When Subcontractors Sue Only the Surety on Payment Bond and Tips for General Contractors
August 13, 2019 —
Ira M. Schulman & Emily D. Anderson - ConsensusDocsPayment bonds have been a staple of public construction projects since 1874, when the U.S. Congress first passed the Heard Act, which required that contractors obtain payment bonds for public projects to ensure that subcontractors and material suppliers have a way to recover their damages if an upstream contractor fails to pay for work performed and materials furnished on the project. The 1874 Heard Act has since been replaced by the 1935 Miller Act, and the concept has been expanded to construction projects funded by the states through state statutes known as “Little Miller Acts.” But the structure remains the same: On most public projects where the project’s cost exceeds $100,000, the prime contractor (the bond principal) is required to obtain a payment bond from a surety equal to the contract price to guarantee to subcontractors and material suppliers (the bond obligees) that the surety will pay for labor and materials under certain statutory or contractual conditions should the contractor fail to make payment.
A surety is jointly and severally liable with the contractor to the subcontractor, which means that the subcontractor may seek recovery against either the contractor or the surety or both, and the contractor and surety will be liable for the damages together. Put another way, in most states and in federal court, an unpaid subcontractor has the right to sue only the surety on the payment bond without joining the contractor because a contract of suretyship is a direct liability of the surety to the subcontractor.1 When the contractor fails to perform, the surety becomes directly responsible at once — it is unnecessary for the subcontractor to establish that the contractor failed to carry out its contract before the obligation of the surety becomes absolute.
Reprinted courtesy of
Ira M. Schulman, Pepper Hamilton LLP and
Emily D. Anderson, Pepper Hamilton LLP
Mr. Schulman may be contacted at schulmani@pepperlaw.com
Ms. Anderson may be contacted at andersone@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Duty to Design and Maintain Reasonably Safe Roadways Extends to All Persons. (WA)
February 25, 2014 —
Natasha Khachatourians – Scheer & Zehnder LLP Liability NewsletterCase: Lowman v. Wilbur, et al., 178 Wn.2d 165, 309 P.3d 3.87 (2013).
Issue: If a passenger’s injuries are in fact caused by the placement of a utility pole too close to a roadway, can the injuries be deemed too remote for purposes of legal causation? NO.
Facts: Plaintiff was a passenger in a vehicle that lost control and collided with a utility pole that was 4.47 feet from the edge of the roadway. The vehicle’s driver was under the influence of alcohol. Plaintiff sued the driver as well as the utility company and Skagit County for negligence. The trial court granted the utility company and Skagit County’s summary judgment motion, finding that the negligent placement of the utility pole was not a legal cause of plaintiff’s injuries.
The issue before the Supreme Court was whether a negligently placed utility pole could be the legal cause of a resulting injury.
Read the court decisionRead the full story...Reprinted courtesy of
Natasha Khachatourians, Scheer & Zehnder LLP Ms. Khachatourians may be contacted at
natashak@scheerlaw.com
Brown and Caldwell Appoints Stigers as Design Chief Engineer
December 13, 2022 —
Brown and CaldwellWALNUT CREEK, Calif., Dec. 06, 2022 — Brown and Caldwell today announces Vice President Tracy Stigers has been appointed as design chief engineer in recognition of four decades of exceptional technical leadership and client service. She is the first woman in the firm's 75-year history to hold the esteemed title.
Stigers will lead all design from a technical and delivery expertise perspective across all of Brown and Caldwell's design initiatives, implementing innovation, quality control, and project delivery throughout North America and the Pacific.
Since joining the leading environmental engineering and construction services firm in 1980, Stigers has progressed from junior engineer to one of its top technical and delivery experts. She has vast experience in the design and construction of large-scale wastewater conveyance, treatment, and reuse facilities, including serving as project manager on the San Francisco Public Utilities Commission's $2.3 billion Biosolids Digester Facilities Project, the largest value design job in Brown and Caldwell's history.
Early in her career, Stigers worked alongside and was mentored by company co-founder Dave Caldwell, helping shape its tradition of solving the most challenging water and environmental challenges. Her dedication to upholding Brown and Caldwell's reputation for project excellence and innovation was commended by CEO Rich D'Amato:
"Tracy is the epitome of quality, commitment, and technical prowess," he said. "Her leadership, knowledge, and legacy of delivering solutions to clients perfectly embody our heritage and is a shining example for tomorrow's aspiring engineering leaders."
Throughout her career, Stigers has held numerous leadership roles at industry organizations, including sitting on the board of trustees for the Water Environment Federation and the California Water Environment Association. She is a current member of the Clarkson University Engineering Advisory Council.
About Brown and Caldwell
Headquartered in Walnut Creek, California, Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and 1,800 professionals across North America and the Pacific. For 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients' expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decisionRead the full story...Reprinted courtesy of
Stacking of Service Interruption and Contingent Business Interruption Coverages Permitted
December 10, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court found that stacking of interruption coverages was allowed based up the language of the policy. Lion Oil Co. v. Nat'l Union Fire Ins. Co., 2015 U.S. Dist. LEXIS 148261 (W.D. Ark. Nov. 2, 2015).
