Texas Federal Court Upholds Professional Services Exclusion to Preclude Duty to Defend
March 16, 2020 —
Jeremy S. Macklin - Traub Lieberman Insurance Law BlogIn Project Surveillance, Inc. v. The Travelers Indemnity Company, No. 4:19-CV-03324, 2020 WL 292247 (S.D. Tex. Jan. 21, 2020), a Texas federal court held that a professional services exclusion in a commercial general liability policy precluded Travelers’ duty to defend its insured.
The underlying lawsuit was a wrongful death action brought by the family of a worker killed on a construction site. Project Surveillance was present at the construction site “to provide safety supervision or other services.” The underlying lawsuit alleged that Project Surveillance negligently failed to inspect or adequately inspect the project and failed to warn or adequately warn the decedent of a dangerous condition. The underlying lawsuit also alleged that Project Surveillance was negligent in failing to stop work.
At the time of the incident, Project Surveillance had commercial general liability insurance through Travelers and professional liability insurance through RLI. RLI agreed to defend Project Surveillance in the underlying lawsuit. Travelers, however, denied owing a duty to defend or indemnify based on an exclusion for “bodily injury” arising out of the rendering or failure to render any “professional service.” The Traveler policy defined the term “professional services” to mean any service requiring specialized skill or training, including “failure to prepare [. . .] any warning,” “supervision,” “inspection,” “control,” “surveying activity or service,” “job site safety,” “construction administration,” and “monitoring [. . .] necessary to perform and of [those] services.”
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy S. Macklin, Traub LiebermanMr. Macklin may be contacted at
jmacklin@tlsslaw.com
EPA Seeks Comment on Clean Water Act Section 401 Certification Rule
July 19, 2021 —
Karen Bennett - Lewis BrisboisThe Environmental Protection Agency (EPA) announced that it will revise a 2020 final rule clarifying requirements for water quality certification under the Clean Water Act (CWA). 85 Fed. Reg. 42210 (June 2, 2021). CWA Section 401 requires states and tribes to certify that any discharges associated with a federal permit will comply with applicable state or tribal water quality requirements.
In an effort to eliminate 401 certification being used as a tool for delaying or imposing conditions unrelated to protecting water quality on federal permits, the 2020 rule established limits on the scope and timeline for review and required any conditions on certification to be water-quality related. State and Tribal governments and environmental groups challenged the rule, arguing it constrained state and tribal decision-making authority by limiting the term “other appropriate requirements of State law” in CWA Section 401(d) to “water quality requirements” and “point source discharges.”
With EPA’s decision to revise the rule, many believe these same scope and timing limitations will be targets for change. Clients with experience, positive or negative, under the 2020 rule should consider submitting comments by the August 2, 2021 deadline.
Read the court decisionRead the full story...Reprinted courtesy of
Karen Bennett, Lewis BrisboisMs. Bennett may be contacted at
Karen.Bennett@lewisbrisbois.com
PSA: Latest Updates from AGC-VA on COVID Rules (UPDATED)
June 14, 2021 —
Christopher G. Hill - Construction Law MusingsThe recent changes in masking requirements and COVID-related restrictions have prompted questions and concerns throughout the construction industry. We understand your questions and continue to work closely with the Department of Labor and Industry (DOLI) and the Safety and Health Codes Board.
Here is what we know at this point:
- The Governor’s second order terminates the state of public emergency as of May 28, 2021. At that point, the DOLI Safety and Health Codes Board will have 2 weeks to meet and decide whether to rescind, modify, or continue the Final Permanent Standard for Prevention of Covid-19. Companies should continue to follow the standard until further notice.
- UPDATE: At present, the emergency order does not expire before June 30, unless amended or otherwise changed. Therefore, the two-week period to announce a meeting of the SCHB to review the permanent COVID-19 standard does not begin until July 1, though the meeting can occur after the two-week period. AGCVA has joined other groups in pushing for a meeting as soon as possible.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Anticipatory Repudiation of a Contract — The Prospective Breach
July 05, 2021 —
David Adelstein - Florida Construction Legal UpdatesThere are instances where a party can engage in the anticipatory repudiation of their obligations under a contract. In essence, this is basically a party prospectively breaching the contract by repudiating their obligations in the contract.
A prospective breach of contract occurs where there is absolute repudiation by one of the parties prior to the time when his performance is due under the terms of the contract. Such a repudiation may be evidenced by words or voluntary acts but the refusal must be distinct, unequivocal, and absolute. Moreover, repudiation can be shown where one party makes additional demands not included in the initial agreement:
The law is clear that where one party to the contract arbitrarily demands performance not required by the contract and couples this demand with a refusal to further perform unless the demand is met, the party has anticipatorily repudiated the contract, which anticipatory repudiation relieves the non-breaching party of its duty to further perform and creates in it an immediate cause of action for breach of contract.
24 Hr Air Service, Inc. v. Hosanna Community Baptist Church, Inc., 46 Fla. L. Weekly, D1344a (Fla. 3d DCA 2021) (quotations and citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Investigators Explain Focus on Pre-Collapse Cracking in Florida Bridge
June 06, 2018 —
Scott Judy & Richard Korman - Engineering News-RecordThe National Transportation Safety Board's preliminary report on the fatal collapse in March of a pedestrian bridge at Florida International University in Sweetwater focuses attention on the widely discussed pre-collapse cracking in the main span. The report also confirms accounts about what the construction crew working on the bridge was doing before the structure fell.
Reprinted courtesy of
Scott Judy, ENR and
Richard Korman, ENR
Mr. Judy may be contacted at judys@enr.com
Mr. Korman may be contacted at kormanr@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
Negligent Construction an Occurrence Says Ninth Circuit
June 30, 2011 —
CDJ STAFFOne June 27, the US Court of Appeals has rejected an appeal from Mid-Continent Casualty Company. Mid-Continent had appealed a summary judgment granted to Titan Construction Company.
Titan Construction had built condominiums for the Williamsburg Condominium Association, which later filed a construction defect lawsuit against Titan and other defendants. Titan settled with the developer, Kennydale, assigning its rights against Mid-Continent to Kennydale. Mid-Continent filed suit, claiming that “it had no obligation to indemnify or defend Titan, Kennydale, or various other defendants.” The district court found in favor of Mid-Continent, granting a summary judgment, concluding that Titan’s insurance covered “occurrences,” and none had taken place.
On appeal, the court found that the negligent construction of the condominiums constituted an “occurrence” The case was remanded and the district court this time found in favor of Titan, “concluding that Mid-Continent failed to raise a triable issue as to the applicability of the remaining policy exclusions.
The Ninth Circuit Court of Appeals has now affirmed that decision and Titan’s summary judgment stands.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Contractor’s Claim for Interest on Subcontractor’s Defective Work Claim Gains Mixed Results
April 27, 2020 —
John J. Gazzola, Associate, Pepper Hamilton LLP - ConsensusDocsThis case concerns calculation of a damages award to a general contractor, Skanska USA Building, Inc., on its claim for breach of contract against its masonry subcontractor, J.D. Long Masonry, Inc., arising from Long’s faulty construction of a masonry façade at a medical research facility in Baltimore. When the façade collapsed and Long failed to repair it, Skanska hired a replacement subcontractor, C.A. Lindman, to remediate Long’s defective work and filed suit against Long to recover the resulting damages. After the court granted Skanska’s motion for summary judgment as to liability, Skanska moved for summary judgment on the issue of damages, relying on the indemnification provision of the subcontract to seek compensatory damages, pre- and post-judgment interest, and litigation fees. In the subcontract, Long agreed to indemnify and hold Skanska harmless from all claims, losses, costs and expenses, including attorneys’ fees, arising before or after completion of Long’s work, caused by, arising out of, resulting from, or occurring in connection with Long’s performance of the work or breach of the subcontract.
The court first applied the terms of this provision to award Skanska compensatory damages, holding that Skanska was, as a matter of law, entitled to recover the amount of the Lindman subcontract and general conditions incurred to supervise remediation of Long’s work. The court, however, denied Skanska’s claim for pre-judgment interest on the entirety of these damages. Skanska asserted that it was entitled to pre-judgment interest on the full award, calculated from the date on which it first paid Lindman. The court disagreed, explaining that, under Maryland law, a claimant is entitled to an award of pre-judgment interest as of right only when the amount due is certain, definite and liquidated by a specific date prior to judgment. The court reasoned that, because much of the Lindman subcontract value was composed of later-executed change orders, an award of pre-judgment interest could not be uniformly calculated back to the date of Skanska’s first payment to Lindman. And moreover, because Skanska continued to withhold sums due to Lindman pending resolution of certain issues, awarding Skanska pre-judgment interest on amounts it had not yet paid would result in a “windfall” to Skanska because there was no “use of income” loss to be compensated.
Read the court decisionRead the full story...Reprinted courtesy of
John J. Gazzola, Pepper Hamilton LLPMr. Gazzola may be contacted at
gazzolaj@pepperlaw.com
Downtown Sacramento Building Riddled with Defects
July 23, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Board of Equalization tower in Sacramento, California has gone through $60 million in repairs to deal with issues such as bats, floods, leaky windows, mold, and glass panels that would “pop off the building with no warning and shatter on the sidewalk,” according to Insurance News. However, an additional $115 million in repairs are planned to deal with “crumbling core plumbing” and “concrete-and-glass exterior,” among other problems.
Now, “a Sacramento attorney filed a $50 million tort claim this month, a first step toward suing the tax-collecting department on behalf of employees who say their bosses downplayed the building's ailments and put workers' health at risk.”
"Even though my lawyers told me not to say this, I don't think it's safe," board Chairman Jerome Horton told Insurance News.
Read the court decisionRead the full story...Reprinted courtesy of