The Difference Between Routine Document Destruction and Spoliation
October 18, 2021 —
Steven A. Neeley - Construction ExecutiveIn today’s world, there is a tendency to believe that everything must be preserved forever. The common belief is that documents, emails, text messages, etc. cannot be deleted because doing so may be viewed as spoliation (i.e., intentionally destroying relevant evidence). A party guilty of spoliation can be sanctioned, which can include an adverse inference that the lost information would have helped the other side. But that does not mean that contractors have to preserve every conceivable piece of information or data under all circumstances. There are key differences between routine document destruction (when done before receiving notice of potential claims or litigation) and spoliation.
The Armed Services Board of Contract Appeals decision in Appeal of Sungjee Constr. Co., Ltd., ASBCA Nos. 62002 and 62170 (Mar. 23, 2021) provides a good reminder. There, Sungjee challenged its default termination under a construction contract at Osan Air Base in South Korea. Sungjee argued that the government denied it access to the site for 352 days (out of a 450-day performance period) by refusing to issue passes that were needed to access the base. The government argued that it had issued the passes, but it could not produce them to Sungjee in discovery because they had been destroyed as part of a routine document destruction policy. The base security force issued hard copy passes and entered the information in a biometric system. The government was able to produce the biometric system data but not the hard copy passes because they were destroyed each year.
Sungjee argued the government was guilty of spoliation and moved for sanctions. It asked the Board to draw an adverse inference that the passes would have shown that the government had not issued proper passes on a timely basis, which delayed Sungjee’s performance. The Board denied Sungjee’s motion for several reasons.
Reprinted courtesy of
Steven A. Neeley, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Neeley may be contacted at
steve.neeley@huschblackwell.com
When Construction Defects Appear, Don’t Choose Between Rebuilding and Building Your Case
October 11, 2021 —
Curtis Martin - ConsensusDocsWhen construction defects occur during construction, they intensify pressure from a schedule that may already be tight. Defects must be analyzed, confirmed, removed, and replaced and this can be time consuming. Or course, a construction schedule rarely anticipates defects, demolition, and rework and the owner will still expect the project to be completed on time; however, pressing forward with immediate remediation may have unintended consequences.
Before starting demolition, consider the evidentiary doctrine of spoliation. Spoilation occurs when a party destroys or unreasonably deprives another party of evidence and courts have imposed sanctions on a party that deprives an opponent of evidence. The doctrine has historically concerned documents, but its application has extended to electronic data, and courts also apply it to building conditions in construction defects cases. So, before tearing out or fixing defective work, consider the need to allow the opposing party to inspect, test and document it.
Imagine this scenario. The concrete in a slab placed by your subcontractor shows low compressive strength results in the 28-day cylinder tests. Tearing out the slab and replacing it will put you at least a month behind schedule and you don’t want to waste any time before removing and replacing it. Nevertheless, while you’re rebuilding the defective slab, be mindful that you are also building a case. If you plan to recover the costs you incur because of the defective concrete from the responsible parties, you should allow the subcontractor (and possibly the concrete supplier and other implicated parties) to examine, preserve, and/or test the work in question. Failure to do so may subject you to spoliation sanctions and jeopardize your right to recover damages.
Read the court decisionRead the full story...Reprinted courtesy of
Curtis Martin, Peckar & AbramsonMr. Martin may be contacted at
cmartin@pecklaw.com
East Coast Evaluates Damage After Fast-Moving 'Bomb Cyclone'
March 06, 2022 —
Scott Van Voorhis - Engineering News-RecordCoastal areas in the northeast US are assessing damage from a fast-moving “bomb cyclone” that caused temperatures to plummet, triggered heavy flooding and high winds, and dumped 2 ft of snow in some New England areas.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Should I Stay or Should I Go? The Supreme Court Says “Stay”
June 10, 2024 —
Brendan J. Witry - The Dispute ResolverIn the construction industry, arbitration is a frequently agreed-upon and utilized dispute resolution method. The Federal Arbitration Act (the “FAA”), 9 U.S.C. 1, et seq., provides the underpinning and framework for how courts should handle litigation in connection with arbitration agreements. Where a party asserts that a claim brought in court should be subject to arbitration, Section 3 of the FAA provides that the action should be stayed. However, some courts have entertained a party’s request to dismiss a suit where the claim is subject to an arbitration agreement, creating a circuit split in the federal appeals courts. In
Smith v. Spizzirri, 2024 WL 2193872, issued on May 16, 2024, the Supreme Court held that, absent some other defect (such as the lack of personal or subject matter jurisdiction), Section 3 of the FAA requires a court which finds a claim is subject to an arbitration must stay the lawsuit during the arbitration proceedings rather than dismissing the action.[1] In so doing, the Court addressed a question that for years it left unanswered.
While most Circuits held, prior to Smith, that Section 3 requires a court to stay the litigation pending an arbitral award; the First, Fifth, Eighth, and Ninth Circuits each held that a court could dismiss an action in lieu of staying.
In Smith, both parties acknowledged the underlying claims were arbitrable, but when the district court compelled arbitration, the court dismissed the action rather than staying the court proceedings. The Ninth Circuit (relying on its prior precedent) affirmed, with two judges noting that the Ninth Circuit’s approach was incorrect. The Supreme Court granted certiorari and reversed.
