Not so Fast! How Does Revoking Acceleration of a Note Impact the Statute of Limitations?
July 30, 2018 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogIntroduction
Lenders routinely accelerate notes after a default occurs, calling the entire loan due immediately. Less regularly, a lender may change its mind and unilaterally revoke the acceleration. Rarely, however, does a lender fail to foreclose on its real property collateral before the statute of limitations expires. In Andra R. Miller Designs, LLC v. U.S. Bank, N.A., 244 Ariz. 265, 418 P.3d 1038 (Ct. App. 2018), a unique set of facts involving these issues led the Arizona Court of Appeals to hold that proper revocation of acceleration resets the statute of limitations.
The Facts
In Miller, a lender made a $1,940,000 loan evidenced by a promissory note and secured by a deed of trust against a home in Paradise Valley, Arizona. The borrower defaulted in September 2008. The default prompted the lender to notice a default, accelerate the note, and initiate a trustee’s sale of the home in 2009. After the lender accelerated the note, the six year statute of limitations began to run. See A.R.S. § 12-548(A)(1) and A.R.S. § 33-816. Pretty standard facts so far, right? Don’t worry, it gets a bit more convoluted.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
The Expansion of Potential Liability of Construction Managers and Consultants
November 18, 2019 —
Scott D. Cessar - Construction ExecutiveOver the last decade or so, there has been far more judicial willingness to adopt legal theories that result in an increased risk of exposure to construction managers and consultants working on construction projects. This has resulted in a greater likelihood of lawsuits being filed that name construction managers and consultants as defendants and a greater likelihood of those lawsuits surviving efforts to have the lawsuits dismissed prior to trial. The consequence of more claims has led to increased costs for legal expenses, settlements and uncompensated personnel time devoted to the defense of the claims.
This expansion of potential liability may be broken into two sets:
- claims for pure economic loss not arising from property damage or personal injury by parties not in a contractual relationship with a construction manager or consultant; and
- claims for property damage or personal injury by a party not in a contractual relationship with a construction manager or consultant.
The first set concerns claims by a contractor against a construction manager or consultant that its breach of duties owed to the owner on a project and/or its provision of incomplete or inaccurate information on a project, which it knew, or should have reasonably anticipated, would be relied on by the contractor, resulted in damages to the contractor.
Reprinted courtesy of
Scott D. Cessar, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Cessar may be contacted at
scessar@eckertseamans.com
Las Vegas Team Obtains Complete Dismissal of a Traumatic Brain Injury Claim
June 21, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to Partner,
Jeffrey W. Saab and Associate,
Shanna B. Carter on their successful Motion to Dismiss!
This personal injury claim arose from an incident whereby Plaintiff allegedly tripped and fell in front of the client’s business and sustained a traumatic brain injury. Initially, a default was entered against the client, and BWB&O was retained to unwind the same, and then defend against the claim. However, during the initial investigation, Shanna uncovered a defect in the service of the Complaint which invalidated not only the default, but more importantly service of the Complaint itself. Working as a team, Shanna performed the research and writing, and Jeff argued the Motion to Dismiss which was granted dispensing of the entire claim.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
The One New Year’s Resolution You’ll Want to Keep if You’re Involved in Public Works Projects
January 07, 2015 —
Garret Murai- California Construction Law BlogNew Year’s resolutions are hard to keep.
In fact, studies (which I have a sneaking suspicion may have been paid for by the tobacco, donut and vacation timeshare lobbies) have found that only 8% of New Year’s resolutions are kept.
But, here’s one you’ll want to make sure you keep.
Mandatory Registration and Notice Requirements
If you’re a public works contractor or subcontractor you only have until March 1, 2015 to register through the California Department of Industrial Relations (“DIR”) to bid and enter into public works contracts on state and local public works projects.
And if you’re a state or local public agency you must provide notice of the DIR’s new registration requirements in all call for bids and contract documents beginning January 1, 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Entire Fairness or Business Judgment? It’s Anyone’s Guess
January 09, 2015 —
Maurice Pesso, Greg M. Steinberg and Christopher J. Orrico – White and Williams LLPIn lawsuits challenging the validity of business transactions and combinations, the most significant issue is often which standard of review the court applies: the defense-friendly “Business Judgment Rule” or the more stringent “Entire Fairness Standard.” The standard utilized by the court – or more often times the standard which the parties think the court will apply – can drive decisions on motion practice, settlement discussions, and resolution strategy. Under the Business Judgment Rule, directors are presumed to have acted in good faith and their decisions will only be questioned when they are shown to have engaged in self-dealing or fraud. However, if a “Controlling Shareholder” stands on both sides of the transaction, the court will often scrutinize the transaction under the more plaintiff-friendly “Entire Fairness Standard.”
So, what constitutes a “Controlling Shareholder?” If the party in question owns more than 50% of a company’s equity, the answer is clear-cut. However, for cases involving stockholders who own less than 50% of a company’s equity and stand on both sides of the disputed transaction, the answer is not so simple. This uncertainty was highlighted in back-to-back decisions by the Delaware Chancery Court in November 2014. On November 25, 2014, the court granted the defendants’ motion to dismiss a derivative lawsuit alleging breach of fiduciary duty in In Re Sanchez Energy Derivative Litigation (“Sanchez”). Vice Chancellor Glasscock held that the complaint failed to plead facts sufficient to raise an inference that two directors with a collective 21.5% equity interest in the company were Controlling Shareholders. The very next day, in In Re Zhongpin Inc. Stockholders Litigation (“Zhongpin”), the Delaware Chancery Court denied the defendants’ motion to dismiss breach of fiduciary duty claims against an alleged “Controlling Shareholder” and members of the company’s board. In Zhongpin, Vice Chancellor Noble held that sufficient facts were plead to raise an inference that a CEO with a 17.5% equity was a “Controlling Shareholder.”
Reprinted courtesy of White and Williams LLP attorneys
Maurice Pesso,
Greg M. Steinberg and
Christopher J. Orrico
Mr. Pesso may be contacted at pessom@whiteandwilliams.com
Mr. Steinberg may be contacted at steinbergg@whiteandwilliams.com
Mr. Orrico may be contacted at orricoc@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Could Impact Contractor Performance Bonds
March 30, 2020 —
Ben Williams & MG Surety - Construction ExecutiveAs COVID-19 continues to expand around the United States and the world, it may only be a matter of time before U.S. construction projects are affected by the virus. Performance bonds guarantee that a project will be completed by a contractor according to the contract. However, what if a contractor cannot complete a project on time due to widespread disease? What, if any, impact could the virus have on a contractor’s surety bond program?
Risk Factors
Several risks associated with the virus could trigger a performance bond claim.
1. Materials. The Chinese account for a large supply of construction materials, including steel, copper, cabinetry, etc. An inability to obtain these materials could significantly delay or stop a project all together. Even if a contractor is able to obtain them from other sources, it may be at a significantly higher cost than they put into the bid.
2. Labor. There is already a shortage of qualified labor in the construction industry. Additionally, construction already lends itself to the spreading of viruses; workers are often in close proximity, handling common materials, and they may not have an easily accessible place to wash their hands. Furthermore, even though many now have paid sick leave, there is often pressure not to use it. These things could magnify the labor shortage and make it difficult to complete projects on time.
3. Safety. Finally, the world is having a serious shortage of respirators. Because of widespread panic, many people have been purchasing N95 respirators—so much that the Surgeon General has asked people to stop buying them. It has created a shortage for people who really need them, like contractors. If contractors can’t get these safety masks, certain trades will either be unable to work, or risk continuing the project without masks, which would endanger workers and open them up to OSHA penalties.
Reprinted courtesy of
Ben Williams and MG Surety, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Williams may be contacted at
benw@mgsuretybonds.com
Legislative Update – The CSLB’s Study Under SB465
March 22, 2018 —
John Castro - Construction Law BlogFollowing the tragic Berkeley balcony collapse in 2015, the Legislature enacted California Senate Bill 465 which commissioned the Contractors State License Board (“CSLB” or “Board”) to perform a study regarding the efficacy of having contractors report settlements to the Board. In December 2017 the CSLB released their findings in a report. The ultimate conclusion of the report is to recommend to the Legislature that the ability of the CSLB to protect the public “would be enhanced by regulations requiring licensees to report judgments, arbitration awards, or settlement payments of construction defect claims for rental residential units.” Senator Jerry Hill authored SB465, and his office is presently now drafting legislation on settlement reporting based in part on this study.
The most troubling concern about the study is transparency. The report references nine exhibits, all of which have been withheld from publication under purposes of confidentiality. Therefore, much of the CSLB’s study must be taken at face value because much of the data they rely on to formulate their conclusions cannot be independently verified.
One of the factors that the CSLB undertook in its study was to determine criteria for when a settlement was “nuisance value,” and therefore less important for reporting purposes. The CSLB acknowledged there was no industry-wide definition for “nuisance value,” whether it be in the insurance industry, construction industry, or otherwise. Insurer survey respondents reached a general consensus on
aspects of what can constitute a “nuisance value” settlement, including the amount of the settlement and the size of the case. However, the response rate to the insurer survey was only 3.3 percent. In general, the concern with using settlement amount and size of the case as indicative factors is the fact that a large settlement size, for instance, may still constitute a “nuisance value” settlement. One example would be a large settlement figure in a case involving hundreds of homes in multiple subdivisions.
Read the court decisionRead the full story...Reprinted courtesy of
John Castro, Gordon Rees Scully Mansukhani LLPMr. Castro may be contacted at
jcastro@grsm.com
Certifying Claim Under Contract Disputes Act
June 08, 2020 —
David Adelstein - Florida Construction Legal UpdatesUnder the Contract Disputes Act (41 USC 7101 en seq.), when a contractor submits a claim to the government in excess of $100,000, the claim MUST contain a certification of good faith, as follows:
For claims of more than $100,000 made by a contractor, the contractor shall certify that–
(A) the claim is made in good faith;
(B) the supporting data are accurate and complete to the best of the contractor’s knowledge and belief;
(C) the amount requested accurately reflects the contract adjustment for which the contractor believes the Federal Government is liable; and
(D) the certifier is authorized to certify the claim on behalf of the contractor.
41 U.S.C. 7103(b)(1). See also 48 C.F.R. s. 33.207(c) as to the wording of the certification.
The contracting officer is not required to render a final decision on the claim within 60 days if, during this time period, he/she notifies the contractor of the reasons why the certification is defective. 41 U.S.C. 7103(b)(3). Importantly, the contracting officer’s failure to render a decision within 60 days is deemed an appealable denial.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com