There’s the 5 Second Rule, But Have You Heard of the 5 Year Rule?
April 23, 2024 —
Garret Murai - California Construction Law BlogThey’re called deadlines for a reason. Usually, because something really bad could happen if you fail to meet the deadline.
For those in the construction industry, you probably aware of the “deadline” to bring a claim for latent defects (10 years from substantial completion); the deadline to file suit to foreclose on a mechanics lien (90 days from the date of recording the mechanics lien), and the deadline for serving a preliminary notice (generally, 20 days from the date labor and/or materials are first furnished).
Well, here’s another deadline: Under Code of Civil Procedure section 585.310, you have 5 years after a complaint is filed to bring a case to trial, absent the court granting relief. I could leave it at that, but in the next case, Oswald v. Landmark Builders, Inc., 97 Cal.App.5th 240 (2023), was too interesting to pass up.
The Oswald Case
On June 28, 2016, homeowners Jack Oswald and Anne Seley sued their general contractor and its subcontractors alleging construction defects at their home. Answers and cross-complaints were filed and on February 2017 the trial court determined the case to be complex and appointed a discovery master. A discovery master, for those who may be unfamiliar, is usually a retired judge or third-party lawyer appointed by a court to oversee discovery in a case such as written discovery, depositions, site inspections, etc.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Bailout for an Improperly Drafted Indemnification Provision
February 11, 2019 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion came out that held that even though an indemnification provision in a subcontract was unenforceable per Florida Statute s. 725.06, the unenforceable portion is merely severed out of the indemnification clause leaving the rest of the clause intact. In essence, an otherwise invalid indemnification clause is bailed out by this ruling (which does not even discuss whether this subcontract had a severability provision that states that if any portion of any provision in the subcontract is invalid, such invalid portion shall be severed and the remaining portion of the provision shall remain in full force and effect).
This opinion arose from a construction defect case, CB Contractxors, LLC v. Allens Steel Products, Inc.,43 Fla.L.Weekly D2773a (Fla. 5thDCA 2018), where the general contractor, sued by an association, flowed down damages to subcontractors based on the contractual indemnification provision in the subcontracts. Subcontractors moved to dismiss the contractual indemnification claim because it was not compliant with Florida Statute s. 725.06. The indemnification provision required the subcontractors to indemnify the general contractor even for the general contractors own partial negligence, but failed to specify a monetary limitation on the extent of the indemnification as required by Florida Statute s. 725.06. (The indemnification clause in the subcontract was the standard intermediate form of indemnification that required the subcontractor to indemnify the general contractor for claims regardless of whether the claims were caused in part by the general contractor.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Is There Direct Physical Loss Under A Property Policy When COVID-19 is Present?
April 06, 2020 —
Tred R. Eyerly - Insurance Law HawaiiMost property policies provide coverage for property damage only when there is "direct physical loss" to covered property. Early indications are that COVID-19 remains on surfaces. The duration can last from a few hours to three weeks, depending on the type of surface material. If an employee is infected and the store or restaurant must closed because the virus may rest on surfaces within the building, is there direct physical loss, even though the building structure itself is unharmed?
To answer this question, cases from jurisdictions outside Hawaii may provide guidance. In a case from Louisiana, the homeowner had to move out of her home when excessive levels of organic lead were discovered in the kitchen, living room, master bedroom, and attic. Widder v. La. Citizens Prop. Ins. Corp., 82 So. 3d 294 (La. Ct. App. 2011). The insurer denied coverage because there was no direct physical loss. The trial court agreed; since the home was still intact, no direct physical loss had occurred, so there was no coverage under the policy. The appellate court reversed. It compared the presence of inorganic lead in the home to cases that found a direct physical loss from the existence of Chinese drywall, from which gaseous fumes were released, rendering the home unusable or uninhabitable. Physical damage was not necessary.
What if smoke from a nearby wildfire fills an outdoor theater, forcing cancellation of performances and loss of business income? This was the situation in Oregon Shakespeare Festival Ass'n v. Great Am. Inc. Co., 2016 U.S. DIst. LEXIS 74450 (D. Ore. Jun 7, 2016). Wildfires in the area caused smoke, soot, and ash to accumulate on the surface of seats and concrete ground of the open-air theater. The air quality was poor, but no federal, state or local agency ordered cancellation of the performances. Further, the theater did not suffer any permanent or structural damage to its property. The insurer denied coverage, contending that the loss or damage must be structural to the building itself. After all, the smoke in the air at the theater did not require any repairs to the structure of the property. The court disagreed. The theater sustained "physical loss or damage to property" when the wildfire smoke infiltrated the theater and rendered it unusable for its intended purpose. The decision in Oregon Shakespeare Festival was eventually vacated by a joint stipulation of the parties. Oregon Shakespeare Festival Ass'n v. Great Am. Ins.Co., 2017 U.S. Dist. LEXIS 33208 (D. Ore. March 6, 2017), but the reasoning is still sound.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Oregon Bridge Closed to Inspect for Defects
February 25, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to The Oregonian, the Morrison Bridge in Multnomah county, Oregon will be closed Sunday, February 23rd “so county crews can inspect the decking that has caused problems since it was installed” in 2012. The “southernmost eastbound lane has been closed for weeks while crews conducted inspections.”
