Indemnitor Owes Indemnity Even Where Indemnitee is Actively Negligent, California Court Holds
June 15, 2017 —
Garret Murai - California Construction Law BlogIndemnity provisions are one of the most fought over provisions in design and construction contracts. But while parties generally understand the intent behind indemnity provisions — that one party (the “indemnitor”) agrees to indemnify (and often defend as well) another party (the “indemnitee”) from and against claims that may arise on a project — few understand how they are actually applied.
In a recent Court of Appeals decision, Oltmans Construction Company v. Bayside Interiors, Inc. (March 30, 2017), Case No. A147313, the California Court of Appeals for the First District examined an indemnity provision and its “except to the extent of” provision whereby a subcontractor agreed to indemnify (and defend) a general contractor from claims arising on a project “except to the extent of” the general contractor’s active negligence or willful misconduct and whether such language either: (1) bars a general contractor from seeking indemnity where the general contractor was actively negligent; or (2) simply bars a general contractor from seeking indemnity where the general contractor was actively and solely negligent, thereby, requiring a subcontractor to indemnify the general contractor where the negligence of another party may have also contributed to the injury or damage.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Private Statutory Cause of Action Under Florida’s Underground Facility Damage Prevention and Safety Act
July 11, 2021 —
David Adelstein - Florida Construction Legal UpdatesFlorida’s Underground Facility Damage Prevention and Safety Act is set forth in Florida Statutes Chapter 556. Any owner or operator of underground infrastructure as well as contractors that perform underground excavation and demolition operations are familiar (or, need to be familiar) with this Act and the requirements it imposes on them.
In a nutshell, this Act requires excavators to notify operators of underground facilities (e.g., pipelines, cables, sewers) through a notification system before excavating or demolishing an underground location. Then notification system gives the operator of the underground facility two days’ advance notice that an excavation will be taking place. After receiving this notice, the operator of the underground facility must mark the area where its infrastructure is located which could be affected by the underground excavation or demolition operations. The Act further imposes duties on excavators to use increased caution, supervise mechanized equipment, perform excavation and demolition operations in a careful an prudent manner, and to re-notify the notification system if the operator’s marking is no longer visible so the location of the operator’s underground facility can be re-marked.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
WSHB Ranked 4th Most Diverse Law Firm in U.S.
July 14, 2016 —
Beverley BevenFlorez-CDJ STAFFAmerican Lawyer, in its annual Diversity Scoreboard Survey, ranked Wood Smith Henning & Berman LLP (WSHB) one of the four top law firms in the nation. Scores are based upon the firms’ combined percentage of minority lawyers as well as minority partners in U.S. offices.
“Historically, law has not been among the most diverse of professions,” Partner Domingo Tan, Chair of WSHB’s Recruiting Committee, stated according to the firm’s media release. “This trend has recently begun to change and I am proud that our firm is one of the national leaders in recognizing and celebrating diversity as a core value.”
WSHB Partner Jade Tran explained how the firm’s diversity benefits its clients: “At WSHB, we are a litigation powerhouse built upon the experiences drawn from our diverse attorney backgrounds. It’s this diversity that also makes our attorneys relatable to our clients who themselves stem from diverse backgrounds.”
Read the court decisionRead the full story...Reprinted courtesy of
Settlement Agreement? It Ain’t Over ‘Til it’s . . . Final, in Writing, Fully Executed, and Admissible
April 12, 2021 —
Todd Likman - Colorado Construction LitigationAs litigators we have all been there: nearing the end of a hard-fought mediation that lasted all day. Your significant other texts to ask what is for dinner; daycare closes in thirty minutes; the dog needs to be let out. The mediator, a retired judge, gently reminds you of his prior commitment—a speaking engagement at a volunteer charity dinner event that night. Though the parties started the day at opposite ends of the spectrum, after numerous counteroffers, persistent negotiation, and mediation tactics, they finally strike a deal.
As the mediator prepares a document memorializing the terms of settlement, the parties wait with bloodshot eyes, and a sense of guarded accomplishment considering compromises were
made, but alas, an outcome seems certain. You text your significant other to indicate that you will pick something up for dinner on your way home.
Then, the mediator informs you that computer problems are preventing finalization and transmission of the document for signature. The mediator offers to send an e-mail setting forth the material settlement terms and asks each party to respond via e-mail to confirm the terms are correct, which the parties do. After a quick e-mail to your experts and case team asking them to cease trial preparation work, you leave for home.
Read the court decisionRead the full story...Reprinted courtesy of
Todd Likman, Higgins, Hopkins, McLain & RoswellMr. Likman may be contacted at
likman@hhmrlaw.com
Seattle Developer Defaults on Renovated Office Buildings
December 23, 2024 —
Anna Edgerton - BloombergA major developer in downtown Seattle defaulted on a loan backed by two of its most prized office properties, including one that formerly housed a branch of the Federal Reserve Bank of San Francisco.
Firms tied to Martin Selig Real Estate are in default on a more than $200 million loan, according to letters from lender Acore Capital dated Nov. 15 that were filed in Washington’s King County. The buildings would change ownership 30 days after that notice if no other action is taken, according to the letters.
