Hard to Believe It, Construction Law Musings is 16
January 07, 2025 —
Christopher G. Hill - Construction Law MusingsOn this date back in 2008 (wow, that seems so long ago), I began Construction Law Musings on the Blogger platform with a brief announcement. Little did I know that this corner of the internet (or is it Blawgosphere?) would still be around in 2024!
In the time since I made that short entry 16 years ago (I know, I can’t believe it either), I’ve met several construction lawyers here in Virginia who refer to me as the “blog guy.” To be recognized for the work I do here at Construction Law Musings, something that benefits me (and I hope the readers), and which I do for the fun of it, is an honor.
The blog has since taken on a life of its own in many respects, allowing me to meet some of the great construction pros who have provided a guest post or two for Musings and added their different perspectives. Musings also kept me up on at least most of the trends in Virginia construction law by making me post consistently (though sometimes less consistently than others). Now, around 975 posts and 16 years later, I find it hard to believe that so much time has passed and effort has been put into what started on a whim and the plan that I’d post thoughts on the legal landscape and construction from the perspective of a Virginia construction lawyer.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
How to Remove a Mechanics Lien from Your Property
March 21, 2022 —
Hannah Kreuser - Porter Law GroupIt sometimes happens that a contractor or material supplier records a mechanics lien on your property that becomes expired. Other times, the mechanics lien may be wrong, invalid and unenforceable for some reason, serving no legitimate purpose. The contractor or material supplier may be reasonable and release the mechanics lien once these issues are brought to its attention, but the contractor or material supplier may very well refuse to release the mechanics lien when requested. When this happens, what are your options?
In California, there are various ways to bring this type of mechanics lien to a court’s attention in the hopes that the court will cause it to be released. Three of the more common methods are: (1) a petition under California Civil Code (“CCC”) § 8480; (2) a petition under California Code of Civil Procedure (“CCP”) § 765.010; or (3) a Lambert motion. This article will briefly discuss each of these methods.
Read the court decisionRead the full story...Reprinted courtesy of
Hannah Kreuser, Porter Law GroupMs. Kreuser may be contacted at
hkreuser@porterlaw.com
Thirteen Payne & Fears Attorneys Honored by Best Lawyers
August 19, 2024 —
Payne & Fears LLPCongratulations to the 13 Payne & Fears attorneys included in the 2025 Edition of “Lawyer of the Year,” The Best Lawyers In America®, and Best Lawyers: Ones to Watch®. Attorneys have been recognized in the following practice areas:
2025 Edition “Lawyer of the Year”
Orange County
Benjamin A. Nix
Daniel F. Fears
- Litigation – Labor and Employment
Read the court decisionRead the full story...Reprinted courtesy of
Payne & Fears LLP
New Case Alert: Oregon Supreme Court Prohibits Insurer’s Attempt to Relitigate Insured’s Liability
November 17, 2016 —
Austin D. Moody – Saxe Doernberger & Vita, P.C. BlogIn a big win for policyholders, the Oregon Supreme Court recently ruled that that insurance companies are not allowed to relitigate the nature of damages awarded against their insureds during an underlying trial.
In a coverage dispute stemming from a contractor’s faulty work on a condominium development, the insurer argued that at least a portion of the damages awarded represented the cost of repairing the contractor’s own work product. Coverage for such damages would be explicitly excluded by the policy. However, the Oregon Supreme Court found that the jury had been instructed that it could not award damages for the contractor’s own faulty workmanship. The court declined to give the insurer a chance to attempt to reclassify the nature of these damages.
Read the court decisionRead the full story...Reprinted courtesy of
Austin D. Moody, Saxe Doernberger & Vita, P.C.Mr. Moody may be contacted at
adm@sdvlaw.com
Revisiting the CMO; Are We Overusing the Mediation Privilege?
