Anti-Concurrent Causation Clause Bars Coverage for Pool Damage
February 23, 2016 —
Tred R. Eyerly – Insurance Law HawaiiRelying upon the policy's anti-concurrent causation clause, the Illinois Court of Appeals affirmed the trial court's ruling that there was no coverage for a pool that popped out of the ground. Bozek v. Erie Ins. Group, 2015 Ill. App. LEXIS 940 (Ill. Ct. App. Dec. 17, 2015).
Following a rainstorm, the insureds reported damage to the swimming pool to Erie. An investigation determined that the heavy rain saturated soils around the pool. This created a significant uplift hydrostatic pressure. The weight of the water in the pool typically prevented the uplift forces, but the pool had been emptied to clean debris making it susceptible to uplift. The pool had a pressure relief valve to prevent uplift, but it was not working properly.
As a result, the pool was damaged to the point that it had to be replaced in its entirety. The heaving of the pool also damaged the concrete slab around the pool, which also had to be replaced.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
A Year After Fatal Genoa Viaduct Collapse, Replacement Takes Shape
November 04, 2019 —
Peter Reina - Engineering News-RecordNearly 14 months after the Morandi viaduct collapsed in Genoa, Italy, killing 43 people, crews placed the first section of a 1,067-meter-long, 19-span steel and concrete replacement structure.
Reprinted courtesy of
Peter Reina, Engineering News-Record
Mr. Reina may be contacted at reina@btinternet.com
READ THE FULL STORY... Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Round-Up (01/11/23) – Construction Tech, Housing Market Confidence, and Decarbonization
February 01, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogTo kick of 2023, this week’s news round-up dives into contech inventions projected to impact the industry, shifting home prices and buyer confidence, investors prioritizing decarbonization efforts, and more.
- From holograms to robots, these 6 contech innovations are projected to tackle some of construction’s toughest issues. (Robyn Griggs Lawrence, Construction Dive)
- Manufacturing and data center projects will support the U.S. construction industry as work begins to slow on retail projects, warehouses and offices. (Sebastian Obando, Construction Dive)
- Despite macroeconomic headwinds, doubling down on decarbonization efforts is projected to be top-of-mind for investors and occupiers in 2023. (JLL)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
California Rejects Judgments By Confession Pursuant to Civil Code Section 1132
May 08, 2023 —
Drew M. Jorgenson & Louis "Dutch" Schotemeyer - Newmeyer DillionThe Elimination of Judgment by Confession
Following in the footsteps of Massachusetts and Florida, California recently updated California Code of Civil Procedure section 1132 which renders judgments by confession unenforceable and inadmissible in any superior court, effective January 1, 2023. The bar is not retroactive, so judgments by confession obtained or entered before January 1, 2023 are still valid. Moving forward, consider the following.
What is a Judgment By Confession?
A judgment by confession, also known as a confession of judgment or "cognovit" clause, is a mechanism by which a debtor agrees that a creditor may summarily obtain a legal judgment against that debtor and enforce it in the event of the debtor's breach of contract or default. In other words, it is a private admission by a debtor that they are liable for a debt without the need for a trial, and consequently, agree to forfeit very important rights. Most importantly, parties agreeing to such clauses are waiving rights such as the right to notice of the judgment and the right to assert defenses against the creditor or third party's claims. Historically, without any judicial involvement, these types of out-of-court judgments would be enforceable.
Reprinted courtesy of
Drew M. Jorgenson, Newmeyer Dillion and
Louis "Dutch" Schotemeyer, Newmeyer Dillion
Mr. Jorgenson may be contacted at drew.jorgenson@ndlf.com
Mr. Schotemeyer may be contacted at dutch.schotemeyer@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Prior Occurrence Exclusion Bars Coverage for Construction Defects
April 11, 2022 —
Tred R. Eyerly - Insurance Law HawaiiWhile the insured's faulty work constituted an occurrence under Florida law, a prior occurrence exclusion barred coverage. Pro-Tech Caulking & Waterproofing v. TIG Ins. Co., 2022 U.S. Dist. LEXIS 12319 (S.D. Fla. Jan. 19, 2022).
Pro-Tech was a waterproofing subcontractor for construction of a oceanfront condominium building and was responsible for the installation of waterproofing systems on the Project. Pro-Tech entered into a separate contract with the developer, BRE Point Parcel, LLC to install a traffic coating on the garage floors.