Read the court decisionRead the full story...Reprinted courtesy of
Brendan J. Witry, Laurie & Brennan LLPMr. Witry may be contacted at
bwitry@lauriebrennan.com
Robinson+Cole’s Amicus Brief Adopted and Cited by Massachusetts’s High Court
July 31, 2024 —
Erica Whaley - Construction Law ZoneEarlier this year, the
Associated Subcontractors of Massachusetts hired Robinson+Cole attorney
Joseph Barra to submit an amicus brief to the Massachusetts Supreme Judicial Court for consideration in the appeal pending before it in
Business Interiors Floor Covering Business Trust v. Graycor Construction Co., Inc. In its June 17, 2024 decision in that case, the Court interpreted the Massachusetts Prompt Pay Act, which applies to private construction projects and “requires that parties to a construction contract approve or reject payment within” an allotted time period and in compliance with certain procedures else such payments will be deemed approved. Two years ago, the Massachusetts Appeals Court, in
Tocci Building Corp. v. IRIV Partners, LLC, decided that an owner who fails to timely advise its general contractor of the reasons as to why it was withholding payment, coupled with failure to certify that such funds are being withheld in good faith, violates the Prompt Pay Act and makes the owner liable for funds owed.
[1] However, the Tocci Building Court left open the question of whether one who violates the Prompt Pay Act forfeits its substantive defenses to non-payment, such as fraud, defective work, or breach of material obligation of the contract.
The facts of Business Interiors involve a general contractor, Graycor, which subcontracted Business Interiors to perform certain flooring work for a movie theatre in Boston’s North End. When Graycor failed to formally approve, reject, or certify, in good faith, its withholding of payment of three of Business Interiors’ applications for payment as prescribed by the Prompt Pay Act, Business Interiors brought suit alleging, among other things, breach of contract. Business Interiors then moved for summary judgement arguing that Graycor’s failure to comply with the Act rendered it liable for the unpaid invoices.
Read the court decisionRead the full story...Reprinted courtesy of
Robinson + Cole
The Cost of Overlooking Jury Fees
February 07, 2022 —
Nicholas B. Brummel, Arezoo Jamshidi & Lawrence S. Zucker II - Haight Brown & BonesteelOn January 21, 2022, the Court of Appeal, Second Appellate District, Division Two (Los Angeles), certified for publication a 2-1 decision that serves as an important reminder to California attorneys to post jury fees in a timely manner and to use appropriate channels and consult with appellate counsel in seeking appellate relief from contested rulings.
In TriCoast Builders, Inc. v. Nathaniel Fonnegra, (B303300, Jan. 21, 2022), a construction defect dispute, the trial court set a jury trial at defendant’s request. However, on the day trial was set, defendant waived jury trial. Plaintiff objected and made an oral request for jury trial. The trial court denied the request finding that plaintiff waived its right to a jury trial by failing to timely post jury fees. The matter proceeded to a bench trial, and the court ruled in favor of defendant. Plaintiff appealed, having failed to seek a writ of mandate, which the appellate court noted “is the proper remedy to secure a jury trial allegedly wrongfully withheld.”
Reprinted courtesy of
Nicholas B. Brummel, Haight Brown & Bonesteel,
Arezoo Jamshidi, Haight Brown & Bonesteel and
Lawrence S. Zucker II, Haight Brown & Bonesteel
Mr. Brummel may be contacted at nbrummel@hbblaw.com
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractors Should be Aware of Homeowner Duties When Invited to Perform Residential Work
September 26, 2022 —
Joshua Lane - Ahlers Cressman & Sleight PLLCDivision 2 of the Court of Appeals
[1] recently addressed a property owner’s liability to a contractor who is injured performing work on their property.
The action arose from an incident in which Virgil Mihaila, a remodeling contractor, fell from a ladder while installing a new roof on the Troths’ shed and landed on a metal grounding rod that was sticking over a foot out of the ground. Mihaila saw the grounding rod as he was working and recognized the danger, but he claimed that he could not complete the roofing job without encountering it. Although he tried to position his ladder so that he would avoid the grounding rod if he fell, he somehow fell off the ladder and landed on the grounding rod, sustaining multiple rib fractures and a punctured lung.
Mihaila filed a complaint against the Troths, alleging that they were negligent in failing to protect him from the danger of the grounding rod sticking out of the ground. The Troths denied that they were negligent and asserted the affirmative defense of contributory negligence. The Troths filed a motion for summary judgment, which the trial court granted, stating that summary judgment was appropriate regarding the Troths’ duty because Mihaila “became aware of the risk, undertook to encounter the risk, and made his own efforts to mitigate the risk.” The trial court denied Mihaila’s motion for reconsideration and Mihaila appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Joshua Lane, Ahlers Cressman & Sleight PLLCMr. Lane may be contacted at
joshua.lane@acslawyers.com
Legal Implications of 3D Printing in Construction Loom
July 10, 2018 —
Aldo E. Ibarra - Engineering News-RecordImagine a printer in the middle of a construction site programmed with a designer’s plans and specifications to build an entire home from scratch. As concrete is fed into the printing device, a technician hits enter on her computer and a 3D printer starts fabricating the structure’s walls and roof.
Read the court decisionRead the full story...Reprinted courtesy of