Inverse Condemnation and Roadwork
October 09, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPThe following case, issued yesterday by the Georgia Supreme Court, addresses the accrual of the statute of limitations on a claim of inverse condemnation based on nuisance.
Wise Bus. Forms, Inc. v. Forsyth Cnty., S22G0874, 2023 WL 6065278 (Ga. Sept. 19, 2023)
We granted certiorari in this case to clarify the standards for determining when a claim for inverse condemnation by permanent nuisance accrues for purposes of applying the four-year statute of limitation set forth in OCGA § 9-3-30 (a).
[. . .]
Permanent nuisance cases vary in relation to when the alleged harm to a plaintiff’s property caused by the nuisance becomes “observable” to the plaintiff. Forrister, 289 Ga. at 333 (2), 711 S.E.2d 641. In some cases, the harm to the plaintiff’s property is immediately observable “upon the creation of the nuisance.” Id. For example, where a landowner or governmental agency “erects a harmful structure such as a bridge or conducts a harmful activity such as opening a sewer that pollutes a stream,” and it is immediately obvious that the structure or activity interferes with the plaintiff’s interests, the plaintiff must file “one cause of action for the recovery of past and future damages caused by [the] permanent nuisance” within four years of the date the structure is completed or the harmful activity is commenced. Id. at 333-336 (2) and (3), 711 S.E.2d 641 (citing Restatement (Second) of Torts §§ 899 and 930). Phrased another way, where the “construction and continuance” of the permanent nuisance at issue is “necessarily an injury, the damage is original, and may be at once fully compensated. In such cases[,] the statute of limitations begins to run upon the construction of the nuisance.” City Council of Augusta v. Lombard, 101 Ga. 724, 727, 28 S.E. 994 (1897).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Issues of Fact Prevent Insurer's Summary Judgment Motion in Collapse Case
January 17, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's effort to dismiss the insured's collapse case by motion for summary judgment failed. Bitters v. Nationwide Gen. Ins. Co., 2021 U.S. Dist. LEXIS 228523 (E.D. Pa. Nov. 30, 2021).
The insured alleged that there was a "sudden and accidental direct physical loss" to his home caused by collapse due to hidden insect damage to the foundation. The insured came home to find the floor of a bedroom dropped down to the cement slab below. He filed a claim with Nationwide, but coverage was denied. Suit was filed and Nationwide moved for summary judgment.
The policy provided coverage for a sudden and accidental collapse caused by hidden insect damage. A building or part of a building was not considered in the state of collapse if it was standing, even if it was in danger of falling low or caving in.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Limits Indemnification Obligations of Design Professionals
August 24, 2017 —
William L. Doerler - White and Williams LLPThe California legislature recently enacted legislation – SB 496 – limiting a design professional’s indemnification obligations in private contracts related to design services. The term “design professional” refers to licensed architects, landscape architects and professional land surveyors, and registered professional engineers. As revised, Cal. Civ. Code § 2782.8 states that, for all contracts entered into on or after January 1, 2018 for design professional services, all provisions that purport to have the design professional indemnify the indemnitee for claims against the indemnitee – or require the design professional to provide a defense to the indemnitee – are unenforceable except to the extent that the claims against the indemnitee arise out of, or relate to, the negligence, recklessness or willful misconduct of the design professional. In addition, as revised, § 2782.8 limits a design professional’s liability for the cost of defense to the design professional’s percentage of fault.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Third Circuit Affirms Use of Eminent Domain by Natural Gas Pipeline
November 28, 2018 —
Anthony B. Cavender - Gravel2GavelOn October 30, the U.S. Court of Appeals for the Third Circuit decided the case of Transcontinental Gas Pipe Line Co., LLC v. Permanent Easements for 2.14 Acres, et al. , affirming the District Court’s grant of a preliminary injunction to Transcontinental Gas Pipe Line Company, LLC (Transcontinental). This case involves the construction of the “Atlantic Sunrise Expansion Project,” a natural gas pipeline that runs through Pennsylvania, Maryland, Virginia, North Carolina and South Carolina.
Under the Natural Gas Act (NGA), pipeline companies can exercise powers of eminent domain when they are acting in the public interest. The Third Circuit cautions that this is a “standard” eminent domain power, and not a “quick take” that is permitted under another statute.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
UPDATE: ACS Obtains Additional $13.6 Million for General Contractor Client After $19.2 Million Jury Trial Victory
June 27, 2022 —
Kristina Southwell - Ahlers Cressman & Sleight PLLCIn March 2022, ACS obtained a $19.2 million jury verdict in favor of its general contractor client after a lengthy trial against the project owner. Since that time, ACS has successfully obtained awards through post-trial motion practice for an additional $13.6 million in favor of the general contractor. These awards increased to total judgment to more than $32 million.