BRE sued the general contractor, Pro-Tech and others for construction defects. The underlying action alleged that Pro-Tech, among other things, failed to wrap the filter fabric to protect the weep holes, improperly installed sealants between the stucco and the underside of the horizontal tile at the balcony slab edge, and failed to properly install traffic coating in one garage. The underlying complaint did not state exactly when the "property damage" resulting from Pro-Tech's alleged defective work occurred.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Fort Lauderdale Partner Secures Defense Verdict for Engineering Firm in High-Stakes Negligence Case
June 10, 2024 —
Lewis Brisbois NewsroomFort Lauderdale, Fla. (June 3, 2024) - Fort Lauderdale Managing Partner Cheryl Wilke recently secured a defense verdict for civil engineering firm Gulfstream Design Group and its owner, Matthew Lahti, in a high-stakes professional negligence case in which the plaintiff sought more than $20 million. The verdict by a six-person jury in St. Augustine followed a nine-day trial.
The case involved a 100-acre tract of land in St. Johns County, Florida, owned by the plaintiff, Cynthia Taylor. The land was zoned for rural farming, and she wished to sell the property for development. She entered into a contract with Southeast Georgia Acquisitions (“SGA”) to sell the property with the goal of creating a 200-home subdivision. SGA hired Doug Burnett as land use counsel and our client, Gulfstream Design Group, as the civil engineer to design the project.
In St. Johns County, only a property owner can submit a Planned Unit Development Plan (“PUD”) for the purpose of rezoning. In this case, Burnett and Gulfstream created text and a proposed map for the PUD and submitted it for approval. The PUD was approved first at the staff level, then by planning and zoning and then by the County Commission. All the services were provided prior to closing with PUD approval, a condition of sale.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Court Voids Settlement Agreement in Construction Defect Case
September 01, 2011 —
CDJ STAFFA U.S. District Court Judge in Florida has ruled in favor of a company that sought to void a settlement agreement. The case, Water v. HDR Engineering, involved claims of construction defects at Florida’s C.W. Bill Young Regional Reservoir. The Tampa Bay Water Authority attributed these to both HDR Engineering’s design and Bernard Construction Company which had built the embankment. Bernard Construction filed a complaint against their subcontractor, McDonald.
Tampa Bay Water settled with Bernard Construction and McDonald, in an agreement that set a minimum and maximum settlement, but also would “prohibit Barnard and McDonald from presenting any evidence on several claims and positions of TBW, to require Barnard to call certain witnesses at trial, to preclude Barnard and McDonald from calling other witnesses, and to restrict the filing of trial and post-trial motions.” HDR Engineering moved to void the agreement as collusive.
The judge that the agreement¬? contained “133 paragraphs of ‘Agreed Facts’ that the parties stipulated would survive any order declaring the Settlement Agreement void or unenforceable.” He characterized these as stipulating “that Barnard neither caused nor contributed to TBW’s damages.” HDR motioned that a summary judgment be given to Barnard Engineering.
The court found that “the evidence identified by TBW is patently insufficient to survive summary judgment.” Further, TBW’s expert initially held Barnard responsible for “lenses, pockets, streaks and layers within the embankment,” but then later withdrew this assigning the responsibility to HDR. Further, the court notes that, “TBW’s arguments that lenses, pockets, streaks, and layers in the soil wedge caused or contributed to its damages and that Barnard is liable for those damages have been foreclosed by the Agreed Facts.”
As TBW failed to provide sufficient evidence to withstand summary judgment, the court granted summary judgment, mooted the claim against McDonald, and terminated the agreement between TBW and the other parties.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “Who Needs Them”
August 28, 2023 —
Daniel Lund III - LexologyWho needs them?
So argued a surety pursuing recovery under its general agreement of indemnity when the indemnitors urged a Louisiana federal court to dismiss the surety’s complaint for failure to join various allegedly required parties as defendants in the litigation.
As part of its court action, the surety moved for preliminary injunction to enforce its collateral security rights. In response thereto, the indemnitors informed the court that if the injunction were to be granted, the indemnitors would “be forced to sell assets that are encumbered by security interests senior to those held by” the surety. In connection therewith, the indemnitors demanded that the other creditors be joined in the action or the lawsuit dismissed. The indemnitors also urged that the public project owner be joined as a party because the surety was seeking proceeds from the project that were still in the possession of the project owner.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at