Read the court decisionRead the full story...Reprinted courtesy of
Anna Edgerton, Bloomberg
Retainage: What Contractors Need to Know and Helpful Strategies
June 04, 2024 —
Gerard J. Onorata - ConsensusDocsIntroduction
Most, if not all, construction contracts contain a provision for “retainage.” The origin and concept of retainage dates back to the railroad boom that embraced Great Britain in the 1840s. In its simplest terms, retainage is a mechanism by which an owner or general contractor withholds disbursement of funds from the payment of a requisition in order to secure future performance of a contract and/or to pay for repair of defectively performed work. Retainage typically ranges from five to ten percent, with the amount being reduced as the project progresses to substantial and final completion. One of the reasons for withholding retainage is to incentivize a contractor to complete its work in accordance with the contract terms and conditions. While this may be well-intentioned in concept, it all too often leads to abuse that impacts project cash flow and raises tension between the parties. This typically happens on projects that have delay issues, deficient drawings, and/or claims of defective work. When a project has “gone bad,” the withholding of retainage is one of the first things that an owner will latch onto in order to leverage its position against a contractor. In order for a contractor to put itself in the best position possible, the following negotiation techniques and protective measures should be kept in mind.
Know Your Applicable Statute
Every state except West Virginia has statutes in place that govern the payment of retainage on public projects. On federal projects, the amount of retainage withheld shall not exceed ten percent as set forth in the Federal Acquisition Regulations (“FAR”). The common thread running through these statutes is the payment of interest as a remedy when the retainage is not timely paid. Historically, most retainage statutes were applicable only to publicly funded projects. This has recently changed with a substantial number of state legislatures recognizing that the payment of retainage on private projects was a serious enough problem to warrant regulation. These include Alabama, Arizona, California, Colorado, Connecticut, Idaho, Illinois, Kansas, Louisiana, Maine, Maryland, Massachusetts, Minnesota, Missouri, Montana, Nebraska, Nevada, New Mexico, New York, North Carolina, North Dakota, Ohio, Oregon, Pennsylvania, Rhode Island, South Carolina, South Dakota, Tennessee, Texas, Utah, and Vermont. New York’s retainage laws relating to private projects were enacted only this past November.
Read the court decisionRead the full story...Reprinted courtesy of
Gerard J. Onorata, Peckar & AbramsonMr. Onorata may be contacted at
gonorata@pecklaw.com
Insurer’s Discovery Requests Ruled to be Overbroad in Construction Defect Suit
October 28, 2011 —
CDJ STAFFThe US District Court has ruled in the case of D.R. Horton Los Angeles Holding Co. Inc. v. American Safety Indemnity, Co. D.R. Horton was involved in a real estate development project. Its subcontractor, Ebensteiner Co., was insured by ASIC and named D.R. Horton as an additional insured and third-party beneficiary. D.R. Horton, in response to legal complaints and cross-complaints, filed for coverage from ASIC under the Ebensteiner policy. This was refused by ASIC. ASIC claimed that “there is no potential coverage for Ebensteiner as a Named Insurer and/or D.R. Horton as an Additional Insured.” They stated that “the requirements for coverage are not satisfied.”
The case same to trial with the deadline for discovery set at March 1, 2011. ASIC stated they were seeking the developer’s “job file” for the Canyon Gate project. D.R. Horton claimed that ASIC’s discovery request was overbroad and that it would be “unduly burdensome for it to produce all documents responsive to the overbroad requests.”
D.R. Horton did agree to produce several categories of documents, which included:
“(1) final building inspection sign-offs for the homes that are the subject of the underlying litigation;(2) an updated homeowner matrix for the underlying actions; (3) the concrete subcontractor files; (4) the daily field logs for D.R. Horton’s on-site employee during Ebensteiner’s work; (5) documents relating to concrete work, including documents for concrete suppliers; (6) documents relating to compacting testing; (7) documents relating to grading; and (8) D.R. Horton’s request for proposal for grading”
The court found that the requests from ASIC were overbroad, noting that the language of the ASIC Request for Production of Documents (RFP) 3-5 would include “subcontractor files for plumbing, electric, flooring, etc. - none of these being at issue in the case.” The court denied the ASIC’s motion to compel further documents.
The court also found fault with ASIC’s RFPs 6 and 7. Here, D.R. Horton claimed the language was written so broadly it would require the production of sales information and, again, subcontractors not relevant to the case.
Further, the court found that RFPs 8, 10, 11, and 13 were also overbroad. RFP 8 covered all subcontractors. D.R. Horton replied that they had earlier complied with the documents covered in RFPs 10 and 11. The court concurred. RFP 13 was denied as it went beyond the scope of admissible evidence, even including attorney-client communication.
The court denied all of ASIC’s attempts to compel further discovery.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Remodel Gets Pricey for Town
December 30, 2013 —
CDJ STAFFUsually when home gets remodeled, it’s the homeowners who encounter unexpected expenses, but in Clearwater, Florida, it’s the town. Clearview has spent about $40,000 trying to determine if changes to a home are a “substantial improvement,” and the bill could get bigger, according to TBNweekly.com.
The home in question, that of David and Aileen Blair, is in a flood zone, and city rules would require the alterations to comply with flood drainage-resistance provisions, but only if it is a “substantial improvement.” The Blairs applied for the remodel permit in April 2001, and it was granted more than 10 years later, in July 2011. Work started soon after until the city put a stop to it.
The Blairs sued, claiming that as the city issued the permit, they assumed the plans were approved, and that the partially-completed renovation now diminishes the value of their home. The city has approved an additional $160,000 in outside legal counsel to respond to the Blair’s lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of