California Subcontractor Gets a Kick in the Rear (or Perhaps the Front) for Prematurely Recorded Mechanics Lien
October 21, 2019 —
Garret Murai - California Construction Law BlogCalifornia provides three statutorily recognized construction payment remedies: (1) mechanics liens; (2) stop payment notices; and (3) payment bond claims. Each is intended to provide payment protections for those who furnish labor, materials and services on a construction project. However, each is also different in important ways.
One of those differences has to do with timing. Specifically, when the statutory payment remedy may be used by a claimant. Stop payment notices can be served at any time during a project even before a claimant has completed its work. However, mechanics liens may only be recorded and payment bond claims may only be made after a claimant has completed or ceased performing its work.
In Precision Framing Systems, Inc. v. Luzuriaga, Case No. E069158 (August 29, 2019), the 4th District Court of Appeal examined whether a subcontractor had prematurely recorded a mechanics lien and, thereby, was prevented from filing a lawsuit to foreclose on its mechanics lien.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Challenging and Defending a California Public Works Stop Payment Notice: Affidavit vs. Counter-Affidavit Process
October 21, 2019 —
William L. Porter - Porter Law GroupOne of the most effective collection procedures available to subcontractors and suppliers to California Construction projects is the “stop payment notice” procedure found under California Civil Code sections 9350 – 9364. Under this procedure, the unpaid subcontractor or supplier may serve the stop payment notice on the public entity and the direct or “prime” contractor and cause the public entity to withhold from the direct contractor 125% of the funds identified in the stop payment notice. Thereafter, funds will not generally be released unless the parties reach a settlement agreement or the issue is decided through litigation, arbitration or mediation. There is however an alternative procedure available to direct contractors to expedite the determination of whether a stop payment notice is valid and to possibly obtain an early release of the funds withheld by the public entity. This “summary proceeding” process could result in release of funds to the direct contractor in less than 30 days. The summary proceeding can also be challenged by the unpaid subcontractor or supplier. All public works contractors, subcontractors and suppliers should be aware of the process. The process for direct contractors to release a stop payment notice and for subcontractors and suppliers to challenge the process works as follows:
After a California stop payment notice has been served and the public entity has withheld funds accordingly, the direct contractor may challenge the stop payment notice by serving an “affidavit” (basically a sworn statement showing why the stop notice is not valid) on the public entity, demanding that the public entity release all funds withheld. Upon receipt of such an affidavit, the public entity will serve the subcontractor or supplier who served the stop payment notice with a copy of the affidavit, along with a “demand for release of funds”. If the stop payment notice claimant does not respond with a “counter-affidavit” by the date stated on the notice sent by the public entity (“not less than 10 days nor more than 20 days after service on the claimant of a copy of the affidavit”), then the public entity will be within its rights to release the withheld funds to the direct contractor, and the stop payment notice claimant will relinquish its stop payment notice rights.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Judgment Proof: Reducing Litigation Exposure with Litigation Risk Insurance
March 04, 2024 —
Latosha M. Ellis & Charlotte Leszinske - Hunton Insurance Recovery BlogIt is not just your imagination: verdicts are getting bigger. So-called “nuclear verdicts” have increased in size and frequency over the past decade, particularly after the COVID-19 pandemic. Litigation risk insurance is a little known, but highly effective, option meant to compliment traditional insurance products and provide additional protection for policyholders nervous about litigation exposure.
Unfortunately, it is difficult to predict the exposure presented by any particular case. Between 2020 and 2022, the median
verdict increased 95%—from $21.5 million to $41.1 million. In
2022, a jury handed down a verdict worth $7.3 billion for injury to a single plaintiff. Even if an injury or loss is minor, juries have shown that they are willing to penalize corporate defendants with punitive damages that significantly exceed the award of compensatory damages. With such uncertainty and millions (if not billions) at stake, companies can reduce risk with litigation risk insurance.
Three key types of litigation risk insurance include: (1) punitive wrap insurance, (2) adverse judgment insurance, and (3) judgment preservation insurance.
Reprinted courtesy of
Latosha M. Ellis, Hunton Andrews Kurth and
Charlotte Leszinske, Hunton Andrews Kurth
Ms. Ellis may be contacted at lellis@HuntonAK.com
Ms. Leszinske may be contacted at cleszinske@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurance Policy to Protect Hawaii's Coral Reefs
December 26, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe New York Times recently reported on an insurance policy issued to the non-profit Nature Conservancy to protect coral reefs in Hawaii. Cihistopher Flavelle, Catrin Einhorn, In a First, Nonprofit Buys Insurance for Hawaii's Threatened Coral Reefs, N.Y. Times, Nov. 21, 2022.
If damaged by a storm, coral reefs need immediate attention if they are going to recover. The Nature Conservancy plans a four step process to save damaged reefs:
- Purchase a policy for all 400,000 acres of coral reefs surrounding the Hawaii island.
