Equities Favor Subrogating Insurer Over Subcontractor That Performed Defective Work
August 04, 2015 —
Christopher Kendrick and Valerie A. Moore – Haight Brown & Bonesteel LLPIn Valley Crest Landscape v. Mission Pools (No. G049060, filed 6/26/15, ord. pub. 7/2/15), a California appeals court held that equities favor an insurer seeking equitable subrogation over a subcontractor that agreed to defend and indemnify claims arising out of its performance of work under the subcontract.
Valley Crest contracted to build a pool at the St. Regis Hotel in Dana Point. Valley Crest subcontracted with Mission Pools to perform the work. The master contract contained an indemnity clause in favor of St. Regis, and the subcontract contained an indemnity clause in favor of Valley Crest. An intoxicated guest who was rendered quadriplegic after diving in the shallow end of the pool sued the hotel, Valley Crest, Mission and others involved in the design, construction and operation of the pool. The suit included allegations that the pool depth was improperly marked; there was inadequate warning signage; and the pool finish caused the pool to appear deeper than it was. Valley Crest tendered its defense to Mission Pools under the subcontract’s indemnity agreement. When Mission did not respond, Valley crest filed a cross-complaint for indemnity. All parties ultimately reached a settlement with the injured plaintiff, leaving Valley Crest’s cross-complaint against Mission Pools.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com; Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Retrospective As-Built Schedule Analysis Can Be Used to Support Delay
May 23, 2022 —
David Adelstein - Florida Construction Legal UpdatesDelay claims are part of construction. There should be no surprise why. Time is money. A delay claim should be accompanied by expert opinions that bolster evidence that gets introduced. The party against whom the delay claim is made will also have an expert – a rebuttal expert. Not surprisingly, each of the experts will rely on a different critical path as to relates to the same project. The party claiming delay will rely on a critical path that shows the actions of the other party impacted their critical path and proximately caused the delay. This will be refuted by the opposing expert that will challenge the critical path and the actions claimed had no impact on the critical path (i.e., did not proximately cause the delay). Quintessential finger pointing!
This was the situation in CTA I, LLC v. Department of Veteran Affairs, CBCA 5826, 2022 WL 884710 (CBCA 2022), where the government terminated the contractor for convenience and the contractor claimed equitable adjustments for, among other things, delay. The contractor’s expert relied on an as-built critical path analysis by “retrospectively creating updates to insert between the contemporaneous updates.” Id., supra, n.3. The government’s expert did not do a retrospective as-built analysis and relied on only contemporaneous schedule updates. Id.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The EEOC Targets Construction Industry For Heightened Enforcement
May 15, 2023 —
Meghan Douris & Andrew Scroggins - The Construction SeytSeyfarth Synopsis: On January 10, 2023, the Equal Employment Opportunity Commission (EEOC) released for public comment its
draft 2023-2027 Strategic Enforcement Plan (“SEP”)—a document that will guide the Commission’s enforcement priorities for the next five years. The EEOC’s prior Strategic Plan described how it would pursue its enforcement goals. (See our earlier blog on the Strategic Plan
here). The Strategic Enforcement Plan, on the other hand, describes what the EEOC’s enforcement priorities will be. Earlier actions by the EEOC suggested that it might be turning its attention to the construction industry. In the SEP, the EEOC makes its intentions explicit, putting the construction industry—and especially those receiving federal funding—squarely in its sights.
History of the SEP
The EEOC’s
first SEP covered Fiscal Years 2013-2016 (the EEOC’s fiscal years begin on October 1) and identified six broad subject-matter priorities. The EEOC’s
second SEP set the course for enforcement priorities for FY2017-2022. The
latest proposed SEP, published in the Federal Register for comment for the first time, provides notable additional details that put the employer community on notice of the Commission’s intentions for FY2023-2027.[
1]
Reprinted courtesy of
Meghan Douris, Seyfarth and
Andrew Scroggins, Seyfarth
Ms. Douris may be contacted at mdouris@seyfarth.com
Mr. Scroggins may be contacted ascroggins@seyfarth.com
Read the court decisionRead the full story...Reprinted courtesy of
Here's Proof Homebuilders are Betting on a Pickup in the Housing Market
April 15, 2015 —
Victoria Stilwell – BloombergHomebuilders have caught spring fever.
