The Trend in the Economic Loss Rule in Construction Defect Litigation
January 14, 2015 —
Beverley BevenFlorez-CDJ STAFFHeather Howell Wright of Bradley Arant Boult Cummings LLP, analyzed the Massachusetts Supreme Court decision in Wyman v. Ayer Properties, LLC, which ruled that the “economic loss rule is not applicable to the damage caused to the common areas of a condominium building as a result of the builder’s negligence.” Wright compared Wyman to last year’s Florida Supreme Court case, Tiara Condominium Association v. Marsh & McLennan Companies that decided “that the economic loss rule did not preclude a condominium association from asserting a negligence claim against a contractor for defective work.”
Wright concluded that “[t]he Wyman decision is another ruling in a growing line of cases where courts have limited application of the economic loss rule and have held that a contractor can be liable in tort for defective work.”
Read the court decisionRead the full story...Reprinted courtesy of
Hurdles with Triggering a Subcontractor Performance Bond
April 05, 2017 —
David Adelstein – Florida Construction Legal UpdatesThere have been a couple of decisions as of late, particularly in federal court, that have gone in favor of a performance bond surety and against a general contractor’s claim against a subcontractor’s performance bond. These decisions have been so unfavorable that they may be swaying certain internal decisions to move to subcontractor default insurance with, perhaps, subcontractors that pose less risk. From the general contractor’s perspective, if they have to stop the management of the job and progress to jump through hoops to trigger the performance bond’s obligations, rightfully or wrongfully, the bond may not provide them the value they need. Performance bonds are an appropriate product in many instances, but there should be more consistency regarding the actual trigger of a subcontractor’s performance bond obligations. Project teams need to absolutely understand what efforts they need to take, and how they need to take such efforts, in order to properly trigger a performance bond’s obligations. This is a must (and I have presented many seminars on this very issue). Or, the general contractor should move away from the traditional AIA /standard performance bond form, which is the direction I always go when I am involved in the drafting of a performance bond.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Housing Bill Threatened by Rift on Help for Disadvantaged
April 09, 2014 —
Cheyenne Hopkins and Clea Benson - BloombergEfforts to overhaul the U.S. housing-finance system could hinge on how far Congress is willing to go to ensure that young, low-income and minority homebuyers can get mortgages.
A bipartisan bill drafted by Senate Banking Committee leaders Tim Johnson and Mike Crapo relies on incentives to persuade financiers to lend to groups with higher risk profiles. Consumer and civil-rights organizations are pushing instead for a mandate that those groups must be served, a concept that has become a political flash point since the housing bubble burst.
Key Democrats on the banking panel whose support is needed to pass the measure may vote against a bill that doesn’t include a mandate, especially as mortgage borrowing has dropped among blacks, Latinos and first-time buyers.
Ms. Hopkins may be contacted at chopkins19@bloomberg.net; Ms. Benson may be contacted at cbenson20@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Cheyenne Hopkins and Clea Benson, Bloomberg
Leveraging the 50-State Initiative, Connecticut and Maine Team Secure Full Dismissal of Coverage Claim for Catastrophic Property Loss
March 23, 2020 —
Regen O'Malley - Gordon & Rees Insurance Coverage Law BlogOn behalf of Gordon & Rees’ surplus lines insurer client, Hartford insurance coverage attorneys Dennis Brown, Joseph Blyskal, and Regen O’Malley, with the assistance of associates Kelcie Reid, Alexandria McFarlane, and Justyn Stokely, and Maine counsel Lauren Thomas, secured a full dismissal of a $15 million commercial property loss claim before the Maine Business and Consumer Court on January 23, 2020. The insured, a wood pellet manufacturer, sustained catastrophic fire loss to its plant in 2018 – just one day after its surplus lines policy expired.
Following the insurer’s declination of coverage for the loss, the wood pellet manufacturer brought suit against both its agent, claiming it had failed to timely secure property coverage, as well as the insurer, alleging that it had had failed to comply with Maine’s statutory notice requirements. The surplus lines insurer agreed to extend the prior policy several times by endorsement, but declined to do so again. Notably, the insured alleged that the agent received written notice of the non-renewal prior to the policy’s expiration 13 days before the policy’s expiration. However, the insured (as well as the agent by way of a cross-claim) asserted that the policy remained effective at the time of the loss as the insured did not receive direct notice of the decision not to renew coverage and notice to the agent was not timely. Although Maine’s Attorney General and Superintendent intervened in support of the insured’s and agent’s argument that the statute’s notice provision applied such that coverage would still be owed under the expired policy, Gordon & Rees convinced the Court otherwise.
At issue, specifically, was whether the alleged violation of the 14-day notice provision in Section 2009-A of the Surplus Lines Law (24-A M.R.S. § 2009-A), which governs the “cancellation and nonrenewal” of surplus lines policies, required coverage notwithstanding the expiration of the policy. The insured, the agent, and the State of Maine intervenors argued that “cancellation or nonrenewal” was sufficient to trigger the statute’s notice requirement, and thus Section 2009-A required the insurer to notify the insured directly of nonrenewal. In its motion to dismiss, Gordon & Rees argued on behalf of its client that Section 2009-A requires both “cancellation and nonrenewal” in order for the statute to apply. Since there was no cancellation in this case – only nonrenewal – Gordon & Rees argued that Section 2009-A is inapt and that the insurer is not obligated to provide the manufacturer with notice of nonrenewal. Alternatively, it argued that the statute is unconstitutionally vague and unenforceable.
