Three-Year Delay Not “Prompt Notice,” But Insurer Not “Appreciably Prejudiced” Either, New Jersey Court Holds
November 04, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPIn Harleysville Preferred Insurance Company v. East Coast Painting & Maintenance, LLC, 2019 U.S. Dist. LEXIS 135295 (D.N.J. Aug. 12, 2019) (East Coast Painting), the U.S. District Court for the District of New Jersey held that an insurer, which received notice of a bodily injury accident three years after it happened, was not “appreciably prejudiced” by such late notice, even as the court acknowledged notice three years later did not satisfy the policy’s “prompt notice” condition. The court also held that the policy’s “Operational Exclusion,” which excluded coverage for bodily injury arising out of the operation of “cherry pickers and similar devices,” did not apply because the accident arose out of the use of a “scissor lift,” which is not a device similar to a cherry picker.
East Coast Painting arose out of a Queens, New York bridge-painting project, during which an employee of the insured, East Coast Painting and Maintenance LLC was injured while “standing on a scissor lift mounted to the back of a truck,” owned and operated by East Coast. The employee sued various project-related entities which, in turn, joined East Coast as a defendant. East Coast sought coverage under its business auto policy, and the insurer agreed to defend the insured under a reservation of rights. The insurer subsequently sought a declaration that it did not owe coverage based on, among other things, the policy’s “Operational Exclusion,” and the insured’s failure to satisfy the policy’s “prompt notice” condition. The insurer moved for summary judgment on both of those bases, but the court in East Coast Painting denied the motion.
As for the insurer’s “prompt notice” defense, the court in East Coast Painting concluded that, the insured’s notice to the insurer was not prompt because it did not receive notice until three years after the accident. But, the court added, the inquiry does not end there. “[T]his Court must determine whether [the insurer] was appreciably prejudiced by that delay.” Reviewing the facts, the court held that the insurer was not “appreciably prejudiced,” even though during the three-year delay the lift truck was “not properly maintained” or “in the same condition it was at the time of the Accident.” The court observed that the insurer had “ample other evidence with which it can defend itself,” such as experts who inspected the lift truck and opined about the cause of the accident.” [Emphasis added.] Further, “there are multiple contemporaneous accident reports,” “a list of the East Coast employees on site at the time,” “photographs of the lift truck and its location when [the employee] was injured,” and “depositions of [the employee] and others regarding the events at issue.” Thus, the court held, the insurer was not prejudiced and summary judgment was inappropriate.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Timothy A. Carroll, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
The Contributors to This Blog Are Pleased to Announce That….
November 02, 2017 —
Snell & Wilmer Real Estate Litigation BlogSnell & Wilmer’s Real Estate Litigation Group, which provides the content for The Real Estate Litigation Blog, is pleased to announce that it has been recognized in both the national and metropolitan rankings by U.S. News Media Group and Best Lawyers for the 2018 edition of “Best Law Firms.” We achieved the following rankings:
- National Tier 1: Litigation – Real Estate
- Phoenix (AZ) Tier 1: Litigation – Real Estate
- Utah Tier 1: Litigation – Real Estate
- Colorado Tier 1: Litigation – Real Estate
- Reno (NV) Tier 1: Litigation – Real Estate
- Tucson (AZ) Tier 1: Litigation – Real Estate
Read the court decisionRead the full story...Reprinted courtesy of
NYC Hires Engineer LERA for Parking Garage Collapse Probe
January 29, 2024 —
James Leggate - Engineering News-RecordThe investigation into the collapse of a Lower Manhattan parking garage last April is still underway. A Jan. 2 notice published in The City Record identified LERA Consulting Structural Engineers RLLP as the engineering firm assisting with the probe.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (06/28/23) – Combating Homelessness, U.S. Public Transportation Costs and the Future of Commercial Real Estate
August 07, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, we examine the Supreme Court’s ruling regarding water supply responsibilities, the federal reserve chair’s reaction to possible banking losses, several analyses of the future of commercial real estate, and more!
- California Representative Maxine Waters has introduced several pieces of legislation aimed at combating homelessness and fixing the increasingly tumultuous affordable housing situation. (Eliza Relman, Business Insider)
- The Supreme Court ruled in favor of the federal government in a case that decided responsibility over water supply as well as the overall dissemination of water usage for the Navajo Nation. (Ariane de Vogue, CNN)
- Unlike other nations with similar construction, the United States’ public transportation has extremely high costs. (Darian Woods, Corey Bridges, Viet Le, NPR)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Nomos LLP Partner Garret Murai Recognized by Best Lawyers®
September 18, 2023 —
Garret Murai - California Construction Law BlogNomos LLP Partner Garret Murai has been recognized by Best Lawyers® in its 30th edition of The Best Lawyers in America® in the area of Construction Law for 2024. This is the the first year Garret has been recognized by Best Lawyers®.
Reprinted courtesy of
Garret Murai, Nomos LLP
Mr. Murai may be contacted at gmurai@nomosllp.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Liquidated Damages Clause Not Enforced
October 02, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPA liquidated-damages clause was not enforced in a recent case before the Georgia Court of Appeals. The clause did not contain standard provisions that would normally allow a trial court to enforce the clause as written. As a result, the trial court looked beyond the contract to determine whether the City satisfied the requirements for enforcement of the liquidated-damages clause. Below are the relevant excerpts.
City of Brookhaven v. Multiplex, LLC, A23A0843, 2023 WL 4779591 (Ga. Ct. App. July 27, 2023)
Here, the Contract provides for “Liquidated Damages at the rate of $1,000.00 per calendar day” in the last paragraph of the Scope of Work addendum. The Contract lacks, however, any language indicating that the liquidated damages were not intended to be a penalty. See Fuqua Const. Co. v. Pillar Dev., Inc., 293 Ga. App. 462, 466, 667 S.E.2d 633 (2008) (rejecting use of parol evidence where the parties “explicitly agreed” in “unambiguous contract language” that the liquidated damages were not a penalty). Absent such language, the court can look to parol evidence in the record to determine the effect the provision was intended to have. See J.P. Carey Enterprises, 361 Ga. App. at 391-392 (1) (b), 864 S.E.2d 588 (looking to “extrinsic evidence” such as emails, documents, and deposition testimony to determine whether the damages provision at issue was a penalty); see also Gwinnett Clinic, Ltd. v. Boaten, 340 Ga. App. 598, 602-603, 798 S.E.2d 110 (2017) (“Shah’s testimony also suggested that one purpose of the liquidated damages provision was to deter employees from breaching the agreement”).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
How New York City Plans to Soak Up the Rain
May 02, 2022 —
Linda Poon - BloombergWhen the remnants of Hurricane Ida pummeled New York City with more than 3 inches of rain in just one hour, the city struggled to soak it up. Instead, streets and subways flooded as storm drains were overwhelmed, basement apartments were inundated, and more than a dozen people died.
That September 2021 storm and the ones before it, including a cloudburst downpour during Tropical Storm Elsa in July, have forced New York to take a hard look at becoming a “spongier” city — one that combines nature-based green infrastructure like street-side rain gardens with gray infrastructure like storm drains to divert or absorb water and prevent catastrophic flooding.
“New York City is preparing for both chronic storm events — these cloudburst events that we see occurring more and more frequently — as well as extreme storm events like Ida,” says Jennifer Cherrier, a professor of earth and environmental sciences at Brooklyn College. On top of that, the city also faces mounting risks from storm surges, like during Hurricane Sandy in 2012.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Poon, Bloomberg
Be Proactive, Not Reactive, To Preserve Force Majeure Rights Regarding The Coronavirus
March 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesIf you are involved in construction, NOW is the time to consider the potential force majeure impacts associated with the pandemic Coronavirus. Things are beginning to drastically change on a minute-by-minute basis. From travel restrictions, to the suspension or cancellation of events on an international level, to company-wide policies and restrictions, the global uncertainty has led to the possibility that a force majeure delay will occur. Thinking otherwise is not being proactive. The Coronavirus, and the impacts / delays associated therewith, is beyond anyone’s control. Due to the uncertainty, it is hard to fathom at this time a reasonable challenge to someone’s reaction to this concern or their companywide response to the concern.
If you are a contractor, subcontractor, or even a supplier, my suggestions would be as follows:
- Revisit your contracts and see what type of force majeure language it has – anything relating to delays beyond your control or epidemics;
- Examine to see whether you have a basis for additional compensation AND additional time;
- Examine what type of notice you are required to provide for force majeure events;
- Be proactive – send notice now of the potentiality that this pandemic can impact / delay the job –no one should take offense to this letter as this pandemic has impacted all walks of life;
- If an impact occurs, send follow-up notice accordingly to ensure rights under the contract are preserved; and
- For future contracts, incorporate language that specifically addresses epidemics and pandemics now that the occurrence of this issue has become real.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com