Confidence among U.S. builders, measured by the National Association of Home Builders/Wells Fargo sentiment gauge, increased in April for the first time in five months. The group's measure of the sales outlook for the next six months climbed to the highest level since December, while a gauge of prospective buyer traffic also rose.
With the housing market posting only middling progress in recent months, the fact that construction companies are optimistic is a good sign, especially heading into the crucial spring-selling season. The period usually starts in mid-February, with deals picking up the following months as the weather warms.
What's more encouraging, though, is that builders seem to be putting money where their mouths are.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, Bloomberg
The Problem With Building a New City From Scratch
May 10, 2022 —
Nolan Gray - BloombergFrom California to Miami and points in between, housing costs in the U.S. are skyrocketing, bringing bidding wars in hot markets and fears of a fresh surge in homelessness as renters scramble for an affordable place to live.
The deepening housing crunch — and the intractable resistance that residents often put up when the prospect of new housing emerges nearby — has led some observers to ask: Why don’t we just make new cities?
“When China needs new places for people to live, they just build a new city,” Nathan J. Robinson recently wrote in Current Affairs, contemplating all the undeveloped land in between California’s costly major urban areas. “They’ve built 600 of them since 1949.”
At first blush, it might seem obvious. But history is full of failed, unfinished or underperforming scratch-built city projects, in California and elsewhere, and more are in the pipeline.
To learn more about how we might best approach building new cities, CityLab talked to a person who’s had a hand in planning a few of them: Alain Bertaud, a fellow at the Marron Institute for Urban Management and a globetrotting former city planner at the World Bank. Our conversation has been edited for length and clarity.
Read the court decisionRead the full story...Reprinted courtesy of
Nolan Gray, Bloomberg
The Private Works: Preliminary Notice | Are You Using the Correct Form?
August 20, 2019 —
William L. Porter, Esq. - Porter Law GroupThe Private Works – Preliminary Notice form which contractors, subcontractors and suppliers had become accustomed to using for many years changed in 2004. Despite this change in law, many in the construction industry have still not started using the correct new form. Changes in the law, championed by the American Subcontractors’ Association, gave a significant new benefit to subcontractors and suppliers by giving the subcontractor or supplier some expectation of actually receiving notice of when a Notice of Completion or a Notice of Cessation has been recorded on many private works projects. The law also changed the language of the California Preliminary Notice that subcontractors and suppliers must use to protect their mechanics’ lien, bond claim and stop payment notice rights. If Owners do not send out the Notice of Completion as required by law they incur a diminishing of the protections afforded to them when they record a Notice of Completion or Notice of Cessation on many private works projects.
The revised law requires private project owners to notify all subcontractors and suppliers within 10 days after recording a Notice of Completion or Notice of Cessation that a Notice of Completion or a Notice of Cessation has actually been recorded. In order to receive such notice, the subcontractor or supplier must properly serve the new form of Preliminary Notice. If this properly occurs and the private project owner provides the required notice, then the subcontractor or supplier will have 30 days to record a Mechanics’ Lien. However, if an owner under such circumstances fails to properly notify a subcontractor or supplier within 10 days after recording a Notice of Completion or Notice of Cessation, then the Subcontractor or supplier will have 90 days to record a Mechanics’ Lien. The details of the law can be found in California Civil Code sections 8190, 8414 and 8416.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Esq., Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Mortenson Subcontractor Fires Worker Over Meta Data Center Noose
April 19, 2022 —
James Leggate - Engineering News-RecordA worker on a data center project for Facebook parent company Meta in Utah was fired after admitting to tying a noose at the worksite where racist graffiti had also been found months earlier.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
BHA has a Nice Swing Donates to CDCCF
May 21, 2014 —
Beverley BevenFlorez-CDJ STAFFBert L. Howe & Associates (BHA) would like to congratulate the winners of the BHA Has a Nice Swing golf game for charity. With the help of the participants, BHA was able to donate $1800 to the Construction Defect Community Charitable Foundation (CDCCF). CDCCF was established to provide financial assistance for active members of the construction defect community who have uninsured expenses because of a disability, sickness, and/or the death of a community member or their immediate family member.
BHA would also like to congratulate their booth’s raffle winners. Prizes included an iPad Air, four sets of Dodger tickets, a Day at the Del Mar Races, and Best Buy gift cards.
Read how the CDCCF assists the construction defect community... Read the court decisionRead the full story...Reprinted courtesy of