The Benefits of Trash Talking: A Cautionary Tale of Demolition Gone Wrong
September 02, 2024 —
Joshua Levy, Anne O'Meara & Kimberly Gutierrez - Construction ExecutiveThat sinking feeling has crossed everyone’s mind at some point: "Did I accidentally throw out...?” It can happen to anyone, from valuable jewelry to uncashed checks or even (in the case of one contractor) to fire-pump control cabinets.
Demolishing the wrong equipment is a concern construction and demolition contractors should review before beginning any project. Recently, one general contractor and its demolition subcontractor would have benefitted from a more detailed “trash” talking session, which could have helped them avoid a dumpster-fire of a legal dispute.
In this case, the general contractor was contracted to renovate a hangar for a military base. The company subcontracted the demolition work to a local, family-owned contractor to demolish aspects of the hangar’s fire-suppression room. The two companies met many times, from planning to daily field walk-downs. They discussed that any equipment that was tagged with bright orange tags would remain in the fire-suppression room. The contractor also reviewed the demolition plans with the demolition company, detailing what should and should not be removed.
Reprinted courtesy of
Joshua Levy, Anne O'Meara & Kimberly Gutierrez, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Court Addresses When Duty to Defend Ends
August 24, 2020 —
Anthony L. Miscioscia & Margo E. Meta - White and WilliamsThere are certain generally held principles regarding an insurer’s duty to defend. One of these principles is that an insurer has a duty to defend its insured if the complaint states a claim that potentially falls within the policy’s coverage. However, there is a lack of consistency regarding the point at which the insurers’ duty to defend ends. When the only potentially covered claim has been dismissed, must the insurer continue to defend?
Certain jurisdictions, such as Hawaii and Minnesota, have held that an insurer’s duty to defend continues through an appeals process, or until a final judgment has been entered, disposing of the entire case. Commerce & Industry Insurance Company v. Bank of Hawaii, 832 P.2d 733 (Haw. 1992); Meadowbrook, Inc. v. Tower Insurance Company, 559 N.W. 2d 411 (Minn. 1997).
Earlier this week, the U.S. District Court for the Eastern District of Pennsylvania took a different approach to this question in Westminster American Insurance Company v. Spruce 1530, No. 19-539, 2020 U.S. Dist. LEXIS 106534 (E.D. Pa. June 17, 2020) – holding that the trial court’s dismissal of the only potentially covered claim was sufficient to terminate Westminster’s duty to defend.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams and
Margo E. Meta, White and Williams
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Ms. Meta may be contacted at metam@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Protecting and Perfecting Your Mechanics Lien when the Property Owner Files Bankruptcy
June 19, 2023 —
William L. Porter - Porter Law GroupIntroduction/Overview of the Mechanics Lien Law
The California mechanics lien is a powerful tool for contractors, subcontractors and materials suppliers to secure payment of unpaid construction debts. A contractor, subcontractor or materials supplier is allowed to record a mechanics lien on real property, based on the value added to the property by the claimant during the construction process.
The recorded mechanics lien provides the claimant with legal right to force the sale of the improved real property and thereby obtain the funds necessary to pay the delinquent debt. Under the usual procedure, the first step is the recording of mechanics lien with County Recorder’s office in the County where the property is located. A lawsuit to foreclose on the lien must then be filed in the County Superior Court of that County, within ninty (90) days after the mechanics lien is recorded. The goal of the lawsuit is to obtain a judgment for foreclosure on the mechanics lien by way of a forced sale of the property. The net proceeds of the sale will be used to pay the unpaid construction debt secured by the recorded mechanics lien, assuming that sale proceeds exceed the amount of senior liens and encumbrances.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Plans Go High Tech
April 25, 2012 —
CDJ STAFFOne construction executive described it as “the wave of the future.” What is it? Accessing building plans on an iPad. According to an article in MacWorld, several companies are now offering solutions to distribute and update construction plans on iPads. Changes to plans and notes can be distributed quickly through cloud computing.
