Do Engineers Owe a Duty to Third Parties?
June 10, 2015 —
Craig Martin – Construction Contractor AdvisorA Texas Court of Appeals, in USA Walnut Creek, DST v. Terracon Consultants, Inc., recently ruled that an engineer owed a duty to the buyer of an apartment complex, even though the engineer had no contractual relationship with the buyer. This is an expansion of the duty professionals owe on construction projects and could signal a change in the law.
In the case, Walnut Creek purchased a three year old apartment complex. A few years after taking possession, Walnut Creek noticed problems with the apartments, including cracking foundations, walls, breaking windows, and out of square door frames. Walnut Creek sued the developer and general contractor, alleging construction defects. The developer claimed that the engineer, Terracon, was at fault and Walnut Creek added Terracon to the lawsuit, asserting that Terracon was negligent in performing engineering services during construction. Terracon asked the court to dismiss the claim, arguing that it did not owe a duty to Walnut Creek. Walnut Creek in turn argued that engineers do owe a duty to subsequent owners. The trial court dismissed the case against the engineer and Walnut Creek appealed.
The appellate court reversed the trial court, finding that the engineer did owe a duty to subsequent purchasers. The court seemed persuaded by the allegations that the engineer actually created the construction defects which were the basis for the litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
The BUILDCHAIN Project Enhances Data Exchange and Transparency in the EU Construction Industry
January 23, 2023 —
Aarni Heiskanen - AEC BusinessTrace Labs, a WEB 3 developer, joins the EU’s efforts to create a smarter and more sustainable built environment with the
BUILDCHAIN project. With its 11 EU partners, Trace Labs aims to improve efficiency, reduce errors, and increase transparency and trust in construction.
Efficient, transparent, and trusted data exchange is a powerful tool for driving sustainability, resilience, and energy efficiency in construction. However, there are several obstacles to trusted data exchange in the industry today:
- Data silos: Construction projects involve multiple parties and stakeholders, each of which may have its systems for storing and sharing information. This can lead to data silos and a lack of coordination, making it difficult to access and trust the data.
- Lack of standardization: Construction projects may use different formats for storing and sharing data, leading to difficulties in comparing and combining information from various projects.
- Data security: Construction projects often involve sensitive information, such as building plans, materials lists, and inspection results. Ensuring this information is secure and protected from unauthorized access can be a significant challenge.
- Lack of incentives: There are often few incentives for construction companies and other stakeholders to share data and collaborate on projects, making establishing trust and transparency challenging.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
City of Birmingham Countersues Contractor for Incomplete Work
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFBack in December of 2013, WVTM News reported that Chris Woods, a contractor, filed a lawsuit against the City of Birmingham, Alabama, demanding $1.5 million for the West Police Precinct and two other projects he had been contracted on. However, “Birmingham claimed Woods was fired for not completing projects on time and other contract breaches.”
On March 7th, WVTM News reported that the City of Birmingham has filed a counterclaim against Woods, alleging that he “owes $1.2 million for incomplete work.” The city listed his “inability to meet specific construction deadlines and finish either project on time as factors for his termination.” Woods, however, blamed the city for delays, citing multiple design changes requested by Birmingham.
The city’s counterclaim also alleged that “Star Insurance Company, ‘identified major, numerous defects in the work that Woods had performed prior to the termination of the West Precinct Project.’”
Read the full story, December 2013 Article...
Read the full story, March 2014 Article... Read the court decisionRead the full story...Reprinted courtesy of
Massachusetts Federal Court Rejects Adria Towers, Finds Construction Defects Not an “Occurrence”
July 03, 2022 —
Eric B. Hermanson & Austin D. Moody - White and WilliamsIn an important ruling for insurers, U.S. District Court Judge Patti Saris found that Massachusetts does not follow the position taken in Cypress Point Condo Association v. Adria Towers, LLC, 226 N.J. 403, 418 (2016), i.e., it does not hold that "faulty workmanship claims [should be recognized] as ... an 'occurrence,' thus triggering coverage, 'so long as the allegedly defective work [was] performed by a subcontractor rather than the policyholder itself."
[1]
Instead, Judge Saris reaffirmed earlier Massachusetts authority holding faulty work is not an "occurrence" for coverage purposes,
[2] and found this authority applied whether or not the work in question was subcontracted.
In the alternative, Judge Saris found, even if a contractor's faulty work could be deemed an an "occurrence," such work did not constitute covered "property damage," because none of the alleged damage was "outside the scope of the work that Tocci was contractually required to fulfill as general contractor."
[3]
Reprinted courtesy of
Eric B. Hermanson, White and Williams and
Austin D. Moody, White and Williams
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Massachusetts Business Court Addresses Defense Cost Allocation and Non-Cumulation Provisions in Long-Tail Context
March 06, 2022 —
Eric B. Hermanson & Austin D. Moody - White and WilliamsA business court in Massachusetts has weighed in on two key issues affecting allocation of insurance coverage for long-tail liabilities in Massachusetts. Specifically, in Crosby Valve LLC et al. v. OneBeacon America Insurance Company, et al.,
[1] involving asbestos bodily injury claims, Judge Kenneth Salinger of the Suffolk County Business Litigation Session addressed:
- whether defense costs in long-tail cases were subject to the same pro rata allocation scheme the Supreme Judicial Court (SJC) adopted to govern successively triggered insurers' indemnity obligations in Boston Gas Company v. Century Indemnity Company;[2] and
- whether “non-cumulation” provisions, like those addressed by the New York Court of Appeals in Matter of Viking Pump,[3] were consistent with this pro rata allocation methodology.
As to the first issue — i.e., allocation of defense costs — Judge Salinger declined to follow Boston Gas, and found the SJC’s holding in that case was limited to an insurers’ indemnity obligations. The SJC in Boston Gas had focused on the language of the policy insuring agreement, saying “[t]his policy applies to ... property damage ... which occurs anywhere during the policy period.” The SJC had also pointed to the policy definition of “occurrence” as “an accident, including injurious exposure to conditions, which results, during the policy period, in property damage neither expected nor intended from the standpoint of the insured.”
[4]
Reprinted courtesy of
Eric B. Hermanson, White and Williams LLP and
Austin D. Moody, White and Williams
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Georgia Federal Court Holds That Pollution Exclusion Bars Coverage Under Liability Policy for Claims Arising From Discharge of PFAS Into Waterways
December 18, 2022 —
Paul Briganti - White and WilliamsOn December 5, 2022, the U.S. District Court for the District of Georgia held that a total pollution exclusion (TPE) in a CGL policy relieved the insurer of any obligation to defend or indemnify a recycling company in a putative class action alleging PFAS contamination of Georgia waterways. See Grange Ins. Co. v. Cycle-Tex Inc., et al., Order, Civ. A. No. 4:21-cv-00147-AT (N.D. Ga. Dec. 5, 2022). The decision adds to a slowly-developing body of case law addressing coverage issues arising out of PFAS-related claims.
In Grange, the insured, Cycle-Tex, Inc., was the operator of a thermoplastics recycling facility in Dalton, Georgia. Cycle-Tex and other defendants – which included chemical suppliers, carpet manufacturers, intermediaries, the City of Dalton and the Dalton-Whitfield Solid Waste Authority – were named in a putative class action complaint alleging that residents of Dalton had been injured as a result of the defendants’ discharge of PFAS into local waterways. The complaint sought damages for: (1) alleged harm to the residents’ health by virtue of ingesting contaminated water; (2) alleged property damage resulting from the contamination of the public water supply; and (3) the payment of surcharges and heightened water rates as a result of the alleged contamination.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Briganti, White and WilliamsMr. Briganti may be contacted at
brigantip@whiteandwilliams.com
FIFA May Reduce World Cup Stadiums in Russia on Economic Concern
July 16, 2014 —
Tariq Panja – BloombergFIFA may reduce the number of stadiums used to host the 2018 World Cup in Russia on concern that their economic viability after the monthlong event ends.
FIFA President Sepp Blatter said a day after Germany’s 1-0 win over Argentina in the final that a delegation from soccer’s governing body will meet Russian tournament organizers in September to discuss plans for the next edition.
Blatter gave a mark of 9.25 out of 10 to an “exceptional” Brazil World Cup, which cost $11 billion to stage. The tournament is a difficult challenge for organizers, Blatter said, illustrated by construction delays at almost all of the 12 arenas used for the 64 games in Brazil.
“The World Cup has taken such a dimension that the organization is hard work for the organizing country and also for FIFA,” Blatter told reporters at Rio de Janeiro’s Maracana stadium, where Germany claimed a fourth title and became the first European country to win the tournament in South America.
Read the court decisionRead the full story...Reprinted courtesy of
Tariq Panja, BloombergMr. Panja may be contacted at
tpanja@bloomberg.net
PFAS and the Challenge of Cleaning Up “Forever”
July 31, 2023 —
PFAS Team - Gravel2Gavel Construction & Real Estate Law BlogFrom a stream of legal challenges, to ever-expanding regulations on things like cosmetics and drinking water, PFAS are the “forever chemicals” keeping companies and consumers on high alert. While industries scramble to remove the synthetic compounds from products, scientists are researching new techniques for scrubbing PFAS from the environment. There is money to be had for those who can find a more streamlined method of purging the substances—the U.S. Army Corps of Engineers has an $800 million contract on the table for the handling, destruction and replacement of PFAS-laden fire-fighting foam—leaving technology companies racing to create solutions. The three main PFAS cleaning techniques currently relied upon can be very effective but are also costly and may leave questionable byproducts in their wake.
The established approaches include:
- Granular Activated Carbon. As one of the most studied treatments for PFAS removal, granular activated carbon is often used in water treatment plants. Large beds of carbon essentially soak up the unwanted chemicals. After the Sweeney Water Plant in North Carolina, whose water source is downstream from a fluorochemical-producing Chemours plant, was found to be contaminated with PFAS, the plant invested around $46 million into upgraded activated carbon systems. Once installed, these systems cost roughly $2.9 million to operate yearly, as the carbon needs to be replaced each time it reaches capacity. Though pricey, the plant says that the process now clears close to 100% of PFAS.
Read the court decisionRead the full story...Reprinted courtesy of
PFAS Team, Pillsbury