Does the Miller Act Trump Subcontract Dispute Provisions?
May 16, 2018 —
Christopher M. Horton - Smith CurrieAll general contractors performing public building or public works contracts with the federal government must be familiar with the Miller Act. It is a requirement for doing business with the federal government. Pursuant to the Miller Act, a general contractor entering into a public building or public works contract with the federal government must furnish a payment bond in an amount equal to the contract price, unless the contracting officer determines that it is impractical to obtain a bond in that amount and specifies an alternative bond amount.
Miller Act payment bonds guarantee payment to certain subcontractors and suppliers supplying labor and materials to contractors or subcontractors engaged in the construction. As a result, subcontractors have an avenue of relief should they not get paid for work done on the project. Specifically, subcontractors have a right to bring an action against the surety within 90-days after the date on which the person did or performed the last labor or furnished or supplied the last of material for which the claim is made. Any such action must be brought no later than one year after the date on which the person did or performed the last labor or furnished or supplied the last of material. 40 United States Code § 3133.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher M. Horton, Smith CurrieMr. Horton may be contacted at
cmhorton@smithcurrie.com
A Survey of Trends and Perspectives in Construction Defect Decisions
November 27, 2013 —
CDJ STAFFThomas F. Segella, Ellen H. Greiper, and Matthew S. Lerner, partners at the firm Goldberg Segalia, together with Suzin L. Raso, an associate of the firm, have prepared a wide-ranging survey of cases, in their commentary, “Emerging Trends and Changing Perspectives on Construction Defect Claims.
The authors examine 11 coverage cases, representing decisions from eight states, and 15 cases of litigation, here covering 11 states. In each case, they give a one-sentence summary, a further discussion of the case, and they end with a practice note.
They start with Alabama, noting that the court found that “faulty workmanship is not an occurrence,” looking at the recent case of Owners Insurance Co. v. Jim Carr Homebuilders, LLC. Here they note that under Alabama law, “there was no damage to personal property or property of others; therefore, there was no ‘occurrence.’” They also note that “the policy involved did not contain a ‘subcontractor exception.’”
In Georgia, they noted, the courts concluded that “damage to insured’s completed work is an ‘occurrence.’” Here they cite a recent decision of the Georgia Supreme Court, noting that the court looked at cases from Connecticut, South Carolina, Illinois, Texas, as well as the Fourth and Tenth Circuits.
Under litigation, they look at such aspects of construction defect litigation such as the application of the economic loss doctrine in Kansas and Florida, and how the courts view arbitration agreements in states including New Jersey, Louisiana, and Colorado.
Read the court decisionRead the full story...Reprinted courtesy of
Giant Gas Pipeline Owner, Contractor in $900M Payment Battle
January 22, 2024 —
David Godkin, Debra K. RubinA Canadian partnership including energy developer TC Energy that is building the $10.6-billion Coastal GasLink pipeline, and a key project contractor, are disputing more than $900 million in project costs in court and in upcoming arbitration. The 670-kilometer line in British Columbia that announced mechanical completion last year is set to carry liquefied natural gas to the LNG Canada export terminal under construction on the province’s Pacific Coast—the country’s first such facility.
Reprinted courtesy of
David Godkin, Engineering News-Record and
Debra K. Rubin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
OSHA’s COVID-19 Emergency Temporary Standard Is in Flux
December 06, 2021 —
Megan E. Baroni & Jonathan H. Schaefer - Construction ExecutiveOn Friday, Nov. 5, 2021, Occupational Safety and Health Administration’s COVID-19 Vaccination and Testing Emergency Temporary Standard was issued, with most requirements set to go into effect on Dec. 5. The ETS applies to employers with a total of 100 or more employees company-wide. Employers covered by the ETS would be required to develop, implement and enforce a mandatory vaccination policy, subject to limited exemptions, or allow unvaccinated employees to test regularly and be subject to a mask policy, among other associated recordkeeping, reporting and training requirements.
Almost immediately, the ETS was hit with a number of legal challenges in various courts across the country. On November 6, just a day after the ETS was issued, the U.S. Circuit Court of Appeals for the Fifth Circuit issued an order staying the implementation of the ETS until further notice. The Court’s order was not a final ruling on the validity of the ETS but has halted implementation of the ETS, at least for the time being. Other legal challenges are already in process, further complicating the issue of if and when the ETS will become effective.
As of November 2021, the ETS is on hold, at least temporarily. That could change any day and the ETS could be back in effect, in whole or in part, or permanently halted. The legal challenges to the ETS are unlikely to end, or diminish, until the Supreme Court has weighed in, making for a few uncertain months ahead.