Alan Dillon, a senior superintendent at DPR Construction told MacWorld, “I can take my iPad into the field and have my whole set of drawings.” He described a set of drawings for a large construction project as “five or six inches thick.” Danielle Douthet, of Level 10 Construction said it “can help everyone be on the same page more quickly, and make sure that everybody is working off the most current set of documents.”
And it’s not just building plans. Other firms offer building management applications designed to be taken into the field on mobile devices.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Pallonji Mistry, Indian Billionaire Caught in Tata Feud, Dies at 93
August 15, 2022 —
Bhuma Shrivastava - BloombergPallonji Mistry, the Indian-born billionaire whose engineering empire built luxury hotels, stadiums, palaces and factories across Asia and whose family’s epic showdown with the Tata Group sparked India’s biggest corporate feud, has passed away in Mumbai. He was 93.
A company spokesperson confirmed the death of the Indian tycoon after social media posts on the news spread.
Mistry and his family control the Shapoorji Pallonji Group, which started more than 150 years ago and today employs more than 50,000 people in over 50 countries, according to its website. Its landmark projects include the Reserve Bank of India and the Oberoi Hotel in Mumbai and the blue-and-gold Al Alam palace for the Sultan of Oman.
Read the court decisionRead the full story...Reprinted courtesy of
Bhuma Shrivastava, Bloomberg
The Future for Tall Buildings Could Be Greener
October 01, 2013 —
CDJ STAFFSkidmore, Owens and Merrill made its reputation by creating iconic structures of steel, concrete, and glass, but in a new report, the firm puts forth ways in which the first item would be wood. Building codes in many cities stipulate that buildings taller than four stories be built of steel and concrete, but the firm says that it has come up with a way of building structures of 30 stories or more using wood.
The tallest wood-framed building currently is only ten stories tall. In order to calculate a comparison, Skidmore, Owens and Merrill designed a forty-two story building based on the design of an existing apartment building. Actually building it would require almost 4 million board-feet of wood. Unlike a typical single-family home (and its 20,000 board-feet of wood), these building would use glue-laminated timber and slabs.
The study found that the building would weigh less than half as much, allowing a less massive foundation. If the wood came from sustainable sources, its environmental impact would be drastically reduced. They calculated that instead of 9,500 tons of CO2 emissions for the conventional tower, the wood structure would be responsible for only 2,100 tons of emissions.
Skyscrapers will continue to be a feature of large cities. But instead of urban canyons of steel and concrete, in the future those towering buildings might be made of wood.
Read the court decisionRead the full story...Reprinted courtesy of
Rebuilding the West: Construction Considerations After the Smoke Clears
December 21, 2020 —
Richard Glucksman & Ravi Mehta – Chapman Glucksman Dean & RoebWildfires have always been a part of life in the western United States, but, in recent years, the frequency and size of wildfires have become staggering. Oregon, Washington, and—in particular—California face drier conditions, making wildfire season longer and more intense.
In these states, among others, prescribed burns (designed to reduce wildfire ignition sources and spreading potential) have been limited or cancelled altogether as the air pollution emitted by these burns may worsen the impact of COVID-19, a respiratory illness in its essence, as noted recently by
Science magazine. These circumstances, further compounded by the severe shortage of housing, have created a “perfect storm” in California, which has seen new and denser construction deeper within wildfire-prone areas, prompting a number of key legislative proposals that will impact the rebuilding process after the smoke clears.
The infamous 2018 Camp Fire in northern California made international headlines for decimating the town of Paradise. While the cause of the Camp Fire was determined to be faulty electrical transmission equipment, unusually dry conditions allowed the fire to spread to just over 150,000 acres, and the fire took 17 days to contain.
Then, five of the 20 largest wildfires in California history occurred during the 2020 wildfire season, according to the California Department of Forestry and Fire Protection (Cal Fire). The Camp Fire was eclipsed by the August 2020 Complex Fire, which is the largest wildfire ever recorded in the state, growing to just over one million acres in size until it was finally contained on Nov. 15.
Legislative Response
The Camp Fire and other 2018 wildfires displaced hundreds of thousands of people from their homes throughout California. The unprecedented scale of both the 2018 and the 2020 wildfire seasons in California has spurred legislators in Sacramento to draft a number of important bills that will undoubtedly impact rebuilding efforts.
California AB 38 was prompted by the 2018 California wildfire season and was signed into law by Gov. Gavin Newsom in October 2019. It requires the state fire marshal, the Office of Emergency Services, and Cal Fire to work together to develop and administer a comprehensive wildfire mitigation program, including "cost-effective structure hardening and retrofitting to create fire-resistant homes, businesses, and public buildings."
Unfortunately, the well-intentioned program has yet to be funded, and may be relying on federal hazard funds from the Federal Emergency Management Agency at a future date. In light of the crippling economic impact of the COVID-19 pandemic, federal funding is likely the only viable source for this important item of legislation.
California SB 182 would enact new building regulations in high fire-risk areas (as determined by the state fire marshal), including new standards for fire-resistive construction, evacuation routes, defensible space, and available water and firefighting resources. It would also prohibit municipalities from approving new construction in high fire-risk areas unless wildfire reduction standards are satisfied. In effect, the bill would discourage new construction in high fire-risk areas.
After passing through both legislative houses, Newsom vetoed the bill, citing its negative impact on the state's strained supply of affordable housing. However, the bill is likely to be revisited in the 2020-2021 legislative session.
California AB 1516 is a comprehensive bill that would:
- Create new defensible-space requirements for both new and existing construction in high fire-risk areas.
- Create a grant-assistance program for fire-prevention education, inspections, and technical assistance.
- Direct Cal Fire to develop vegetation management recommendations to minimize flammability.
Additionally, the bill would allow insurers providing course of construction coverage for a project to request, from the owner, municipal certification that the structure to be built complies with existing and new building standards. Newsom vetoed this bill, cautioning that a "one size fits all" approach to wildfire management may not be appropriate, given that each individual community's needs differ.
California AB 2380 focuses on the development of standards and regulations for a relatively new and growing phenomenon: the rising use of private firefighting personnel, particularly by wealthy homeowners. Several prominent and well-known carriers offer homeowners-insurance policies that provide for private firefighting personnel, as well as preventative services (wildfire hazard inspections and clearing defensible space), and expected post-incident services (clean up and removal of fire retardant and similar substances).
AB 2380 was signed into law by Newsom at the tail end of the 2018 wildfire season, and it now requires Cal Fire, the governor's Office of Emergency Services, and the board of directors of the FIRESCOPE Program (designed to coordinate firefighting resources among different agencies) to develop standards and regulations for privately contracted fire fighters.
Housing Shortage and New Construction
These legislative efforts are underscored by the worsening housing crisis, which has both strained existing supply and increasingly pushed new construction into areas known as the Wildland Urban Interface (WUI).
WUI areas are designated as either "interface" or "intermix:” Interface WUI areas have little to no wildland vegetation, but are near large wildlands. By contrast, in intermix WUI areas, structures are mixed with wildland vegetation.
A recent study by the U.S. Forest Service found that, as expected, WUI areas are the hardest hit by wildfires. However, the study also found that, contrary to popular belief, wildfires cause greater damage in interface WUI areas than intermix WUI areas- in other words, wildfire damage is greatest where there is little to no wildland vegetation. The study concludes that wildfires in WUI areas are fueled more by human-made fuels as opposed to natural vegetation. These human-made fuels include building materials and landscaping.
It may not come as a surprise that a growing body of scientific literature has ascribed more severe and frequent wildfires to climate change. However, what may be less appreciated is the profound impact of building in the WUI. By 2050, an estimated one million new homes are projected to be built in California WUI areas.
In light of this, as well as the recognition that wildfire risk is determined, in large part, by construction standards and the fire resistivity of materials as opposed to natural vegetation, California has developed a special building code for WUI areas: Chapter 7A of the California Building Code- Materials and Construction Methods for Exterior Wildfire Exposure. California is one of the few states to have a unique building code for WUI areas, and, in light of the recent wildfires, California officials are developing stricter WUI building standards.