November 19, 2021 —
Michael T. Kennedy Jr. - BERDING|WEILOne of the most common features in construction defect cases is the Case Management Order (“CMO”) or Pre-Trial Order (“PTO”) to govern pre-trial and mediation procedures. CMOs and PTOs arose in the days when the HOA would sue the developer, the developer would cross-complaint against the subcontractors, and each defendant and cross-defendant might have 2 or 3 insurance carriers defending, each of whom may retain their own panel counsel. In a large case there may have been 20 parties and 30 defense attorneys. In order to avoid the cost and chaos of all of those parties propounding their own discovery, and in order to prepare these cases for mediation well before trial and the associated costs, it became standard practice in California to include provisions in the CMO to stay all discovery until just before trial.
Plaintiff would provide a Defect List or Statement of Claims and the parties experts would meet and exchange information as part of the mediation process. All of the information exchanged would be subject to mediation privileges and inadmissible at trial. The benefit of this practice was that the parties (and carriers) would avoid the cost of formal discovery and allow the experts to discuss compromised scopes of repair to help settle the case while being able to take a more aggressive position at trial. The disadvantages are that each party uses its privileged initial expert reports to stake out negotiating positions more extreme than what they would put on at trial, with each side losing credibility with the other in assessing the value of the case, and for those cases that did not settle, the parties would be faced with having to do all of the depositions and discovery in the last 60 days, or delaying trial, or both.
Over the last 10 or 15 years with the advent of wrap-up insurance policies, these cases now usually involve 2 sides instead of 20; only the HOA and the developer remain in the case. However, old habits die hard, and the standard CMO/PTO hasn’t evolved with other aspects of these cases. The practice of staying all discovery and exchanging information only under mediation privileges remains, and as a result insurance carriers don’t receive the admissible evidence that they need to determine coverage and evaluate the real settlement value of the case until just before trial. On the plaintiff’s side, if most of the experts’ work is done under the guise of mediation privilege, those costs may not be recoverable. Outside the context of mediation, costs incurred in investigation of the defects and preparation of a scope and cost of repair are recoverable.
This reflexive claim of mediation privilege over all information exchanged during the case has outlived its usefulness. The CMO can and should remain to regulate formal discovery and to help the parties prepare for mediation, but regulated discovery should be opened early in the case. In California, the SB800 process already provides for the exchange of admissible information during the prelitigation right to repair process. Continuing that exchange during the early litigation allows the parties to continue to prepare for mediation, but waiving privileges had advantages for both sides.
A senior claims manager once commented that Plaintiff’s mediation-protected Statement of Claims “might as well be a stack of blank paper” for all of its usefulness to the carrier in assessing the value of the case. If the Plaintiff and it expects are free to inflate their claims early in the case without having to worry about every supporting those claims in front of a jury, they have little or no credibility. And if those claims are inflated or not “real,” not only can the carrier not properly assess the verdict range and settlement value of the case, but it may also be hampered in making a coverage determination. Simply put, if the exchange of real information through formal discovery is put off until just before trial, the defense cannot be ready to settle until then. Worse, the cost of defense goes through the roof in the last 60 days before trial as the lawyers’ scramble to take all of the depositions and to all of the other work that had been stayed for the previous year or two.
The Plaintiff is faced with the same question of credibility of defense experts where they are free to take a “low ball” negotiating position without having to support that position through cross-examination in front of the jury. Just as the carrier behind the defense attorney needs the Plaintiff’s “real” evidence to assess the claim, so does the HIOA Board of Directors behind the Plaintiff’s counsel. Additionally, in California as in most states, the cost of experts’ preparation for mediation may not be recoverable as costs or damages, but investigation of the defects and preparation of the scope and cost of repair is recoverable.
The biggest challenge is resolving construction defect claims for both sides is how to resolve these cases quickly while keeping costs under control. Practices that worked 20 years ago are no longer applicable with changes in insurance, and in light of some of the bad habits that arise when all of the information exchanged was confidential.
