Florida's New Pre-Suit Notification Requirement: Retroactive or Prospective Application?
February 05, 2024 —
Holly A. Rice - Saxe Doernberger & Vita, P.C.Florida’s newly formed Sixth District Court of Appeal (“Sixth DCA”) recently certified conflict with Florida’s Fourth District Court of Appeal on the issue of retroactive application of the pre-suit notice requirement contained in Florida Statute §627.70152.1 Earlier this year, the Fourth District Court of Appeal (“Fourth DCA”) held that the pre-suit notice provision applies retroactively, meaning, it applies to all suits filed after July 1, 2021, regardless when the insurance policy was issued.2 The Sixth DCA, in
Hughes v. Universal Property & Casualty Insurance Company,3 directly rejected the Fourth DCA’s interpretation and instead found a retroactive application of the pre-suit notice to be unconstitutional under Florida law. Prior to the Fourth DCA’s ruling, most trial courts had found no retroactive application for the pre-suit notice provision.4
In August 2021, shortly after Florida Statutes Section 627.70152 went into effect on July 1, 2021, Rebecca Hughes (“Hughes”) sued Universal Property & Casualty Insurance Company (“Universal Property”) for breach of contract after Universal Property denied her insurance claim. Hughes did not file a pre-suit notice under Section 627.70152. Universal Property moved to dismiss based on Hughes’ failure to file the pre-suit notice, arguing that the pre-suit notice requirement applies to all lawsuits filed after July 1, 2021, even if the claimant’s insurance policy was issued before the statute’s effective date. The trial court agreed with Universal Property and dismissed the lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
Holly A. Rice, Saxe Doernberger & Vita, P.C.Ms. Rice may be contacted at
HRice@sdvlaw.com
No Coverage for Negligent Misrepresentation without Allegations of “Bodily Injury” or “Property Damage”
February 10, 2012 —
Tred R. Eyerly - Insurance Law HawaiiJeff City Industries was the general contractor for a sewer system improvement project in Branson, Missouri. Bituminous Cas. Corp. v. United HRB Gen. Contractors, Inc., 2011 U.S. Dist. LEXIS 145666 (W.D. Mo. Dec. 19, 2011). Branson sued Jeff City, alleging breach of the construction contract for the project. The claims included improperly bedded sewer piping, improper aligning portions of trenching for the sewer piping, improper service line connections to the sewer piping, etc.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Good News on Prices for Some Construction Materials
June 28, 2021 —
ABC - Construction ExecutiveThe elevated price of softwood lumber, a major talking point during much of the pandemic, appears to have peaked in early May at more than $1,700 per thousand board feet. As of June 23, the price has fallen below $900 per board feet, down about 49% in less than two months.
That’s still an unusually lofty price by historic standards—prices remain almost twice as high as in February 2020—but the trend is very much in the right direction. Builders that had been hoarding lumber have now begun to sell from their own inventory, other builders have delayed lumber purchases in anticipation of lower prices and sawmill operators have been adding shifts, as well as expanding capacity, all of which puts downward pressure on prices.
Reprinted courtesy of
ABC, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Is the Manhattan Bank of America Tower a Green Success or Failure?
April 15, 2014 —
Beverley BevenFlorez-CDJ STAFFConstruction Digital reported that the Bank of America tower in Manhattan, New York, “has been conversely hailed as both the greenest skyscraper in the world and an energy-guzzling toxic tower that exposes the charade of the LEED rating system.” It is the first skyscraper to ever achieve the highest LEED Platinum rating. However, a critic alleged that the eighty-year old Empire State Building “uses half the energy” of the new Bank of America tower.
The Bank of America tower, designed by architects Cook and Fox, was built with “local and recycled materials,” as well as “floor-to-floor insulated glazing” that maximizes “natural light and traps heat, and lights are automatically dimmed in daylight.” Rainwater is captured for reuse, and “waterless urinals save an estimated 8,000,000 US gallons of water per year.”
However, Construction Digital reported that Sam Roudman in New Republic Magazine “pointed out that buildings contribute more to global warming than any other sector of the economy, consuming more energy and producing more greenhouse gas emissions in America than every car, bus, jet, and train combined; and furthermore, than every factory combined.”
Joel Levy writing for Construction Digital declared, “We can call LEED a failed artifice and even suggest abandoning it as a pointless charade, but unless we want to live in caves and go back to using candles for light, we must accept the fact that the 155,000,000 people that make up America’s workforce power the country and indeed the world’s economy…need somewhere to work.”
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Temporarily Requires Employers to Provide Sick Leave While Awaiting COVID-19 Testing
April 06, 2020 —
Shawna Ruetz - The Grindstone Lewis Brisbois Labor & Employment BlogOn March 11, 2020, the Colorado Department of Labor and Employment (CDLE) issued emergency rules, referred to as Colorado Health Emergency Leave with Pay (Colorado HELP) Rules, requiring employers in certain industries to provide four days of paid sick leave to employees with flu-like symptoms while awaiting test results for COVID-19, or to anyone who is under instructions from a healthcare provider to quarantine or isolate due to a risk of having COVID-19. These rules take effect immediately for 30 days, or longer if the state of emergency declared by Colorado Governor Polis continues.
Which industries are covered by the Colorado HELP Rules?
- Leisure and hospitality;
- Food services;
- Child care;
- Education (including transportation, food service, and related work at educational establishments);
- Home health (if working with elderly, disabled, ill, or otherwise high-risk individuals)
- Nursing homes; and
- Community living facilities; and
- Retail establishments that sell groceries (added March 26).
How much paid sick leave must be provided?
Employers are required to provide up to four days of paid sick leave to employees with flu-like symptoms who are being tested for COVID-19. If the employee tests negative, the leave ends.
Read the court decisionRead the full story...Reprinted courtesy of
Shawna Ruetz, Lewis BrisboisMs. Ruetz may be contacted at
Shawna.Ruetz@lewisbrisbois.com
Georgia Supreme Court Limits Damages Under Georgia Computer Systems Protection Act
March 01, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPOn January 27, 2017, the Supreme Court of Georgia issued a decision determining whether the Georgia Computer Systems Protection Act (“GCSPA”) provides for punitive damages. While not directly related to construction, the GCSPA can be a potential mechanism for asserting claims against former employees that use company information stored in computers.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
Why Is It So Hard to Kill This Freeway?
April 18, 2023 —
Benjamin Schneider - BloombergKeith Pete remembers what Claiborne Avenue was like before the interstate.
As a child in the early 1960s, the native New Orleanian would come to Claiborne Avenue with his dad to buy chickens from the local grocers. Sometimes, as a treat, father and son would get hamburgers on French rolls and pineapple juice and picnic on the neutral ground — the avenue’s wide, grassy median, which was thick with live oak trees and azaleas.
“People used to sit and enjoy the weather,” Pete, 68, recalls. “There was beautiful grass all the way down. It was gorgeous.”
At the time, Claiborne Avenue coursed through the heart of New Orleans’ Tremé neighborhood and a major center of Black commerce and culture. “It was safe; it was thriving,” Pete said. “It was mostly wiped out.”
In 1966, workers began removing the avenue’s oaks and driving the pilings that would transform 18 blocks of the tree-lined boulevard into a viaduct carrying Interstate 10. While plans for a Robert Moses-designed waterfront freeway through the French Quarter were halted in 1969 after intense resistance from historic preservationists, the state- and city-backed Claiborne Expressway proceeded. The elevated highway and its tangle of off-ramps destroyed some 500 homes and 326 Black-owned businesses. The once-thriving corridor became a dark, noisy netherworld, unsafe for pedestrians and unhealthy for anyone who breathes.
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin Schneider, Bloomberg
Contractual Waiver of Consequential Damages
January 02, 2019 —
David Adelstein - Florida Construction Legal UpdatesContractual waivers of consequential damages are important, whether they are mutual or one-sided. I believe in specificity in that the types of consequential damages that are waived should be detailed in the waiver of consequential damages provision. Standard form construction agreements provide a good template of the types of consequential damages that the parties are agreeing to waive.
But, what if there is no specificity in the waiver of consequential damages provision? What if the provision just states that the parties mutually agree to waive consequential damages or that one party waives consequential-type damages against the other party? Let me tell you what would happen. The plaintiff will argue that the damages it seeks are general damages and are NOT waived by the waiver of consequential damages provision. The defendant, on the other hand, will argue that the damages are consequential in nature and, therefore, contractually waived. FOR THIS REASON, PARTIES NEED TO APPRECIATE WHAT DAMAGES ARE BEING WAIVED OR LIMITED, AND POTENTIALLY THOSE DAMAGES NOT BEING WAIVED OR LIMITED, WHEN AGREEING TO A WAIVER OF CONSEQUENTIAL DAMAGES PROVISION!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at