Read the court decisionRead the full story...Reprinted courtesy of
Regen O'Malley, Gordon & ReesMs. O'Malley may be contacted at
romalley@grsm.com
Homeowner may pursue negligence claim for construction defect, Oregon Supreme Court holds
March 01, 2011 —
Lori Bauman, Ater Wynne LLPIn Abraham v. T. Henry, Oregon’s court of appeals held that a Oregon’s court of appeals holds that a homeowner may sue builder for common law negligence absent a contractual provision that forecloses such a claim. Plaintiff homeowners hired defendant contractors to build a house. When plaintiffs discovered defects in the construction years later, they sued for negligence.
The Court of Appeals held that the parties’ contractual relationship did not prevent a negligence claim, and that plaintiffs were entitled to pursue a negligence per se claim based on a violation of the Oregon Building Code.
The Supreme Court affirmed, but on a somewhat different basis. First, according to the Court, a construction defect claim concerns damage to property — and not mere economic losses — and thus is not barred by the economic loss doctrine. Second, the existence
Read Full Story...
Read the court decisionRead the full story...Reprinted courtesy of
Implied Warranties for Infrastructure in Florida Construction Defect Claims
December 30, 2013 —
CDJ STAFFThe homeowners in the Lakeview development built by Maronda Homes in Orange County, Florida started having water and drainage problems shortly after the homeowners association took control of the community. They fought their case all the way to the Florida Supreme Court, where the question was whether implied warranties of fitness covered the community’s infrastructure.
William Martin III, writing on the DestinLog, notes that previous Florida Supreme Court decisions went the other way. In a case involving a seawall, the court held that “unless the seawall was part of or in connection with the construction of a home or in support of a residence.” In the Lakeview case, they determined that the community’s infrastructure was just that: “essential to the habitability of the residence.” The court specifically included roads for ingress and egress, drainage systems to divert flooding, retention ponds to correct water flow damage, and underground pipes which are necessary for living accommodations.”
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Bill Preserves Insurance Coverage in Lava Zones
May 20, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Hawaii legislature passed a bill in its recently concluded session to protect homeowners and businesses affected by lava flows from losing coverage.
The Puna district on the Big Island was severely impacted by the Pu`u O`o lava flow as it crept closer to homes, businesses, schools and populated areas. Problems were created by the imposition of a moratorium on the sale of new policies in certain areas of the Puna district.
SB 589 grants relief to homeowners who have had continuous insurance in lava zone areas that are declared to be in a state of emergency. The bill (1) allows the homeowners to have their policies renewed, (2) permits continued coverage for homeowners who wish to sell their homes, (3) grants coverage for new buyers of an insured property, and (4) allows homeowners who have not previously had insurance to purchase coverage from the Hawaii Property Insurance Association.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Harsh New Time Limits on Construction Defect Claims
April 26, 2011 —
Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq.A recent Colorado Supreme Court decision, Smith v. Executive Custom Homes, Inc., 230 P.3d 1186 (Colo. 2010), considerably shortens the time limit for bringing many construction defect lawsuits. Homeowners and homeowner associations risk losing the right to seek reimbursement from builders, developers and other construction professionals unless they carefully and quickly act upon discovery of evidence of any potential construction defect.
The Statute of Limitations for Construction Defect Claims
Colorado’s construction defect statute of limitations limits the time for homeowners and homeowners associations to bring lawsuits for construction defects against “construction professionals,” including developers, general contractors, builders, engineers, architects, other design professionals, inspectors and subcontractors. The statute requires homeowners and associations to file suit within two years “after the claim for relief arises.” A claim for relief “arises” when a homeowner or association discovers or reasonably should have discovered the physical manifestation of a construction defect.
The two-year time limitation applies to each construction defect separately, and will begin to run upon the appearance of a “manifestation” of a construction defect (which may include, for example, a condition as simple as a roof leak or drywall cracks), even if the homeowner or association does not know the cause of the apparent problem.
The Smith Opinion and its Effect on the Statute of Limitations
In Smith v. Executive Custom Homes, Inc., the plaintiff homeowner, Mrs. Smith, slipped on ice that had accumulated on her sidewalk because of a leaking gutter and suffered injury. When she first noticed the leak, she reported it to her property manager, who reported it to the builder. The builder attempted to repair the gutter, unbeknownst to Mrs. Smith, and she did not notice further problems until approximately one year after she first observed the leak, when she fell and suffered serious injury. She sued the builder within two years of her injury, but nearly three years after she first learned of the leak.
The Colorado Supreme Court dismissed Mrs. Smith’s claims as untimely and held that under the construction defect statute of limitations, the two-year period for suing for injuries due to construction defects begins when the homeowner first observes the physical manifestation of the defect, even if the resulting injury has not yet occurred. The court acknowledged that this ruling could result in “unfair results,” especially if a serious and unforeseeable injury occurs more than two years after the first time the homeowner noticed the problem, and as a result the victim is unable to seek redress from those responsible for the defect.
Read the full story…
Reprinted courtesy of Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq. of Sullan2, Sandgrund, Smith & Perczak, P.C., and they can be contacted through their web site.
Read the court decisionRead the full story...Reprinted courtesy of