Reprinted courtesy of
Megan E. Baroni and Jonathan H. Schaefer, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Ms. Baroni may be contacted at mbaroni@rc.com
Mr. Schaefer may be contacted at jschaefer@rc.com
Read the court decisionRead the full story...Reprinted courtesy of
Foundation Arbitration Doesn’t Preclude Suing Over Cracks
March 28, 2012 —
CDJ STAFFThe Louisiana Court of Appeals has reversed the decision of a lower court, allowing a construction defect case to go through. In Greer v. Town Construction Company, the Greers hired Town Construction to build a home in Baton Rouge. The business relationship went sour, with disputes over “costs, change orders, workmanship, and timeliness issues.”
Town Construction filed an arbitration claim for the unpaid contract balance. In the counterclaim, the Greers made claims of mold and mildew problems, and wall cracks that they attributed to a “structural defect in the foundation.” In arbitration, Town Construction was awarded the full contract balance plus extra costs and interest, while the Greers were awarded for their structural claims.
Three years later, the Greers found additional cracks and filed a suit against Town Construction. Town Construction argued that the Greer’s lawsuit should be dismissed, as the claims had already been through the arbitration process. The district court agreed with Town Construction and dismissed the suit.
The appeals court noted that the Greers would have no ground for a suit if the arbitration was a “valid and final judgment,” and went on to note that there was no evidence in the trial record that the arbitration met this qualification. The court noted that although it was clear that both parties had agreed to the decisions of the arbiter, under Louisiana law, arbitration is not final until it has been “rendered by a court with jurisdiction over subject mater and over parties.”
The court remanded the case to the lower court, noting that “the district court is obligated to first determine whether a valid arbitration award is in existence and had been confirmed before considering the merits of the exception. The court noted that their decision “should not be read to express any opinion as to the merits of the claims or as to the propriety of damages sought in the Greer’s lawsuit.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Message from the Chair: Kelsey Funes (Volume I)
November 06, 2023 —
Marissa L. Downs - The Dispute ResolverI am so honored to assume the Division 1 mantle from my friend, Tom Dunn, and look forward to carrying on his good work.
For those of you who don’t know me, I’d like to take this opportunity to share a bit about my background. I grew up in New Orleans and went to LSU for undergraduate and law school. (Geaux Tigers!) I started my practice in 1997 at Phelps Dunbar LLP in Baton Rouge, where I still practice today. I manage the litigation group in the Baton Rouge office of the firm. I practice as a construction lawyer full time and serve on the Construction Panel of the American Arbitration Association and serve as a mediator in construction cases.
I am married to Dr. Chris Funes (the world’s best pediatrician) and we are the parents to two high schoolers. My son is a high school senior and my daughter is a sophomore. So, when I am not lawyering, I have been spending my time lately touring colleges, prepping for homecoming, and helping to teach my daughter to drive (all very relaxing!!). We also have a very sweet (and very hairy) rescue dog, Maggie, who makes sure we get lots of walks.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Five Facts About Housing That Will Make People In New York City and San Francisco Depressed
February 26, 2015 —
Flavia Krause-Jackson and Alexandre Tanzi – BloombergIf you live in New York or San Francisco, you should spend some time mining the latest crop of home price data -- starting with the Standard & Poor’s Case-Shiller indices. Then, pull out your last rent check. It might be enough to make you move.
Here are a few things to get you thinking:
1. What you pay for parking in New York can buy a cheap home in Chicago
The cheapest tier of homes in the Windy City were valued at less than $170,368 in November, the Case-Shiller tiered-price indices show (there are three tiers: low, middle and high). That compares to the $136,052 average price tag for parking space in New York last year, according to Jonathan J. Miller, the president of the appraisal firm Miller Samuel and a Bloomberg View contributor.
Reprinted courtesy of
Flavia Krause-Jackson, Bloomberg and
Alexandre Tanzi, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Fire Fears After Grenfell Disaster Set Back Wood Building in UK
May 29, 2023 —
Olivia Rudgard - BloombergThis article is part of the Bloomberg Green series Timber Town, which looks at the global rise of timber as a low-carbon building material.
To get fire department approval for their six-story London office project made of strong engineered wood known as
mass timber, Theo Michell and Richard Walker had to build a full-scale section of it in the UK, ship it to Poland and attempt to set it on fire.
The mockup was set alight “with enough material that replicates the fire load that you get from furniture and carpets and desks, and all the rest of it, and you see how that structure performs,” says Michell.
“It was cool,” adds Walker. “It looked amazing.”
Their building, called Paradise, passed the fire test and is under construction, though not without a significant drag on their budget and time.
Read the court decisionRead the full story...Reprinted courtesy of
Olivia Rudgard, Bloomberg