President Trump Nullifies “Volks Rule” Regarding Occupational Safety and Health Administration (OSHA) Recordkeeping Requirements
April 13, 2017 —
Louis “Dutch” Schotemeyer – Newmeyer & Dillion LLPOSHA requires employers to maintain safety records for a period of five years. The Occupational Safety and Health Act contains a six month statute of limitations for OSHA to issue citations to employers for violations. In an effort to close the gap between the five years employers are required to keep records and the six month citation window, the Obama Administration implemented the “Volks Rule,” making recordkeeping requirements a “continuing obligation” for employers and effectively extending the statute of limitations for violations of recordkeeping requirements from six months to five years.
On March 22, 2017, the Senate approved a House Joint Resolution (H.J. Res. 83) nullifying the “Volks Rule” and limiting the statute of limitations to six months for recordkeeping violations. President Trump signed the resolution nullifying the “Volks Rule” on April 3, 2017. The nullification appears to be in line with President Trump’s stated goal of generally eliminating governmental regulations.
What Does This Mean for California Employers?
California manages its own OSHA program, which generally follows the federal program, but is not always in lock-step with Federal OSHA. Cal/OSHA, under its current rules, may only cite employers for recordkeeping violations that occurred during the six months preceding an inspection or review of those records. To date, there has been no indication that California’s Division of Occupational Safety and Health (DOSH) has plans to adopt the “Volks Rule.” Barring a change, California employers will continue to operate under the status quo and be required to maintain safety records for five years, but will only be exposed to citations for recordkeeping violations occurring within the last six months.
Current Cal/OSHA Recordkeeping Requirements
Cal/OSHA form 300 (also known as the “OSHA Log 300”) is used to record information about every work-related death and most work-related injuries that cannot be treated with onsite first aid (specific requirements can be found in the California Code of Regulations, Title 8, Sections 14300 through 14300.48). Currently, California Code of Regulations, Title 8, Section 14300.33 requires employers to retain OSHA Log 300 for a period of five years following the end of the calendar year during which the record was created, despite the fact that Cal/OSHA can only cite employers for failing to maintain such records for up to six months preceding an inspection.
Looking to the Future
Cal/OSHA is working on regulations that would require electronic submission of OSHA Log 300 records in California. This would bring Cal/OSHA more in line with Federal OSHA, which already requires electronic submission.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Louis "Dutch" Schotemeyer, Newmeyer & Dillion LLPMr. Schotemeyer may be contacted at
dutch.schotemeyer@ndlf.com
Effective Strategies for Reinforcing Safety Into Evolving Design Standards
July 02, 2024 —
Ethan Harris - Construction ExecutiveFrom design/build condos to built-to-suit warehouses, one factor remains the highest priority regardless of the project type—the approach to upholding the highest level of safety. Safety exists as a core value across all areas of the construction industry, but the increased risk of serious injuries or fatalities persists. Ranked fourth on the United States Bureau of Labor Statistics’ list of occupations with the most fatality rates, construction workers put their lives in danger each time they step onto the jobsite.
Considering this risk, it’s important for every team member—from subcontractors to superintendents—to take responsibility for safety compliance, empowering their workforce to take ownership of their own actions and hold others accountable for theirs. To help enhance safety efforts from start to completion, safety leaders are focusing on ways to implement safety standards within each component of a building’s design. Although this approach requires more comprehensive planning and strategizing on the front end, it is intended to reduce and mitigate hazards before they become larger issues. Keeping this idea in mind, here are a few actionable methods for managing projects designed around safety compliance.
ASSESS FIRST
No two jobsites are the same. From crowded pedestrian walkways to dangerous existing infrastructure, each project requires specific layouts, materials and processes to be fully functional both during and after construction. Given the unique nature of each site, a detailed risk assessment must be conducted before any other design and/or building activities begin. During this initial assessment, careful consideration should be placed on the overall flow as it relates to the people, processes and equipment located on or near the construction site.
Reprinted courtesy of
Ethan Harris, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Surety Bond Now a Valid Performance Guarantee for NC Developers (guest post)
June 09, 2016 —
Melissa Dewey Brumback – Construction Law in North CarolinaWelcome summer days! Today we have a guest post by Todd Bryant, president and founder of
Bryant Surety Bonds. He is a surety bonds expert with years of experience in helping contractors get bonded and start their business. While design professionals generally don’t have to deal with performance bonds directly, they are often at the front lines of advising owners as to various Requests for Proposals submitted by hopeful contractors. In that spirit, be sure to read how the new law changes security requirements. Take it away, Todd!
Last year wrapped up with some good news for North Carolina subdivision developers:
House Bill 721 confirmed that construction bonds are, in fact, a viable form of performance guarantee. Previous legislation was ambiguous on this point, but the new bill– which took effect last October– sought to clear up the confusion. Although the new rules have been in effect for eight months, there’s been scant coverage of the changes, and what they mean for developers.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
The Shifting Sands of Alternative Dispute Resolution
February 03, 2020 —
Tim Scully - Porter Law GroupIn California there are few tools which work to protect the employer, and California employers may have just lost another one. On October 10, 2019, Governor Gavin Newson signed into law AB 51, which bans the use of mandatory arbitration agreements in employment contracts.
