Statute of Limitations Upheld in Construction Defect Case
September 30, 2011 —
CDJ STAFFThe Missouri Court of Appeals has ruled in Ball v. Friese Construction Co., finding that Mr. Ball’s claims were barred by the statute of limitations.
Mr. Ball hired Friese Construction Company to build a single-family home. The sale was completed on March 29, 2001. That December, Mr. Ball complained of cracks in the basement floor. SCI Engineering, n engineering firm, hired by Friese, determined that the home’s footing had settled and recommended that Mr. Ball hire a structural engineer to determine if the footings were properly designed and sized. In September 2002, the structural engineer, Strain Engineering, determined that the cracks were due to slab movement, caused in part by water beneath the slab, recommending measures to move water away from the foundation. In 2005, Mr. Ball sent Friese correspondence “detailing issues he was having with the home, including problems with the basement slab, chimney structure, drywall tape, and doors.” All of these were attributed to the foundation problems. In 2006, Friese stated that the slab movement was due to Ball’s failure to maintain the storm water drains.
In 2009, Ball received a report from GeoTest “stating the house was resting on highly plastic clay soils.” He sued Friese in May, 2010. Friese was granted a summary judgment dismissing the suit, as the Missouri has a five-year statute of limitations. Ball appealed on the grounds that the extent of the damage could not be determined until after the third expert report. The appeals court rejected this claim, noting that a reasonable person would have concluded that after the conclusion of SCI and Strain Engineering that “injury and substantial damages may have occurred.”
The court concluded that as there were not “continuing wrongs causing new and distinct damages,” he should have filed his lawsuit after the first two expert reports, not waiting seven years for a third expert to opine.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Four White and Williams Lawyers Recognized as "Lawyer of the Year" by Best Lawyers®
September 19, 2022 —
White and Williams LLPWhite and Williams is proud to announce that Chuck Eppolito, Michael Kassak, Anthony Miscioscia and Christian Singewald have been recognized by U.S. News – Best Lawyers® as a “Lawyer of the Year” in their respective practices. "Lawyer of the Year" recognitions are awarded to individual lawyers with the highest overall peer-feedback for a specific practice area and geographic location.
Chuck Eppolito was named in the area of Litigation - Heath Care in Philadelphia, PA. His practice consists primarily of medical malpractice defense as well as other insurance-related defense, including general negligence, electrical engineering and product liability issues in utilities cases. Chuck's clients include hospitals and physicians throughout Pennsylvania, utility companies and insurance carriers, including primary, excess and reinsurance, throughout the nation.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Insurer’s Consent Not Needed for Settlement
October 14, 2013 —
CDJ STAFFThe Texas Supreme Court has concluded in Lennar Corp. v. Markel Am. Ins. Co. that “the costs incurred by a builder to locate and repair damage caused by the builder’s defective product are covered under its general liability insurance policy.” Hunton & Williams have issued a Client Alert discussing the case.
For the background of the case, Lennar built about 800 homes using EIFS. The EIFS trapped water and the homes suffered from rot, structural damage, mold, mildew, and termites. Lennar fixed all the homes so built, avoiding litigation. Lennar “notifed its insurers of the defects and invited its insurers to participate in the proactive remediation program.”
A lower court had agreed with Markel, one of Lennar’s insurers, that the losses were not “caused by property damage,” and that Lennar should not have made “voluntary payments without Markel’s consent.” The Texas Supreme Court granted review, rejecting Markel’s argument and affirming the jury’s finding.
According to Hunton & Williams, the implications of the Texas Lennar decision is that it “confirms that all insurers with policy in effect at the time of property damage are responsible for all sums for which the policyholder is liable.”
Read the court decisionRead the full story...Reprinted courtesy of
Hold on Just One Second: Texas Clarifies Starting Point for Negligence Statute of Limitations
July 11, 2022 —
Lian Skaf - The Subrogation StrategistIn construction or similar ongoing projects, problems often pop up. Sometimes they can pop up again and again. Making things even more complicated, one problem may affect another, seemingly new problem. When these construction problems result in property damage, timelines tend to overlap and determining when a statute of limitation begins to run for a particular claim can be difficult. Especially in states with short statute of limitations for tort claims like Texas, knowing when a statute begins to run is crucial for a subrogation professional.
In Hussion St. Bldgs., LLC v. TRW Eng’rs, Inc., No. 14-20-00641-CV, 2022 Tex. App. LEXIS 2193, 2022 WL 1010313, the Court of Appeals of Texas provided clarity on when the two-year statute of limitations for tort claims begins to run. Reversing the judgment from the lower court, the appellate court denied summary judgment to the defendant, holding that, despite there being existing issues with the ongoing construction project, the negligence cause of action for Hussion Street Buildings, LLC (Hussion) did not begin to run more than two years prior to filing suit.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
The Privilege Is All Mine: California Appellate Court Finds Law Firm Holds Attorney Work Product Privilege Applicable to Documents Created by Formerly Employed Attorney
June 29, 2017 —
David W. Evans & Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Tucker Ellis LLP v. Superior Court (A148956 – Filed 6/21/2017), the First Appellate District held that (1) the holder of the attorney work product privilege is the employer law firm rather than the former employee attorney who created the privileged documents while a firm employee, and (2) as a result, the firm did not owe a duty to obtain the former attorney’s permission before disclosing the subject documents to third parties.
