California Court of Appeal Makes Short Work Trial Court Order Preventing Party From Supplementing Experts
August 06, 2019 —
Garret Murai - California Construction Law BlogYears ago I recommended to a client that we hire a construction defect expert in a case. The client, a thrifty fellow, responded, “But I thought you were the construction expert. Why do I need to hire another expert? A fair question and one that caught me flat footed.
Whether I’m an “expert” or not can be debated, but I explained to the client that while I was an attorney whose practice focused on construction law, I was not someone who he would want to take the stand and testify about the engineering design and seismic stability of pilings. For that, he needed an expert.
In construction litigation it’s not uncommon for parties and their attorneys to hire “experts.” There are even special rules set forth in the California Code of Civil Procedure for disclosing, supplementing and deposing experts, which basically provide as follows:
1. Demand for Exchange of Expert Information: After the court sets a trial date in a case, any party may demand that each party exchange information concerning the experts they intend to have testify at trial;
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
“License and Registration, Please.” The Big Risk of Getting Busted for Working without a Proper Contractor’s License
July 25, 2021 —
Christopher A. Henry & Mia Hughes - ConsensusDocsThe need for contractors to maintain the proper contracting license may seem like a mundane, clerical detail, and generally is just that. If, however, the contractor ignores or mishandles paperwork and the proper license is not in hand, licensing may go from a mundane, clerical detail to a financial catastrophe. An unlicensed contractor may be barred from asserting claims or collecting payments for work already performed; the contractor may even be required to return payments for unlicensed work performed.
A recent case in Georgia, a state that had no state-wide general contractor’s license requirement in effect until 2008 illustrates the risk of unlicensed work.[1] In Saks Management and Associates, LLC v. Sung General Contracting, Inc.,[2] the court ruled that without a license the general contractor did not have the right to enforce a contract. The contractor’s claims for payment failed, and the mundane, clerical error led a major financial loss. This disastrous result for the Georgia contractor is far from an outlier, and is a real risk in many states.
Reprinted courtesy of
Christopher A. Henry, Jones Walker LLP and
Mia Hughes, Jones Walker LLP
Mr. Henry may be contacted at chenry@joneswalker.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Incorrectly Relies Upon "Your Work" Exclusion to Deny Coverage
June 10, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Eleventh Circuit reversed the district court's determination that there was no coverage based upon the policy's "your work" exclusion. Southern-Owners Ins. Co. v. Mac Contractors of Fla, LLC, 2019 U.S. App. LEXIS 10689 (11th Cir. April 11, 2019).
Mac Contractors contracted with the homeowners to custom build their home. After construction began, Mac left the site before completing the project and before the issuance of a certificate of occupancy. The homeowners sued, alleged damage to wood floors and the metal roof.
Southern-Owners originally agreed to defend under the CGL policy, but later withdrew the defense and filed this action for declaratory relief. The parties cross-filed motions for summary judgment. Southern-Owners argued that the "your work" exclusion applied to bar coverage. The "your work" exclusion barred coverage for "'property damage' to 'your work' arising out of it or any part of it and included in the 'products' completed operations hazard.'" The "products' completed operations hazard" included all "'property damage' occurring away from premises you own or rent and arising out of . . . 'your work' except . . . (1) products that are still in your physical possession; or (2) work that has not yet been completed or abandoned."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Billionaire Row Condo Board Sues Developers Over 1,500 Building Defects
September 29, 2021 —
Robert Burnson, BloombergThe condo board at one of New York’s tallest and toniest towers sued the building’s developers, claiming design flaws are to blame for flooding, stuck elevators and “horrible and obtrusive noise and vibration.”
The residential tower at 432 Park Avenue is a 1,396-foot skyscraper overlooking Central Park that was opened in 2015 on the city’s so-called Billionaire Row.
The condo board claims its engineering consultant has identified more than 1,500 construction and design defects — “many of which are described as life safety issues.”
The board that represents the condo owners sued the developers, CIM Group and Macklowe Properties, and the company, also known as sponsor, that the developers formed to build the tower.
The board is seeking $250 million, plus punitive damages, in the lawsuit, filed Thursday in New York Supreme Court.
Read the court decisionRead the full story...Reprinted courtesy of
Robert Burnson, Bloomberg
UCF Sues Architects and Contractors Over Stadium Construction Defects
October 19, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.The University of Central Florida (UCF) filed suit over alleged construction defects of their 45,000-seat arena including the claim of “premature wear of the steel,” spokesman Chad Binette stated, according to the Orlando Sentinel.
Bid documents suggest that rust may be an issue. UCF recently sought contractors for “Stadium Emergency Rust Repairs.” The Orlando Sentinel reported that the university stated “the word ‘emergency’ reflects deadlines for the football season instead of safety concerns.” Other documents also claimed ongoing rust remediation.
The UCF stadium had earned the nickname “Bounce House” from the arena “subtly swaying as fans jumped together to the song ‘Kernkraft 400’ by Zombie Nation. UCF spent hundreds of thousands of dollars in 2008 stiffening the underpinnings of the stadium by bolting additional steel to about 160 beams,” according to the Orlando Sentinel. Officials claim that the stadium was never unsafe.
Read the court decisionRead the full story...Reprinted courtesy of
Trump Administration Waives Border Wall Procurement Rules
March 23, 2020 —
Mary B. Powers & Debra K. Rubin - Engineering News-RecordActing Homeland Security Secretary Chad Wolf on Feb. 20 waived federal contracting rules to expedite construction of the U.S-Mexico border wall in California, Arizona, New Mexico and Texas, citing legal authority under several U.S. laws, some dating back to the 1990s, to deal with what he claimed is "an acute and immediate need to construct physical barriers and roads ... to prevent unlawful entries."
Reprinted courtesy of
Mary B. Powers, Engineering News-Record and
Debra K. Rubin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Risk Management for Condominium Conversions
July 31, 2013 —
David McLain, Higgings, Hopkins, McLain & Roswell, LLCOne of the bright spots in the Colorado construction industry over the last few years has been the construction of for-rent apartments. It seems as though apartments are going up everywhere you look along the Front Range. As market forces change, it will be interesting to see whether these units will remain apartments or whether they will be converted into for-sale condominiums or townhouses. One of the risk management strategies we have recently discussed with our general contractor clients who have been asked to build apartments is to ensure that the project remains a for-rent apartment project through the applicable statute of repose, conservatively assumed to be eight years. Unfortunately this is not always feasible, usually because the owner and/or lender are not interested in encumbering the property for such a long period of time, and want to retain the ability to convert the project if and when market forces allow, even if that is before the running of the statute of repose. The purpose of this article is to discuss the insurance and risk management ramifications of converting a project too early.
I have recently heard from several sources in the insurance industry that there are owners and contractors who are currently building apartments with the idea that they will be held as apartments for two to three years and then converted to for-sale condominiums or townhomes. While this strategy may have great appeal from a business point of view, it has a very serious risk management downside. Apparently, these owners and contractors are operating under the mistaken belief that they will have no liability exposure to the ultimate purchasers of the converted units or to the homeowners association for construction defects. This is an incorrect belief.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLainDavid M. McLain can be contacted at
mclain@hhmrlaw.com
Another Las Vegas Tower at the Center of Construction Defect Claims
November 07, 2012 —
CDJ STAFFAccusations are coming from both sides over construction defects at a Las Vegas tower, only this time, it’s not the Harmon Towers, it’s Hilton Grand Vacations, which is part of the Planet Hollywood Resort. The project was originally dubbed PH Towers Westgate, and it was developed by Westgate Resorts, which is suing the contractor, Tutor-Saliba for $10 million over late completion and construction defects.
Among the defects Westgate is claiming are cracked floor tiles in the valet lobby and cracks and delamination of the pool deck. Tutor-Saliba argues that the failure of the valet lobby floor is due to Westgate specifying only 1/16th inch-wide grouting, instead of the specified ¼ inch, and Westgate’s refusal to allow expansion joints on the pool deck has lead to problems there. Westgate’s attorney, Robert Schumacher, attributes the problems to “shoddy construction practices.”
According to the article in the Las Vegas Review Journal, plans were only 60 percent complete when construction began, leading to “thousands of change orders.” Despite not meeting an August completion deadline, Tutor-Saliba is claiming it is owed a $1.5 million bonus nevertheless.
Read the court decisionRead the full story...Reprinted courtesy of