The defects appeared “almost immediately after the project” was completed, reported The Oregonian. Drivers have “dealt with a bumpy, noisy ride as the loose decking panels flopped beneath them.”
Multnomah county has sued “Conway Construction, the company the installed the decking, as well as Strongwell Corp., the company that supplied Conway with the decking materials, and Zellcomp, the company that made the decking materials, to determine who should foot the bill for extensive repairs or outright replacement of the decking.”
Read the court decisionRead the full story...Reprinted courtesy of
Construction Warranties and the Statute of Repose – Southern States Chemical, Inc v. Tampa Tank & Welding Inc.
January 20, 2020 —
David R. Cook - AHC Construction and Procurement BlogIn a recent holding by the Georgia Court of Appeals, the court held that Georgia’s eight-year statute of repose applied to bar the project owner’s warranty claims. The renovation work by the contractor on the owner’s chemical tank constituted an improvement of real property, and thus, the statute of repose bared any claims eight years after substantial completion thereof. In addition, the court rejected the project owner’s claim that it qualified as a third-party beneficiary of an extended warranty contained in a report given by a subcontractor to the contractor.
Factual Background
In 2000, Southern States Phosphate and Fertilizer Company (“Southern States”) hired Tampa Tank & Welding, Inc (“Tampa Tank”) to renovate a tank to hold sulfuric acid. The parties’ written contract contained an express one-year warranty for material and workmanship from the date of completion. Two years later, in January 2002, the tank renovation was completed. Tampa Tank contracted with Corrosion Control Inc. (“CCI”) to design, assist with, and test the cathodic corrosion system. CCI provided only consultation and did not provide any onsite installation. Upon completion of installation, CCI supplied a report to Tampa Tank that the system was properly installed and fully functioning. Additionally, a post–installation report from CCI to Tampa Tank calculated an estimated life expectancy of forty-three to forty-five years.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Connecticut Reverses Course for Construction Managers on School Projects
August 05, 2024 —
Anand Gupta - Construction Law Zone BlogOn June 6, 2024, Connecticut Governor Ned Lamont signed into law Public Act 24-151 (H.B. 5524) (Bill 5524). Bill 5524 authorized and adjusted bonds of the state and provisions related to state and municipal tax administration, as well as addressed school building projects. Notably, Bill 5524 removed the ban on construction managers self-performing work on public school construction projects, effective July 1, 2024. Allowing construction managers to self-perform certain portions of the work, such as general trades, subject to the standard bidding requirements, is a common industry practice that, theoretically, reduces total project costs by reducing the amount of subcontracted work. However, proponents of banning self-performance argue that construction managers have too much information to bid fairly and competitively.
Reprinted courtesy of
Anand Gupta, Robinson+Cole
Mr. Gupta may be contacted at agupta@rc.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
The Big Three: The 9th Circuit Joins The 6th Circuit and 7th Circuit in Holding That Sanctions For Bad-Faith Litigation Tactics Can Only Be Awarded Against Individual Lawyers and Not Law Firms
September 03, 2015 —
Christopher B. Lloyd & Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Law v. Wells Fargo Bank, N.A. (2015 S.O.S. 13–56099 – filed August 27, 2015), the Ninth Circuit joined the shortlist of Circuit Courts to hold that sanctions for bad-faith litigation tactics under 28 U.S.C. section 1927 can only be sought against individual attorneys and not law firms. Section 1927 authorizes sanctions against “[a]ny attorney or other person admitted to conduct cases in any court of the United States … who so multiplies the proceedings in any case unreasonably and vexatiously….”
On behalf of the client, an attorney with Kaass Law filed a complaint against ten different defendants, including Wells Fargo Bank, which moved to dismiss under F.R.C.P. Rule 12(b)(6). Rather than responding to the motion to dismiss, plaintiff filed a motion to amend the initial complaint; Wells Fargo Bank filed a notice of non-opposition.
Reprinted courtesy of
Christopher B. Lloyd, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr.Lloyd may be contacted at clloyd@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Need Not Pay for Rejected Defense When No Reservation of Rights Issued
November 08, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe Massachusetts Appeals Court reversed the trial court's order that defense costs be paid for a period during which the insured rejected the defense even though no reservation of rights was issued. OneBeacon Am. Ins. Co. v. Celanese Corp., 2017 Mass. App. LEXIS 140 (Mass. App. Ct. Oct. 16, 2017).
Celanese was sued over many years for claims of bodily injury due to asbestos and chemicals allegedly contained in its products and facilities. For many years, Celanese had an agreement with its insurer, OneBeacon, for defense cost-sharing. In April 2009, Celanese terminated this agreement and demanded that OneBeacon defend the cases under the policies previously issued. OneBeacon agreed to defend without a reservation of rights. OneBeacon also agreed to waive any issues of coverage and to indemnify Celanese from any settlements of judgments up to ts full liability limits. However, OneBeacon also sought to assume full control of the defense of claims against Celanese.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at