The insured's oil line was ruptured, causing an interruption of crude oil delivery service. The insured held policies issued by National Union.
The policies included multiple time element extensions. One extension related to Service Interruption which promised to insure against loss for:
Service Interruption: electrical, steam, gas, water, sewer, incoming or outgoing voice, data, or video, or an other utility or service transmission lines and related plants, substations and equipment situated on or outside of the premises.
Both parties agreed that the service interruption provision was unambiguous and that the court should give effect to the plain language of the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Alabama Federal Magistrate Recommends Dismissal of Construction Defect Declaratory Judgment Action Due to Expanded Duty to Defend Standard
May 31, 2021 —
Anthony L. Miscioscia & Margo Meta - White and WilliamsWhile the starting point for assessing an insurer’s duty to defend requires comparing the allegations contained within a complaint to the language contained within the insured’s policy, the majority of states require an insurer to do more. In Alabama, a failure of the underlying complaint to allege damages falling within the policy’s terms is not necessarily fatal to coverage – if there are facts provable by admissible evidence to place the loss within coverage.
The U.S. District Court for the Southern District of Alabama recently examined Alabama’s broadened duty to defend standard in Frankenmuth Mutual Insurance Company v. Gates Builders, No. 20-00596, 2021 U.S. Dist. LEXIS 83645 (S.D. Ala. Apr. 29, 2021). In Frankenmuth, the magistrate judge was tasked with determining whether the court should abstain from hearing an insurer’s declaratory judgment coverage action pending the resolution of the underlying state court action.
The underlying state court action arose out of an allegedly defective construction project. Frankenmuth’s insured, Gates Builders, was hired to perform exterior and structural rehabilitation work at the Resort Conference Center Condominium (the Condominium) in Gulf Shores, Alabama. The project began in July 2014 and concluded in June 2015. In 2019, Gates Builders was informed that the Condominium’s decks were sagging. Gates Builders shored up the decks and provided the Condominium with a quote for the cost of repairs. In July 2020, the Condominium’s Association filed suit, alleging that the work performed in 2014 and 2015 was faulty and had caused damage to the Condominium.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams and
Margo Meta, White and Williams
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Ms. Meta may be contacted at metam@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
SunTrust Will Pay $968 Million to Resolve Mortgage Probes
June 18, 2014 —
Tom Schoenberg – BloombergSunTrust Banks Inc. (STI) agreed to pay $968 million to resolve federal and state claims that a unit misrepresented the quality of mortgages the bank originated and deceived homeowners on loans it serviced.
The agreement covers loans SunTrust Mortgage made from January 2006 through March 2012 that were backed by the Federal Housing Administration even though they didn’t meet agency requirements, the Justice Department said in a statement today. Atlanta-based SunTrust disclosed the agreement in an October regulatory filing and has already accounted for the payment.
“SunTrust’s conduct is a prime example of the widespread underwriting failures that helped bring about the financial crisis,” Attorney General Eric Holder said in a statement. “We will continue to hold accountable financial institutions that, in the pursuit of their own financial interests, misuse public funds and cause harm to hardworking Americans.”
Read the court decisionRead the full story...Reprinted courtesy of
Tom Schoenberg, BloombergMr. Schoenberg may be contacted at
tschoenberg@bloomberg.net
Seattle Independent Contractor Ordinance – Pitfalls for Unwary Construction Professionals
October 09, 2023 —
Travis Colburn - Ahlers Cressman & SleightChapter 14.34 of the Seattle Municipal Code is a relatively new ordinance that can affect the parties to a construction contract for work performed within the City of Seattle’s city limits. The Independent Contractor Protection Ordinance (“ICPO”) was enacted to provide self-employed persons, or entities composed of not more than one person, regardless of corporate form, recourse for timely payment for work performed. The ICPO applies to contracts of $600[i] or more between an independent contractor and a hiring entity where the work, in whole or in part, is known to be performed within the City of Seattle’s city limits.[ii] The ICPO cannot be waived by parties to a contract.[iii]
Historically, the primary legal recourse for non-payment or late payment for work performed under a contract involves an expensive breach of contract action, and one reason the ICPO was enacted was to give greater protection to a growing number of Washington independent contractors who report problems with timely and accurate payment.
The ICPO affects “hiring entities” or any individual, partnership, association, corporation, business trust, or any entity, person or group of persons, or a successor thereof, that hires independent contractors to provide services within the scope of a hiring entity’s business or commercial activities. In the construction context, most general contractors, subcontractors, design professionals, and design consultants should be aware of this ordinance, as well as certain owners[iv] and development-side entities.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
Contract Change # 10: Differing Site Conditions (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaPreviously, the A201 required a Contractor to provide notice to the Owner and Architect within 21 days after discovery of unforeseen site conditions. This notification is required prior to the conditions being disturbed, so as to allow the Design Team the ability to evaluate the site and determine the compensability of any such differing conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina