Relying Upon Improper Exclusion to Deny Coverage Allows Bad Faith Claim to Survive Summary Judgment
December 04, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer was successful on summary judgment in establishing it correctly denied coverage for collapse, but its motion was denied regarding the insureds' bad faith claim. Jones v. State Farm Fire & Cas. Co., 2018 U.S. Dist. LEXIS 153102 (W.D. Wash. Sept. 7, 2018).
The insureds' retaining wall collapsed. They tendered to State Farm under their homeowners policy. An engineer retained by State Farm determined that the wall buckled due to "excessive lateral earth pressure from retained soils behind the wall." The parties agreed that the soil, saturated by water from frequent rain, grew too heavy for the retaining wall to bear, causing the collapse.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The New York Lien Law - Top Ten Things You Ought to Know
December 23, 2023 —
Ralph E. Arpajian - White and Williams LLPOver the course of my career, I have had the privilege of working with and representing numerous construction lenders (and borrowers/developers) in the financing of some of the largest commercial projects in the United States.
A number of these projects have been in New York, where one encounters the New York Lien Law (the “Lien Law”). Many of my clients, particularly those lenders, borrowers, and their counsel, located outside of New York, are often perplexed by my advice regarding the Lien Law and the loan structuring requirements which result. In the hope that it would be helpful (especially for non-New York counsel), I have compiled a “top ten” list outlining, in my view, the most critical (and most perplexing) aspects of structuring New York construction loans under the Lien Law.
Read the court decisionRead the full story...Reprinted courtesy of
Ralph E. Arpajian, White and Williams LLPMr. Arpajian may be contacted at
arpajianr@whiteandwilliams.com
Real Estate & Construction News Roundup (05/23/23) – Distressed Prices, Carbon Removal and Climate Change
June 05, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn this week’s roundup, we consider distressed property bonds and loans, cities that are sinking under their own skyscrapers, efforts to lower carbon emissions, the unexpected potential of dirty diapers as a building material, and so much more.
Globally, more than $190 billion of property bonds and loans are
trading at distressed prices, a result of China’s real estate woes. (
Alice Huang and
Erin Hudson, Bloomberg)
PacWest Bancorp sees a stock market boost as it announces the sale of its
real estate loans, valued at around $2.6 billion. (
Jaiveer Shekhawat and
Chibuike Oguh, Reuters)
New construction home sales
exceeded expectations for April while existing home sales dropped. (
Anna Bahney, CNN)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
The Unthinkable Has Happened. How Should Contractors Respond?
May 11, 2020 —
Bruce Orr - AEC BusinessAny construction veteran expects the economy to contract and expand. However, the global pandemic presents contractors with a challenge unlike any in recent memory.
How should they respond in an environment of such uncertainty? For some perspective, I chatted with Dr. John Killingsworth, a construction management professor at Colorado State University who has conducted extensive research on how contractors can weather economic downturns.
BRUCE ORR: John, let’s say you’re in IT or are a c-suite executive at a contracting firm. This event has occurred. What are some of the questions you should be asking right now?
JOHN KILLINGSWORTH: For starters, we have to acknowledge that the uncertainties are so tremendous that many contractors have no choice but to be reactive in the short term. They’re literally not sure whether particular job sites will be open or closed tomorrow or whether they’ll go to work next week. They’re also looking at predictions—from highly qualified statisticians, public health officials and others—that are just all over the map due to the limited nature of the data we have at hand.
Read the court decisionRead the full story...Reprinted courtesy of
Bruce Orr, AEC BusinessMr. Orr may be contacted at
bruce@pronovos.com
Shaken? Stirred? A Primer on License Bond Claims in California
July 14, 2016 —
Garret Murai – California Construction Law BlogShaken?
Stirred?
A bit hot under the tuxedo collar perhaps?
Maybe it’s time for a martini. Or two.
When your project’s a mess, your contractor isn’t returning your calls, and you don’t have a license to kill it’s only natural that you would want to go after that other license: the contractor’s license bond.
However, except for smaller claims, or situations where you discover that the contractor is or might be judgment-proof, going after a contractor’s license bond isn’t necessarily the panacea many might hope it to be. Read on to learn why.
What is a license bond?
First, a license bond is not insurance. While insurance is typically limited to property damage and personal injury, a license bond covers a contractor’s violation of the Contractors State License Law. All California contractors are required to have on file a license bond (or, alternative, such as a cash deposit) with the California Contractors State License Board (“CSLB”).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Dot I’s and Cross T’s When It Comes to Construction Licensure Requirements
February 21, 2022 —
David Adelstein - Florida Construction Legal UpdatesIt should serve as no surprise that making sure you are appropriately licensed is important. This includes complying with any state requirement that requires licensure, as well as complying with any local licensure requirement. Not doing so can result in the dispute centered on the lack of licensure, as opposed to leading facts relating to the substance of the dispute. In other words, you are dealing with a technicality that could have harsh implications. This lack of licensure issue recently played out in a dispute with a contractor and subcontractor in ABA Interior, Inc. v. The Owen Corp., 2022 WL 386103 (Fla. 4th DCA 2022), dealing with a local licensure requirement.
In this case, a subcontractor was hired by the general contractor for a commercial project in Palm Beach County. The subcontract contained the standard provision that the subcontractor would comply with all federal, state, and local laws and ordinances.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
National Infrastructure Leaders Visit Dallas' Able Pump Station to Tout Benefits of Water Infrastructure Investment
September 25, 2023 —
American Society of Civil EngineersDALLAS, TX. — An award-winning pump station in south downtown Dallas that protects residents from the Trinity River today was showcased by the
national Engineering and Public Works Roadshow as an example of how infrastructure investment can improve the resilience of a community, protect residents, and encourage economic growth.
The Able Pump Station in downtown Dallas, Texas won awards from both the American Council of Engineering Companies and the American Society of Civil Engineers since its completion in 2019 and has been credited with providing 100-year flood protection to approximately three square miles of high-profile land that was historically vulnerable to severe flooding events from the Trinity River.
The Engineering and Public Works Roadshow is a joint project of the
American Council of Engineering Companies (ACEC), the
American Public Works Association (APWA), and the
American Society of Civil Engineers (ASCE).
The properties adjacent to the previous Able sump complex had experienced frequent flooding. The sump complex included nine separate and interconnected ponds that store stormwater, as well as two existing pump stations, constructed in the 1930s and 1950s, with a combined capacity of 220,000 gallons per minute. To help prevent the loss of life as a result of flooding, the City of Dallas hired HDR to design the new Able Pump Station, which increases the pumping capacity nearly fourfold, to 875,000 gallons per minute. It also lowers the 100-year flood elevation from 399.0 to a design elevation of 392.5 feet.
As the federal government continues to implement this monumental legislation, the second year of the Bipartisan Infrastructure Law will not be fully realized without an expanded and robust workforce. It is imperative that students nationwide are educated on the rewarding careers of civil engineering and public works so that these professions have the necessary staffing to complete transformative projects.
Read the court decisionRead the full story...Reprinted courtesy of