The constituents of State Sen. Bill Dodd in Napa County and surrounding areas have faced some of the state's most devastating wildfires. Dodd is at the forefront of significant fire-related legislation, and was responsible for the passage of the Insurance Adjuster Act of 2019, which sets regulations for insurance-claim adjusting in emergencies.
Dodd also spearheaded the passage of SB 190, which was enacted in late 2019. The law requires, among other things, the state fire marshal to develop suitable materials and products for building in WUI areas with respect to exterior wall siding and sheathing, exterior windows, doors and skylights, vents, decking, treated lumber and ignition-resistant materials, and roofing materials. The state fire marshal's office found that roofing material is among the most important factors in a structure's fire resistivity, and slate, metal, and tile roofs have the highest fire resistance rating of "A:”
As of July 1, 2021, wood-shake roofs will no longer be allowed by the California Fire Code. The state fire marshal also cites non-combustible siding as an important building element.
Wildfire-Resistant Construction
A recent study prepared by Headwaters Economics and commissioned by the U.S. Forest Service, WR Foundation, and Insurance Institute for Business & Home Safety analyzed cost differentials between traditional construction and wildfire-resistive construction as they relate to the four most fire-critical assemblies of a structure: roofs, exterior walls (including windows and doors), decks, and landscaping. Wildfire-resistant roofing, vents, fascia, and gutters were estimated to cost about 27 percent more than traditional components. However, the wildfire-resistant roofing materials feature lower maintenance requirements and longer lifespans.
Wildfire-resistant exterior walls were estimated to cost 25 percent less than traditional components, due in large part to the substitution of true wood siding with fiber cement siding.
Wildfire-resistant decking involves the use of composite boards, foil-faced bitumen tape on support joists, and the creation of non-combustible space beneath decking. This type of construction was estimated to cost approximately 19 percent more than traditional decking construction. Wildfire-resistant landscaping has the most significant cost difference as compared to traditional landscaping construction, with the former costing about double the latter. Landscaping fabric can minimize the growth of weeds and thus reduce fire hazard, as does the use of rocks instead of mulch.
While certain components of fire-resistant construction may have increased costs, the benefits far outweigh these increases: longer life cycles and less maintenance of the components, and, most importantly, greatly increased fire resistivity of the structure itself and thus its life cycle.
As construction in WUI areas is expected to grow substantially in the coming years, so too are fire-resistive construction standards and material requirements. These standards and requirements are part and parcel of a more comprehensive and deliberate set of land use planning, vegetation management, and emergency-response regulations and policies that California will develop by necessity to meet the growing demand for housing in WUI areas, and also to rein in the staggering costs of wildfire suppression. Thus, construction in WUI areas, and, to a lesser degree, in non WUI areas, will be subject to more exacting standards in the years to come.
As the science of wildfire prevention and suppression advances, so too will the technological innovations that will allow for safer, longer-lasting and ecologically sensitive construction. As in many other fields, California is expected to emerge as a leader in wildfire resistant building and material requirements, and will undoubtedly play a key role in shaping fire policy throughout the United States.
Richard Glucksman is a partner, and Ravi Mehta is senior counsel, at Chapman Glucksman Dean & Roeb. rglucksman@cgdrlaw.com; rmehta@cgdrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
After Breaching its Duty to Defend, Insurer Must Indemnify
August 11, 2011 —
Tred R. Eyerly - Insurance Law HawaiiIn a brief decision analyzing Oregon law, the Ninth Circuit determined that once an insurer breaches its duty to defend, it must indemnify. See Desrosiers v. Hudson Speciality Ins. Co., 2011 U.S. App. LEXIS 12591 (9th CIr. June 21, 2011).
The victim secured a judgment against the insured after he was beaten by another patron outside the insured's bar. Hudson Speciality Insurance refused to defend the insured, claiming the injury arose from an assault and battery, which excluded coverage.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of