- If reefs are sufficiently damaged by a storm the policy will pay out within two weeks.
- The Nature Conservancy will ask the State of Hawaii, owner of the reefs, for a permit to repair the storm damage.
- Finally, if the state officials issue the permit, the insurance proceeds will pay teams of divers to repair the damage. Crews will have about six weeks before coral begins to die.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Nine Newmeyer & Dillion Attorneys Recognized as Southern California Super Lawyers
February 11, 2019 —
Newmeyer & Dillion LLPProminent business and real estate law firm Newmeyer & Dillion LLP is pleased to announce that nine of its Newport Beach attorneys have been selected to the 2019 Southern California Super Lawyers list. Each year, no more than 5 percent of lawyers are selected to receive this honor.
Attorneys named to the Southern California Super Lawyers list include:
Michael Cucchissi
Jeff Dennis
Greg Dillion
Joseph Ferrentino
Charles Krolikowski
John O'Hara
Jane Samson
Michael Studenka
Paul Tetzloff
Super Lawyers is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high-degree of peer recognition and professional achievement. The patented selection process includes independent research, peer nominations and peer evaluations.
About Newmeyer & Dillion
For almost 35 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, privacy & data security and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client's needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
U.K. Construction Growth Unexpectedly Accelerated in January
February 05, 2015 —
Tom Beardsworth – Bloomberg(Bloomberg) -- U.K. construction growth unexpectedly accelerated last month as housing strengthened and civil engineering bounced back from a contraction.
Markit Economics said its Purchasing Managers’ Index rose to 59.1 from 57.6 in December. A reading above 50 indicates expansion. Economists forecast the gauge would fall to 57, according to the median estimate in a Bloomberg News survey.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Beardsworth, BloombergMr. Beardsworth may be contacted at
tbeardsworth@bloomberg.net
Notice of Completion Determines Mechanics Lien Deadline
August 13, 2019 —
William L. Porter - Porter Law GroupThe California Mechanics Lien is one of the most valuable collection devices available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California Private Works project. The mechanics lien allows the claimant to sell the property where the work was performed in order to obtain payment. The process starts with the recording of a mechanics lien in the office of the County Recorder where the property in question is located. As noted below, certain deadlines must be met.
Know Your Mechanics Lien Filing Deadlines Generally
Working within deadlines is absolutely crucial to preserving mechanics lien rights under California law. The deadlines differ, depending on whether you are a ”direct” contractor, also known as “original” or “prime” contractor (one who contracts directly with the property owner) or a subcontractor or material supplier. The primary differences are that, the direct contractor is only required to serve the “Preliminary Notice” on the Construction Lender (Civil Code section 8200-8216), whereas the subcontractor and material supplier must serve not only the Construction Lender, but also the Owner and Direct Contractor (see Civil Code section 8200(e)). Another difference is that a direct contractor has a longer period of time in which to record a mechanics lien after a valid “notice of completion” or a “notice of cessation” has been recorded (Civil Code sections 8180-8190), (60 days for original contractors as compared to 30 days for subcontractors and suppliers – See Civil Code sections 8412 and 8414). A further general description of the rules is as follows:
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
The Enforceability of “Pay-If-Paid” Provisions Affirmed in New Jersey
January 04, 2023 —
Levi W. Barrett, Michael S. Zicherman & Brian Glicos - Peckar & Abramson, P.C.On December 7, 2022, the Appellate Division affirmed the New Jersey Superior Court decision in Jersey Precast v. Tricon Enterprises, Inc. et al., finding that the “pay-if-paid” clause in a material supplier’s purchase order with a general contractor was binding and enforceable. While clauses conditioning a general contractor’s obligation to pay its subcontractors on the general contractor’s receipt of payment from the project owner are not unique – this is the first time that a court in New Jersey has affirmed this practice in a published opinion. [1]
Background
The general contractor, Tricon, sent Jersey Precast its standard form purchase order for the supply of prestressed box beams to fulfill a public improvement contract with Union County. The reverse side of the form purchase order contained standard terms and conditions, and included a pay-if-paid clause drafted by Michael Zicherman, a partner of Peckar & Abramson, P.C. While Jersey Precast provided some draft revisions to the terms and conditions, Tricon never signed the purchase order and the proposed revisions were never accepted. Significantly, Jersey Precast did not attempt to modify the pay-if-paid provision. It later developed that the construction of the project became impossible, and the beams fabricated by Jersey Precast were not used. Tricon invoiced Union County for the cost of the beams, but the County failed to make payment and refused to accept delivery of the beams.
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Michael S. Zicherman, Peckar & Abramson, P.C. and
Brian Glicos, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Zicherman may be contacted at mzicherman@pecklaw.com
Mr. Glicos may be contacted at bglicos@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of