Brooklyn Atlantic Yards Yields Dueling Suits on Tower
September 03, 2014 —
Erik Larson – BloombergForest City Ratner Cos., the initial developer of Brooklyn’s $4.9 billion Atlantic Yards project surrounding Barclays Center arena, exchanged lawsuits with the Swedish construction firm Skanska AB (SKAB) over claims of design flaws and delays in building a stalled residential tower.
The lawsuits, filed today in Manhattan state court, focus on a contract for the 34-floor “modular” residential high-rise building under construction next to the arena for the National Basketball Association’s Brooklyn Nets that opened in 2012 as the centerpiece of the former rail yard and a symbol of the New York borough’s resurgence.
Skanska, a Stockholm-based firm that has grown to become New York’s second-largest building contractor, seeks at least $50 million in damages for changes to the building that were made without consultation, according to its complaint. Brooklyn-based Forest City Ratner blames Skanska for the project’s problems, citing “tens of millions of dollars” in cost overruns caused by a lack of skill and a failure to adhere to terms of the 2012 contract.
Read the court decisionRead the full story...Reprinted courtesy of
Erik Larson, BloombergMr. Larson may be contacted at
elarson4@bloomberg.net
Improper Classification Under Davis Bacon Can Be Costly
April 01, 2015 —
Craig Martin – Construction Contractor AdvisorThe Department of Labor announced late last year that it had recovered nearly $2 million in back wages and fringe benefits from a subcontractor that provided constructions services at the federally funded Crescent Dunes Solar Energy Project in the Nevada desert. This was not a failure to pay Davis Bacon wages, but a failure to properly classify laborers on the project. The DOL determined that the laborers should have been paid as skilled trade steelworkers, not general laborers. As the subcontractor found out, this proved very costly.
The subcontractor submitted its bid, classifying its laborers as general laborers and designating their wage at $30.00. The laborers were to assemble billboard sized mirrors on the project. There is some indication that the Department of Energy agreed with the classification, even though the Department of Labor has the final say on classifications. The Department of Labor’s investigation revealed that the laborers routinely performed duties in skilled trades, such as ironworking, electrical work, painting or bridge crane operation. Based on these activities, the Department of Labor concluded that the laborers should have been paid $60.00 per hour plus fringe benefits.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Unlicensed Contractors Caught in a Sting Operation
March 19, 2015 —
Beverley BevenFlorez-CDJ STAFFSeven suspects were cited for contracting without a license after being caught by the Contractors State License Board (CSLB), reported CBS local news, and eighty-five people may face criminal charges. The undercover sting operations occurred over a two day period in Rancho Mirage, California. A hearing is scheduled for June 3rd at Riverside County Superior Court.
CSLB Registrar Cindi A. Christenson told CBS, “Several of the suspects we targeted turned out to be repeat offenders and individuals with a criminal history and drug violations. If you knew their backgrounds, you'd never allow them near your home or family."
Read the court decisionRead the full story...Reprinted courtesy of
The Murky Waters Between "Good Faith" and "Bad Faith"
September 30, 2019 —
Theresa A. Guertin - Saxe Doernberger & VitaIn honor of Shark Week, that annual television-event where we eagerly flip on the Discovery Channel to get our fix of these magnificent (and terrifying!) creatures, I was inspired to write about the “predatory” practices we’ve encountered recently in our construction insurance practice. The more sophisticated the business and risk management department is, the more likely they have a sophisticated insurer writing their coverage. Although peaceful coexistence is possible, that doesn’t mean that insurers won’t use every advantage available to them – compared to even large corporate insureds, insurance companies are the apex predators of the insurance industry.
In order to safeguard policyholders’ interests, most states have developed a body of law (some statutory, some based on judicial decisions) requiring insurers to act in good faith when dealing with their insureds. This is typically embodied as a requirement that the insurer act “fairly and reasonably” in processing, investigating, and handling claims. If the insurer does not meet this standard, insureds may be entitled to damages above and beyond that which they could otherwise recover for breach of contract.
Proving that an insurer acted in “bad faith,” however, can be like swimming against the riptide. Most states hold that bad faith requires more than just a difference of opinion between insured and insurer over the available coverage – the policyholder must show that the insurer acted “wantonly” or “maliciously,” or, in less stringent jurisdictions, that the insurer was “unreasonable.”
Read the court decisionRead the full story...Reprinted courtesy of
Theresa A. Guertin, Saxe Doernberger & VitaMs. Guertin may be contacted at
tag@sdvlaw.com
Insurer’s Duty to Indemnify Not Ripe Until Underlying Lawsuit Against Insured Resolved
February 03, 2020 —
David Adelstein - Florida Construction Legal UpdatesA liability insurer has two duties: 1) the duty to defend its insured; and 2) the duty to indemnify its insured.
With respect to the second duty – the duty to indemnify – this duty is typically “not ripe for adjudication unless and until the insured or putative insured has been held liable in the underlying action.” Hartford Fire Ins Co. v. Beazer Homes, LLC, 2019 WL 5596237, *2 (M.D.Fla. 2019) (internal quotation omitted).
For instance, Beazer Homes involved an insurance coverage dispute stemming from construction defects. An owner sued its general contractor for construction defects relating to stucco problems. The general contractor paid for the repairs. The general contractor then sued its stucco subcontractor to recover the costs it incurred. The subcontractor tendered the defense of the lawsuit to its commercial general liability insurer which is defending its insured-subcontractor under the commonly issued reservation of rights.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Seattle Expands Bridge Bioswale Projects
May 11, 2020 —
Jim Parsons - Engineering News-RecordThe success of engineered systems to capture stormwater runoff from Seattle’s Aurora Avenue Bridge has spurred construction of additional measures that proponents say will increase total filtering capacity by another two million gallons per year.
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Signs of a Slowdown in Luxury Condos
January 28, 2015 —
Prashant Gopal, Oshrat Carmiel and John Gittelsohn – BloombergManhattan real estate agent Lisa Gustin listed a four-bedroom Tribeca loft for $7.45 million in October, expecting a quick sale. Instead, she cut the price by $550,000 in January. “I thought for sure a foreign buyer would come in,” says Gustin, a broker at Brown Harris Stevens who is still marketing the 3,800-square-foot apartment. “So many new condos are coming up right now. They’ve been building them for the past few years, and now they’re really hurting the resales.”
New high-priced condominiums and mansions are hitting the market in New York, Miami, and Los Angeles just as international buyers, who helped fuel luxury demand in the three cities, are seeing their purchasing power wane with the strengthening dollar. Signs of a pullback may already be showing in Manhattan, where luxury-home sales have slowed amid a boom in the construction of towers aimed at U.S. millionaires and foreign investors. Sales of homes costing more than $2 million in the New York area rose 10 percent last year, compared with a 27 percent jump in 2013, according to CoreLogic DataQuick.
Reprinted courtesy of Bloomberg reporters
Prashant Gopal,
Oshrat Carmiel and
John Gittelsohn
Mr. Gittlesohn may be contacted at johngitt@bloomberg.net; Ms. Carmiel may be contacted at ocarmiel1@bloomberg.net; Mr. Gopal may be contacted at pgopal2@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Butterflies, Salt Marshes and Methane All Around
November 16, 2020 —
Anthony B. Cavender - Gravel2GavelOur latest summary of some recent developments in the courts and the federal agencies includes a unique case involving salt marshes adjacent to San Francisco Bay.
THE FEDERAL COURTS
A Wolf Among the Butterflies
On October 13, 2020, the U.S. Court of Appeals for the District of Columbia Circuit decided the case of North American Butterfly Association v. Chad Wolf, Acting Secretary of the Department of Homeland Security. The National Butterfly Center is a 100-acre wildlife sanctuary located in Texas along the border between the United States and Mexico, and in 2017, the DHS exerted control over a segment of the sanctuary to construct facilities to impede unauthorized entry into the United States. It was alleged that the government failed to provide advance notice to the sanctuary before it entered the sanctuary to build its facilities. The Association filed a lawsuit to halt these actions for several reasons, including constitutional claims and two federal environmental laws (NEPA and the Endangered Species Act), but the lower court dismissed the lawsuit because of the provisions of the Illegal Immigration Reform and Immigrant Responsibility Act of 1996 (IIRIRA). That law forecloses the applicability of these laws if the Secretary of DHS issues appropriate declaration. On appeal, the DC Circuit held, in a 2 to 1 decision, that the lawsuit should not have been dismissed. The plaintiffs had standing to file this lawsuit, but the jurisdiction stripping provisions of the IIRIRA, when invoked, required that the statutory claims be dismissed as well as a constitutional Fourth Amendment search and seizure claim. However, the plaintiff’s Fifth Amendment claim that the government’s actions violated their right to procedural due process must be reviewed. The Center was given no notice of the government’s claims and no opportunity to be heard before these actions were taken. The dissenting judge argued that the court was being asked to review a non-final decision, which it should not do.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at