Alabama Court Upholds Late Notice Disclaimer
August 20, 2018 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Evanston Ins. Co. v. Yeager Painting, LLC, 2018 U.S. Dist. LEXIS 130316 (N.D. Ala. Aug. 3, 2018), the United States District Court for the Northern District of Alabama had occasion to consider an insured’s reporting obligations under a general liability policy.
Evanston’s insured, Yeager, was hired to sandblast water tanks, and in turn, subcontracted out the work to a third party. On May 19, 2012, an employee of the subcontractor was severely injured in connection with a work-site accident. It is not entirely clear when Yeager provided notice of occurrence to Evanston, although Evanston advised by letter dated January 30, 2013 that it would be further investigating the matter subject to a reservation of rights. Evanston subsequently denied coverage by letter dated April 10, 2013, the disclaimer based on a subcontractor exclusion on the policy. Notably, Evanston’s letter advised that Yeager should immediately contact Evanston if any facts changed or if it had any additional information concerning the matter.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub Lieberman Straus & Shrewsberry LLPMr. Margolies may be contacted at
bmargolies@tlsslaw.com
Insurer in Bad Faith For Refusing to Commit to Appraisal
October 08, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court denied State Farm's motion for summary judgment on the insured homeowners' bad faith claim for State Farm's failure to agree to an appraisal. Currie v. State Farm Fire and Cas. Co., 2014 WL 4081051 (E.D. Pa. Aug. 19, 2014).
Superstorm Sandy caused a tree to crash in the insureds' home. The loss was reported to State Farm. The State Farm adjuster verbally quoted the roof replacement at more than $100,000. State Farm eventually paid $60,000 for the roof replacement. The insureds' adjuster estimated the loss at $363,804.98.
The insureds demanded an appraisal. State Farm rejected the demand because the claim involved certain items for which State Farm did not admit liability, including damage to the interior hardwood floors. State Farm contended that since the dispute went beyond the amount of loss, an appraisal was not an appropriate method of resolution.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Solar Power Inc. to Build 30-Megawatt Project in Inner Mongolia
October 15, 2014 —
Justin Doom – BloombergSolar Power Inc. (SOPW), a renewable-energy developer backed by China’s LDK Solar Co., has agreed to build a solar farm with 30 megawatts of capacity in Inner Mongolia.
Solar Power’s Xinyu Xinwei New Energy unit signed a construction agreement with Alxa League ZhiWei PV Power Co., the Roseville, California-based company said today in a statement. The project is expected to connect to the power grid by the end of March. Financial terms weren’t disclosed.
It’s Solar Power’s second accord this month to build a project in China’s Inner Mongolia Region. Solar Power also is building a 20-megawatt power plant in Wulaichabu City.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Doom, BloombergMr. Doom may be contacted at
jdoom1@bloomberg.net
Don’t Let Construction Problems Become Construction Disputes (guest post)
October 01, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaTo start our week off right, today we have another important article from guest blogger Christopher G. Hill, LEED AP. Chris is a Virginia Supreme Court certified mediator, construction lawyer and owner of the Richmond, VA firm, The Law Office of Christopher G. Hill, PC. He authors the Construction Law Musings blog where he discusses legal and policy issues relevant to construction professionals. His practice concentrates on mechanic’s liens, contract review and consulting, occupational safety issues (VOSH and OSHA), and risk management for construction professionals. [His blog was also one of the first construction law blogs I found and followed, even if he is a Duke alum!] Take it away, Chris!
First and foremost, thanks to Melissa for inviting me back to post here at her great blog. She continues to invite me back despite my being a Blue Devil (and I try not to hold her Tar Heel status against her).
So much of discussion relating to construction law and construction lawyers centers on the litigation of disputes. This discussion comes in many forms from avoidance of such litigation through the early intervention of good counsel prior to getting into a project to what sort of resolution mechanism to use. Another branch of this discussion is essentially the right way to pursue your claim (or as some may read it start the dispute ball rolling). Sometimes a payment bond claim is the best method while others a straight up contractual suit is the best way to go.
Of course, all of this discussion presumes that there will be disputes. While I agree to some degree that in the Murphy’s Law riddled world of commercial construction, problems will arise. These problems need not rise to the level of a dispute that requires outside (read court or arbitrator) intervention. A few tips that are easy to write, but admittedly hard to practice at times can hopefully keep problems from blossoming into disputes. I’ve listed three big ones here:
1.Use “in house counsel.” Yes, I know that most of you engineers, architects, commercial general contractors and subcontractors out there aren’t big enough to either want or need a full time attorney on the payroll. What I mean by this is that when problems occur (or preferably before doing so), give your friendly local construction lawyer a call. As I learned from my dad, an ounce of prevention and all that. That 10 minute phone call may help avoid many hours of time and bills from your attorney later down the road.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to Las Vegas Team on Their Successful Motion for Summary Judgment!
May 06, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPThis case arose from an alleged trip and fall on an uneven surface in a parking lot outside of BWBO’s client’s restaurant. Plaintiff alleged more than $385,000 in past medical specials (with high potential for future care and treatment) with exposure in excess of $1,000,000.00. The Plaintiff named as Defendants BWBO’s client as well as several entities related to their landlord.
Early in the case, Las Vegas Partner Jeffrey W. Saab and Senior Associate D. Ryan Efros moved for summary judgment based on terms of the restaurant’s lease. They argued that based on the lease, the duty to maintain the surface of the parking lot fell exclusively to the landlord, rather than the restaurant’s client. Plaintiff opposed the motion arguing that the prevailing case law held that any agreement between a tenant and its landlord does not preclude a plaintiff from asserting either or both defendants breached their duties of care. Jeff and Ryan distinguished that case and successfully persuaded the Court that there could be no contractual duty and no common law duty to maintain the parking surface, clearing the way for the court to grant summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Axa Unveils Plans to Transform ‘Stump’ Into London Skyscraper
June 17, 2015 —
Patrick Gower – BloombergPlans for a skyscraper at 22 Bishopsgate in the City of London go on show for the first time today before developers Axa Real Estate and Lipton Rogers seek planning approval.
Axa bought the site in February, three years after work halted on the tower during the financial crisis. The plot became known as “the stump” because only the foundations, basements and the lift core up to level nine were built.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Gower, Bloomberg
Conspirators Bilked Homeowners in Nevada Construction Defect Claims
March 28, 2012 —
CDJ STAFFCourthouse News has a summary of the current lawsuit over a Nevada conspiracy to defraud homeowners by taking control of homeowner boards and then providing inadequate repairs. Homeowners in eight Las Vegas area communities are involved in the suit, which claims that the conspirators purchased units in the communities and then transferred fractional interests to others to allow them to run for HOA board elections. The suit claims that David Amesbury and his firm helped manipulate the elections.
Once homeowner boards were controlled by the conspirators, Nancy Quon, the construction defect attorney whose recent death appears to be by suicide, handled the litigation against homebuilders. She would settle out of court, engaging Silver Lining Construction to “do very minor and superficial repairs” to the homes. The remainder of the money was split by the conspirators. The suit also notes that the construction defect claims were “frivolous,” and?in addition to the negative publicity?caused the homes to lose at least 5% of their value.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of