More specifically, AB 51 adds Section 432.6 to the California Labor Code, making it unlawful to require a prospective employee, or current employee, to waive any right, forum, or procedure for a violation of any provision of the California Fair Employment and Housing Act (“FEHA”)(Part 2.8 (commencing with Section 12900) of Division 3 of Title 2 of the Government Code) or the California Labor Code, starting January 1, 2020. Additionally, an employer is also prohibited from threatening, retaliating or discriminating against, or terminating any applicant or employee who may choose not to sign a voluntary arbitration agreement.
Previously, an employer was able to require employees and prospective employees to agree to arbitration to resolve almost any and all disputes between the employee and the employer as a term of their employment. These terms were often the bulk of employers’ written contracts. Employers could have employees waive the right to a jury trial, the right to court costs, and other expenses, provided that the employer paid for the expenses of the alternative dispute resolution. The injured employees right to recover attorney’s fees was always a non-waivable right under the Labor Code. There were only a few actions which could not be arbitrated, the most prominent exception being the right to seek recovery under the Private Attorney’s General Action (PAGA).
Read the court decisionRead the full story...Reprinted courtesy of
Tim Scully, Porter Law GroupMr. Scully may be contacted at
tscully@porterlaw.com
Balancing Risk and Reward: The Complexities of Stadium Construction Projects
April 15, 2024 —
Gregory A. Eichorn - Peckar & Abramson, P.C.From grand designs to opening day, stadium construction projects present a captivating blend of high-profile opportunities and significant challenges and risks. Navigating this complex landscape is not easy, but when managed properly, the potential rewards, both in terms of reputation and finances, can make it a gamble worth taking. While each stadium project is different, some of the more common risks include:
- Securing adequate labor, materials and equipment based on the size of the project;
- Logistical concerns regarding the concurrent performance of multiple trade scopes on a single site;
- Protection of work in place from weather due to the large footprint of the stadium project;
- Cash flow issues caused by protracted change order processing, conflicting and/or onerous payment requirements from project financing entities, and reimbursement of considerable monthly general condition costs; and
- Meeting the schedule requirements for the project.
Read the court decisionRead the full story...Reprinted courtesy of
Gregory A. Eichorn, Peckar & Abramson, P.C.Mr. Eichorn may be contacted at
geichorn@pecklaw.com
Feds to Repair Damage From Halted Border Wall Work in Texas, California
May 31, 2021 —
Mary B. Powers - Engineering News-RecordWith hurricane season fast approaching, the U.S. Dept. of Homeland Security has begun repair of large breaches in a 13-mile section of Rio Grande flood barriers in Texas caused by Trump administration border wall contractors building on them—after local officials feared "extensive problems" with their integrity and threatened to bring in their own crews.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Subcontractors on Washington Public Projects can now get their Retainage Money Sooner
July 26, 2017 —
Brett M. Hill - Ahlers & Cressman PLLCSubcontractors on public projects in Washington State will no longer be required to wait until final acceptance of the project to get their retainage money. A new statute, which goes into effect on July 23, 2017 and applies only to Washington public projects, will allow subcontractors to get their retainage sooner.
Under prior law, a subcontractor could only get its retainage prior to final acceptance if the general contractor provided a retainage bond to the public owner to secure a release of the general contractor’s retainage and the subcontractor then provided a similar retainage bond to the general contractor in the amount of its own retainage. If the general contractor decided to not provide a retainage bond to the owner, the subcontractor would be forced to wait until final acceptance of the project before it could get paid its retainage.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers & Cressman PLLCMr. Hill may be contacted at
bhill@ac-lawyers.com
New Mexico Holds One-Sided Dispute Resolution Provisions Are Unenforceable
November 05, 2024 —
Bill Wilson - Construction Law ZoneDispute resolution provisions that grant one party the unilateral right to choose either litigation or arbitration to resolve disputes are common in the construction industry. The main difference between the two forums is that courts are more likely to strictly enforce contract terms as written as well as the applicable law, while arbitrators make decisions on more equitable considerations, untethered to the contract terms and—to some degree—the law. The party with the sole discretion to select the dispute resolution procedure can select the process most beneficial to its interests based on the nature of the dispute, regardless of who brings the claims. In Atlas Electrical Construction, Inc. v. Flintco, LLC, 550 P.3d 881 (N.M. Ct. App. 2024), the Court of Appeals of New Mexico recently held that an arbitration provision in a subcontract, under which the contractor retained the exclusive right to choose whether disputes arising under the subcontract were litigated in court or arbitrated was unreasonably one-sided, substantively unconscionable, and unenforceable.
The Atlas Electrical case involved two sophisticated entities with equal bargaining strength to negotiate the terms of a subcontract. The parties agreed to a subcontract provision which provided in the relevant part:
In the event [contractor] and [subcontractor] cannot resolve the dispute through direct discussions or mediation … then the dispute shall, at the sole discretion of [contractor], be decided either by submission to (a) arbitration … or (b) litigation …
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at