When moving to enter judgment on the jury verdict, ACS successfully argued for and obtained more than $5 million in prejudgment interest on the jury verdict to compensate the general contractor for having to go years without payment for work performed. ACS also successfully obtained a decree of foreclosure on its construction lien and incorporated language in the judgment requiring the owner to pay an additional $1.9 million in Washington State sales tax on the jury award. Finally, under the authority of the Washington construction lien statute (RCW 60.04.181), ACS sought to recover the attorneys’ fees, costs, and expenses incurred by the general contractor client during the course of litigation. ACS succeeded in obtaining an award for more than $6.6 million for various expenses and costs including ACS’s attorney fees, all the costs of hiring expert witnesses, costs and expenses related to subcontractors’ presentation of pass-through claims against the owner, and other litigation costs and expenses.
Read the court decisionRead the full story...Reprinted courtesy of
Kristina Southwell, Ahlers Cressman & Sleight PLLCMs. Southwell may be contacted at
wendy.wheatmccoy@acslawyers.com
Dorian’s Wrath: How Event Cancellation Insurance Helps Businesses Recoup Losses from Severe Weather
December 16, 2019 —
Sergio F. Oehninger, Andrea DeField & Daniel Hentschel - Hunton Insurance Recovery BlogAs the 2019 hurricane season peaks, the Bahamas and the Southeast United States have already endured a catastrophic storm. Hurricane Dorian not only tragically caused loss of life and substantial property damage, but it also led to the cancellation or postponement of major events, resulting in considerable economic losses for affected companies.
For instance, Hurricane Dorian forced the cancellation of one of the Rolling Stones’ concerts at Hard Rock Stadium in Miami, as well as the cancellation of R&B singer Chris Brown’s concert in Fort Lauderdale. Dorian also affected the college football game between Florida State University and Boise State University in Jacksonville. Having sold 45,000 tickets to the game, officials were forced to move the game inland to Tallahassee at great expense and effort.
The planners, headliners, teams and fans of these and similar events were not the only ones affected by the cancellations and schedule changes. Hotels, restaurants and businesses relying on tourism also were severely impacted by the schedule changes resulting from Hurricane Dorian over Labor Day weekend. Other programming that may have been affected includes conventions and meetings, fairs and festivals, trade shows and exhibitions, or any other corporate events planned to take place outdoors, requiring travel or with ticket-paying audiences.
Reprinted courtesy of Hunton Andrews Kurth attorneys
Sergio F. Oehninger,
Andrea DeField and
Daniel Hentschel
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Ms. DeField may be contacted at adefield@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Fast-Moving Isaias Dishes Out Disruption in the Mid-Atlantic, Northeast
August 24, 2020 —
Jim Parsons - Engineering News-RecordFar from the most powerful storm to strike the Eastern Seaboard, Hurricane Isaias nevertheless proved disruptive enough to rival some infrastructure impacts from Superstorm Sandy in 2012 while also raising concerns about the potential of additional doses of destruction arriving in the coming months.
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Summary Judgment for Insurer Reversed Based on Expert Opinion
May 30, 2022 —
Tred R. Eyerly - Insurance Law HawaiiAfter the trial court discounted the insured's expert witness and granted summary judgment to the insurer, the Florida District Court of Appeal reversed. Morales v. Citizens Prop. Ins. Corp., 2022 Fla. App. LEXIS 1831 (Fla. Ct. App. March 15, 2022).
The insureds' property was allegedly damaged by Hurricane Irma in 2017. They filed a claim with Citizens. Citizens sent its adjuster and eventually denied the claim because the policy did not cover damages caused by wear and tear. Further, there was no coverage for loss caused by "rain . . . unless a covered peril first damages the building causing an opening in a roof or wall and the rain . . . enters through this opening."
The insureds sued and Citizens moved for summary judgment. At the hearing, Citizens' expert, a civil engineer, concluded that there were no storm-created openings in the roof. The insureds engaged a licensed contractor, Steven Delgado, who stated that he found significant damage to the roofing system and water intrusion through the roof. He observed loose shingles which were most likely damaged during Hurricane Irma, allowing for high winds and airborne debris to create small openings permitting water intrusion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com