In Tucker Ellis LLP, the attorney, while still employed by Tucker Ellis, exchanged a series of e-mails with a consultant retained by the firm to assist in asbestos litigation for a client. The firm also entered into an agreement with the consultant to summarize scientific studies on the causes of mesothelioma in a published review article. After the attorney departed the firm, Tucker Ellis was served with a subpoena in connection with a matter pending in Kentucky for the production of communications with the consultant regarding the article. In response, Tucker Ellis, in relevant part, produced the work product e-mails authored by the former attorney. The e-mails eventually ended up on the Internet and reached over 50 asbestos plaintiffs’ attorneys, resulting in the attorney’s termination from his new firm. After Tucker Ellis ignored the attorney’s “claw-back” letter, he filed suit against the firm for negligence, among other causes of action. The trial court granted the former attorney’s motion for summary adjudication on the issue of duty, reasoning that the firm owed the attorney a legal duty to prevent the disclosure of the work product. Tucker Ellis filed a petition for a writ of mandate with the Court of Appeal challenging the trial court’s decision on the duty issue.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Awarding Insurer Summary Judgment Before Discovery Completed Reversed
August 29, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Florida Court of Appeal reversed the trial court's awarding of summary judgment to the insurer because discovery was not completed. Sacramento v. Citizens Prop. Ins. Corp., 2022 Fla. App. LEXIS 4292 (Fla. Ct. App. June 22, 2022).
The insured filed a claim under the all-risk policy for water damage caused by Hurricane Irma. Citizens denied the claim based upon a policy exclusion. The insured filed suit on March 8, 2019.
On April 24, 2020, Citizens moved for summary judgment. A hearing was set for August 10, 2020. Citizens filed a notice for a deposition of a Mitigation Company representative scheduled to occur on December 1, 2020. On August 14, 2020, the insured filed an opposition to the summary judgment motion arguing that it would be premature to grant the motion because there were still pending depositions. The insured specifically requested that the trial court not enter summary judgment until the mitigation company's representative was deposed because he was a key witness who would be testifying regarding the cause of loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Tall Mass Timber Buildings Now Possible Under 2021 IBC Code Changes
February 03, 2020 —
Kenneth Bland - Construction ExecutiveThe International Code Council (ICC) has approved 17 changes to the 2021 editions of the International Building Code (IBC) and International Fire Code, allowing for mass timber buildings up to 18 stories. With the addition of three new mass timber construction types (Type IV-A, IV-B, and IV-C), this is the first time in the history of the modern building code that significantly new construction types have been added to the code.
Building Materials
The primary building material that makes tall mass timber (TMT) buildings possible is cross-laminated timber (CLT). CLT is manufactured from dimension lumber (nominal 2x lumber) laid side-by-side or mass plywood panels of a specified width. Laminations of lumber are typically laid perpendicular to each other to form panels of various thicknesses that are bonded together using heat resistant adhesives that cure in large hydraulic presses. CLT commonly consists of an odd number of laminations.
These solid wood panels can be anywhere from 6 inches to 20 inches nominal thickness and 60 feet long. Typical CLT panels will be 6 inches to 14 inches nominal thickness. The panels are fabricated off site, transported onto the construction site and assembled in a manner that is efficient and remarkably fast. CLT panels can be used as floor, wall, or roof building elements supported by glued-laminated beams and columns.
Reprinted courtesy of
Kenneth Bland, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Court of Appeals Upholds Default Judgment: Serves as Reminder to Respond to Lawsuits in a Timely Manner
October 02, 2023 —
Anna Basnaw - Ahlers Cressman & Sleight PLLCIn
Cyrus Way Partners, LLC. (“Cyrus”) v. Cadman, Inc. (“Cadman”), the primary issue on appeal was whether the trial court erred in denying Cadman’s motion to vacate the default judgment under Civil Rules 55 and 60. A default judgment is a legal ruling that can be entered in favor of the plaintiff when the defendant fails to respond to a lawsuit. If that happens, the court may resolve the lawsuit without hearing from the other side. In Washington, a party typically has 20 days to appear in a suit before being at risk for default judgment. If a default judgment is entered for the plaintiff, the defendant can move to vacate the default judgment, meaning the defendant hopes the court will set aside the default judgment as if it never happened. In this case, Cadman, the defendant, presents several ultimately unsuccessful arguments for why the default judgment in favor of Cyrus, the plaintiff, should be vacated.
Cyrus and Orca Beverage Inc. (“Orca”) are under common ownership. In 2018, Cyrus began a project to build a warehouse for Orca, which included the construction of a large concrete slab. Cadman was hired to supply the concrete. Cyrus hired Olympic Concrete Finishing Inc. (“Olympic”) to finish the concrete. On April 1, 2018, Cadman poured the concrete, and Olympic finished the slab. The next day, Cyrus noticed several problems with the slab, which experts hired by both Cyrus and Cadman opined were caused by an abnormally high air content in the concrete.
Read the court decisionRead the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC