Nonresidential Construction Employment Expands in August, Says ABC
December 16, 2019 —
Associated Builders and Contractors - Construction ExecutiveThe construction industry added 14,000 net new jobs in August, according to an Associated Builders and Contractors analysis of data released by the U.S. Bureau of Labor Statistics. On a year-over-year basis, industry employment has expanded by 177,000 jobs, or 2.4%.
Nonresidential construction employment increased by 11,600 net jobs in August and is up by 114,200 net jobs over the last 12 months, translating into 2.5% growth. The majority of job gains emerged from nonresidential specialty trade contractors, which added 5,400 jobs last month and nearly 103,000 positions over the past year. Heavy and civil engineering added 4,400 net new jobs, while nonresidential building added 1,800 jobs on a monthly basis.
The construction unemployment rate stood at 3.6% in August, up 0.2 percentage points from the same time last year. Unemployment across all industries stood at 3.7% in August, unchanged from the previous month.
“While job growth across all industries fell short of projections, today’s employment report was just about perfect,” said ABC Chief Economist Anirban Basu. “Yes, employment growth has been softening for quite some time, with average monthly job growth totaling 150,000 during the last six months after approaching 200,000 during the prior six-month period. And employment growth estimates were also revised lower for both June and July. That said, looking beyond the headline number, August’s labor market performance was more than respectable, even accounting for about 25,000 of the jobs being added for temporary Census work.
Reprinted courtesy of
ABC, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Limited Number of Insurance-Related Bills Passed by 2014 Hawaii Legislature
June 11, 2014 —
Tred R. Eyerly – Insurance Law HawaiiVery few insurance-related bills survived the 2014 Hawaii Legislative session, with several consumer-friendly bills failing to make it out of committee.
Here is a summary of the bills that passed:
SB2365: Limits reimbursement of prescription medications in order to prevent drug prices from becoming an unreasonable cost driver of health care in workers' compensation and motor vehicle insurance claims.
SB2470: Appropriates general funds to provide for the sustainability of the Hawaii Health Connector, but provides for greater transparency, stakeholder engagement, and legislative involvement in the activities of the Hawaii Health Connector.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Office REITs in U.S. Plan the Most Construction in Decade
July 09, 2014 —
Brian Louis – BloombergOffice buildings in top U.S. markets are getting so expensive that landlords are choosing to build rather than buy, spurring the most development by real estate investment trusts in at least a decade.
Office REITs, led by Boston Properties Inc. (BXP), Vornado Realty Trust (VNO) and Kilroy Realty Corp. (KRC), are planning to plow almost $11 billion into new projects, triple the amount just two years ago and the most in data going back to 2004, according to research firm Green Street Advisors Inc. Much of that is focused on the coasts, including San Francisco and New York, the areas with the most demand from both tenants and investors.
Prices for office buildings in major markets have surged past peak levels, lifted in part by sovereign-wealth funds and pensions willing to accept lower yields than other investors because they are seeking safe investments. For REITs, which have to answer to shareholders seeking higher returns, building is often a better option than competing with institutional buyers.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Louis, BloombergMr. Louis may be contacted at
blouis1@bloomberg.net
Unravel the Facts Before Asserting FDUTPA and Tortious Interference Claims
September 05, 2022 —
David Adelstein - Florida Construction Legal UpdatesCMR Construction and Roofing, LLC v. UCMS, LLC, 2022 WL 3012298 (11th Cir. 2022) is an interesting opinion where a contractor asserted a Florida’s Deceptive and Unfair Trade Practices Act (known by its acronym “FDUTPA”) claim and tortious interference claims (with a contract and with an advantageous business relationship) against another contractor, i.e., a competitor, that were dismissed from the get-go. It is an opinion worthy of interest based on the claims asserted against a competitor. Throwing around FDUTPA and tortious interference may sound good from an intimidation standpoint, but pleading and then proving these claims are a lot different than loosely throwing around these claims. Before filing a lawsuit for FDUTPA and tortious interference, spend time unraveling the facts and the chronology. Do not rely on conclusory allegations simply to check the box regarding required elements to plead while ignoring the actual facts that support the allegations. These are fact-based claims and it is imperative the facts are fully known from on the onset so that they can be strategically pled and pursued.
In this matter, a contractor, the plaintiff, was hired by a condominium association around April 2018 to repair damage caused by a hurricane which included roofing work. The association was going to have its insurer pay its contractor. In May 2020, the association hired a new contractor to perform the same work (the “new contractor”). The association then directed the plaintiff to cease work since it hired the new contractor.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California Expands on Scope of Coverage for Soft Cost Claims
February 14, 2023 —
Caitlin N. Rabiyan - Saxe Doernberger & Vita, P.C.The California federal district court case of KB Home v. Illinois Union Insurance Co., No. 8:20-cv-00278-JLS-JDE, (C.D. Cal. August 23, 2022), provides much needed guidance for cases involving builder's risk insurance claims for soft cost coverage.
The case stems from damage to several of KB Home’s residential building sites caused by a severe rainstorm in January 2017. Each home site was a smaller part of a large housing development project. The damage caused significant delay in the completion of some individual home sites, although there was limited evidence of delay to the overall housing development project.
As a result, KB Home sought coverage under a builder’s risk policy purchased from Illinois Union for both hard costs and soft costs. “Hard costs” are the costs directly associated with repairing property damage to the sites. Conversely, “soft costs” are indirect expenses associated with project delays caused by such property damage and repair efforts. For example, hard costs would include labor and materials, whereas the soft costs claimed by KB Home included additional real estate taxes, construction loan interest, and advertising and promotional expenses incurred because of the delays. Illinois Union paid the claim for the hard costs, but denied the soft costs claim. KB Home filed suit and Illinois Union eventually filed a motion for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Caitlin N. Rabiyan, Saxe Doernberger & Vita, P.C.Ms. Rabiyan may be contacted at
CRabiyan@sdvlaw.com
That Boilerplate Language May Just Land You in Hot Water
December 17, 2015 —
Kevin Brodehl – California Construction Law BlogThe following post originally appeared in my partner
Kevin Brodehl‘s informative blog,
Money and Dirt. If you’re involved in real estate investment, development and/or secured lending in California, it’s a must read. While Kevin’s post below discusses a case involving a real estate purchase agreement, it applies equally to construction contracts, perhaps even more so, since I can’t think of any other type of contract in which indemnity and integration clauses are as common, or as integral.
Almost all real estate purchase and sale agreements contain provisions relating to integration and indemnity.
In the “boilerplate” worldview, these provisions are standard, generic, and basically all the same — integration clauses prohibit extrinsic evidence that would contradict the terms of the agreement, and indemnity clauses force the seller to protect the buyer from third party claims arising after closing.
But a recently published opinion by the California Court of Appeal (Fourth District, Division Three in Santa Ana) — Hot Rods, LLC v. Northrop Grunman Systems Corp. — clarifies that integration and indemnity clauses can have vastly different effects depending on how they are drafted.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin Brodehl, California Construction Law BlogMr. Brodehl may be contacted at
kbrodehl@wendel.com
Traub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp Obtain Summary Judgment in Favor of Residential Property Owners
December 13, 2022 —
Gregory S. Pennington & Emily A. Velcamp - Traub LiebermanTraub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp obtained summary judgment in favor of their clients, owners of a residential property [the “Owners” or “Defendants”] used as a short-term rental in Beach Haven, New Jersey. Plaintiff alleged injuries resulting from a fall into an open water meter pit, located in the public sidewalk abutting the Owners’ property during the time within which the property was rented to plaintiff and his family. According to plaintiff, defendants breached their duty owed to him, relying on a Borough of Beach Haven Ordinance, thereby allowing the water meter pit to be raised in an unsafe manner, which resulted in plaintiff’s fall and subsequent injuries.
After the Court denied defendants’ initial Motion for Summary Judgment on the grounds that issues of material fact existed regarding defendants’ duty and the alleged breach of that duty, a Motion for Reconsideration was filed. Mr. Pennington and Ms. Velcamp argued that their clients, as residential landowners, owed no duty of care to plaintiff for the raised condition of the water meter pit lid, located in the abutting sidewalk, as they did not cause or contribute to the alleged condition. Defendants further argued that even if a duty of care existed, no breach occurred given the lack of notice to defendants, either actual or constructive. Plaintiff attempted to argue that defendants had constructive notice of the lid’s raised condition, relying on his expert report and the fact that defendants had 3.5 months from the date the property was purchased, to the date of the subject accident to discover the lid’s raised condition. Mr. Pennington and Ms. Velcamp successfully argued that despite plaintiff’s allegations and the findings contained in plaintiff’s expert report, authored 2 months after the alleged accident, there was still no credible, material evidence to say how long the water meter pit lid was in that raised condition to allow defendants a reasonable time to discover it, remedy it, or report it to the Borough.
Reprinted courtesy of
Gregory S. Pennington, Traub Lieberman and
Emily A. Velcamp, Traub Lieberman
Mr. Pennington may be contacted at gpennington@tlsslaw.com
Ms. Velcamp may be contacted at evelcamp@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Takeaways From Schedule-Based Dispute Between General Contractor and Subcontractor
September 09, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion out of the Southern District of Florida, Berkley Insurance Co. v. Suffolk Construction Co., Case 1:19-cv-23059-KMW (S.D.Fla. July 22, 2024), provides valuable takeaways on schedule-based disputes between a general contractor and subcontractor on a high-rise project.
In a nutshell, the general contractor’s original project schedule was abandoned due to project delays and the project wasn’t being built by any updated project schedule. The subcontractor claimed the general contractor was mismanaging the schedule putting unreasonable manpower and supervision constraints on it, i.e., it was working inefficiently. A bench trial was conducted and the Court found in favor of the subcontractor’s arguments. The Court found the general contractor had unrelated delays and that work activities were no longer methodical but, simply, piecemeal demands. The Court also rejected any inadequate manpower arguments finding the subcontract did not place any manpower requirements on the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of