The CMO/PTO process can still be useful to regulate the discovery and mediation schedule given the volume of documents and other information to be exchanged but exchanging “real” information in a form that may come into evidence at trial should foster earlier resolution, resulting in cost savings for the parties. The CMO can provide for the parties to respond to controlled discovery, and the exchange of expert reports and potentially depositions can and should be done earlier in the case, well before the eve of trial. The parties can then assess the true value of each case and prepare for more substantive mediation without waiting until they are on the figurative courthouse steps.
Construction defect cases have a pattern, and it is tempting for busy lawyers to just put each case through the same algorithms that they have used for years. However, these cases have evolved and those of us handling these cases need to reevaluate our approach to these cases. Taking aggressive negotiating positions that no longer have any credibility with the other side has become counterproductive, and the exchange of real evidence earlier in the case would better serve our clients and carriers.
BERDING|WEIL is the largest and most experienced construction defect and common interest development law firm in California. For more information, please visit https://www.berding-weil.com
Read the court decisionRead the full story...Reprinted courtesy of
Michael T. Kennedy Jr., BERDING|WEILMr. Kennedy may be contacted at
mkennedy@berdingweil.com
Insured's Claim for Replacement Cost Denied
December 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Illinois Appellate Court affirmed the trial court's ruling that the insured was only entitled to the actual cost value of his loss, not the replacement cost. Lytle v. Country Mutual Ins. Co., 2015 Ill. App. LEXIS 756 (Sept. 30, 2015).
The insured's home was built around 1903. On June 21, 2011, the insured discovered damage to his home because of a severe storm. He made a claim with his insurer, Country Mutual.
The policy contained a depreciation holdback provision. The provision said the insurer would not pay more than the actual cash value until the actual repair or replacement was complete. If the insured elected to accept actual cash value, he would have one year from the date of the loss to repair or replace the damaged property and request the difference between the actual cash value and the replacement cost.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Before Collapse, Communications Failed to Save Bridge Project
December 30, 2019 —
Scott Judy - Engineering News-RecordThe National Transportation Safety Board’s Oct. 8 release of documents related to its FIU bridge collapse investigation raises questions but provides no definitive conclusions about why the partially built structure suddenly crashed to the ground on March 15, 2018, killing six. The last official word on the cause of the fatal collapse will have to await the agency’s final report, scheduled to be released on Oct. 22.
Scott Judy, Engineering News-Record
Mr. Judy may be contacted at judys@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Dust Infiltration Due to Construction Defect Excluded from Policy
September 09, 2011 —
CDJ STAFFA summary judgment was affirmed in the case of Brown v. Farmers Group, by the California Court of Appeals. The Browns bought a new home in Oakley, California. At the time, they signed disclosure statement “acknowledging that the area around their home experienced gusty winds and would be in development for years to come, which might result in dust and airborne mold.”
The Browns found an unusual amount of dust in their home, which became worse when they ran their heating and air conditioning system. Shelia Brown was later diagnosed with chronic valley fever, which was attributed to airborne mold. The Browns contacted Farmers which investigated the house. Although the adjustor from Farmers said the Browns would be covered, Farmers denied the claim.
After the Browns moved out of the house, an inspector found that the HVAC line in the attic was disconnected, sending dust into the home. The Browns brought action against Mid-Century Insurance, which managed the policy, and Farmers. The identified the HVAC defect, window problems, and valley fever as causes, suing for breach of contact, breach of implied covenant of good faith and fair dealing, and the intentional infliction of emotional distress.
The court rejected all these claims. The policy with Farmers excluded losses due to defective construction. This ruled out the faulty HVAC system and any problems there might have been from the windows. The policy also specifically excluded losses from contamination, fungi, pathogens, and noxious substances. The court further found that the adjustor’s opinion was irrelevant to the question of what the policy actually covered. Finally, the court found no evidence of intentional infliction of emotional stress.
On review, the appeals court upheld the trial court’s conclusions and affirmed the summary judgment.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of