreement that contained the following arbitration provision:
Any controversy or claim arising out of or relating to this Agreement or the breach thereof shall be subject to the dispute resolution procedures, if any, set out in the Prime Contract between [Prime Contractor] and the [Owner]. Should the Prime Contract contain no specific requirement for the resolution of disputes or should the [Owner] not be involved in the dispute, any such controversy or claim shall be resolved by arbitration pursuant to the Construction Industry Rules of the American Arbitration Association then prevailing, and judgment upon the award by the Arbitrator(s) shall be entered in any Court having jurisdiction thereof.
The prime contract between the owner and prime contractor did not require arbitration.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Federal Interpleader Dealing with Competing Claims over Undisputed Payable to Subcontractor
September 28, 2017 —
David Adelstein - Florida Construction Legal UpdatesWhat do you do if you are holding undisputed money owed to a subcontractor? Well, you make an effort to pay it or tender it! Right? I am never a fan of a client holding undisputed sums without a legitimate contractual basis.
There are circumstances, however, where the effort to pay an undisputed payable is not so easy. In fact, it is challenging, as in the below case example where the subcontractor filed for an Assignment for the Benefit of Creditors (referred to as an “ABC”). An ABC, in a nutshell, allows an insolvent entity to file an insolvency action in state court governed by state law and choose its assignee (versus a federal bankruptcy action governed by federal law where a trustee is appointed). One major difference is that there is no automatic stay in an ABC as there is in a federal bankruptcy action. Thus, the insolvent entity can still be sued, but, while that entity is in an ABC, there are many creditors that will not be able to enforce a judgment. (See Florida Statute Ch. 727).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Architect, Engineer, and Design Professional Liens in California: A Different Animal than the Mechanics’ Lien
August 15, 2022 —
William L. Porter - Porter Law GroupMost in the construction industry are familiar with the rules governing California mechanics’ liens. They know that the Preliminary Notice of Civil Code Section 8034 and 8200-8216 is an important foundational prerequisite document and that the deadline to record a mechanics’ lien is generally triggered by events occurring at the end of construction, including completion of the work of improvement and/or the recording of the notice of completion or notice of cessation. Most of these rules are found in California Civil Code sections 8160-8494.
While architects, engineers and other design professionals are certainly entitled to pursue a mechanics’ lien at the end of a construction project when they are unpaid for their work, unless they also consider the remedy available to them under the California “design professional lien,” they are missing a powerful opportunity to preserve the right to payment only available to architects, engineers, and design professionals.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at