Risky Business: Contractual Protections in the 'New Normal'
January 04, 2023 —
Daniel Lund III - Construction ExecutiveThe point of contracts is to create certainty to avoid litigated or arbitrated disputes. Still, the various parties in the construction process may have different risk tolerances. For example, general contractors are often characterized as “risk-tolerant.” That risk, though, is usually calculated by the contractor internally, outside the terms of the written contract, based on an assumption that the contractor can get the work done more cheaply and more quickly than the owner anticipated. Project owners typically want and expect close-to-absolute certitude—absolutely as to cost—in their construction contracts. The standard fixed-price or lump-sum construction contract is geared toward protecting that interest.
Post-COVID-19, however, the discussion in the industry suggests that all bets are off when pricing and agreeing to construction work. Labor and materials shortages have sent owners and their design consultants backpedaling when general contractors pursuing a fixed-price contract seek contractual concessions that “un-fix” the price.
Reprinted courtesy of
Daniel Lund III , Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
BWB&O ranks as a 2025 Best Law Firm by Best Lawyers®
December 10, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is honored to announce the firm has been recognized for its fifth consecutive year in the 2025 edition of Best Law Firms® and is ranked by Best Lawyers® regionally in three practice areas. To read the publication, please click here.
Metropolitan Tier 1
Las Vegas: Litigation – Construction
Orange County: Litigation – Construction
Metropolitan Tier 2
Orange County: Family Law
San Diego: Litigation – Real Estate
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Colorado Senate Committee Approves Construction Defect Bill
March 19, 2015 —
Jesse Howard Witt – Acerbic WittLate last night, the Colorado Senate Business, Labor, and Technology Committee voted to refer
SB 15-177 to the committee of the whole. The vote followed nearly seven hours of testimony from those in favor of construction defect legislation and those opposed.
As I have
previously discussed, the bill sponsors have argued that their measure will encourage the construction of more affordable housing by giving builders de facto immunity for claims of defective workmanship and property damage in common interest communities. The bill achieves this by establishing difficult voting and disclosure requirements for homeowner associations and requiring costly, private arbitration of any disputes that can overcome the procedural hurdles. During the recent hearing, proponents echoed these statements and testified that insulating homebuilders from claims would lower home prices and rents by increasing the supply of cheaply-built condominiums.
Opponents questioned whether the bill contained any provisions that would actually help the affordable housing market. They also argued that it was improper for the legislature to shift the cost of fixing construction defects onto those homeowners who can least afford to pay for necessary repairs.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, The Witt Law FirmMr. Witt welcomes comments at www.acerbicwitt.com
Second Circuit Denies Petitions for Review of EPA’s Final Regulations to Establish Requirements for Cooling Water Intake Structures
August 20, 2018 —
Anthony B. Cavender - Gravel2GavelOn July 23, 2018, the U.S. Court of Appeals for the Second Circuit decided the case of Cooling Water Intake Structure Coalition v. EPA. Environmental conservation groups and industry associations petitioned for review of a final rule promulgated by the U.S. Environmental Protection Agency (EPA) pursuant to section 316(b) of the Clean Water Act (CWA), establishing requirements for cooling water intake structures at existing facilities. Denying the petitions for review, the Court of Appeals summarized:
“Because we conclude, among other things, that both the Rule and the biological opinion are based on reasonable interpretations of the applicable statutes and sufficiently supported by the factual record, and because the EPA 3 gave adequate notice of its rulemaking, we DENY the petitions for review.”
This is a significant CWA and Endangered Species Act (ESA) decision involving the operation of major industrial facilities requiring the daily use of large amounts of water taken from adjacent bodies of water.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
Unpredictable Opinion Regarding Construction Lien (Reinstatement??)
January 17, 2023 —
David Adelstein - Florida Construction Legal UpdatesHere comes the discussion of an appeal I was intimately involved in dealing with a construction lien. See Suntech Plumbing and Mechanical Corp. v. Bella Isla, LLC, 2022 WL 14672765 (Fla. 3d DCA 2022). Unfortunately, it was a losing result on my end but not a losing result to the issue at-hand. You should ask what in the world does this mean. I will tell you.
Here is the fact pattern. A subcontractor files a construction lien foreclosure lawsuit against an owner for unpaid contract balance. In the same lawsuit, the subcontractor sues the general contractor for breach of contract and unjust enrichment associated with an approximate three-year delay on a construction project. The project was scheduled to be completed in 2019. It was not. The project was pushed into COVID and into 2022. (The subcontractor did not sue the general contractor for amounts subject to the lien foreclosure claim.) The general contractor, assuming the defense of the owner, moved to stay the lawsuit pending the outcome of arbitration based on an arbitration provision in the subcontract. The subcontractor did not dispute the arbitration provision, but argued that arbitration provision should not extend to the owner that was (a) not bound by the subcontract, (b) would not be a party to the arbitration, and (c) the amounts pled against the general contractor did not include the amounts subject of the lien foreclosure lawsuit. At a minimum, the lawsuit should be stayed, not dismissed. Nevertheless, the trial court dismissed the entire lawsuit in an order that states that it is a final order with language that the lien may be “reinstated” after the outcome of the arbitration (that the owner is not a party to).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Who is Responsible for Construction Defect Repairs?
August 24, 2017 —
Laura Parsons-CDJ STAFFAn appellate court has ruled that the sponsor and not the condo board is responsible for repairing construction defects at 50 Madison Avenue, a multi-story apartment building in New York City across from Madison Square Park, Habitat reported. Plaintiff’s Simon and Ludmilla Lorne have brought upon three lawsuits in a legal battle lasting a decade.
The first came in 2007, two years after the Lorne’s purchased their $3 million seventh-floor apartment. At that time, the sponsor offered to repair the concrete slab under the hardwood floors that had not been properly leveled. However, the Lorne’s and the condo board disagreed about who and how the repairs would be accomplished. The second lawsuit wherein the court ruled that repairing the construction defects was the responsibility of the sponsor occurred in 2009. However, the Lorne’s sued the board yet again in 2015, citing failure to maintain and repair the building. Since the 2015 suit was based on the same allegations as the 2007 suit, it was dismissed by the judge.
Read the court decisionRead the full story...Reprinted courtesy of
Wisconsin Court Applies the Economic Loss Doctrine to Bar Negligence Claims for Purely Economic Losses
August 17, 2020 —
Rahul Gogineni - The Subrogation StrategistIn Mech. Inc. v. Venture Elec. Contrs., Inc., No. 2018AP2380, 2020 Wisc. App. LEXIS 170, the Court of Appeals of Wisconsin, District Two, considered whether a party may bring a negligence claim for purely economic damages. In upholding the lower court, the appellate court found that a party is barred by the Economic Loss Doctrine from bringing a negligence claim for purely economic damages.
Both parties involved in this action were subcontractors on a building project at the Great Lakes Research Facility for the University of Wisconsin-Milwaukee. As a result of Venture Electrical Contractors, Inc. (Venture) not paying for requested work, Mechanical, Inc. (Mechanical) sued Venture for $11,961.31. Venture, in turn, countersued in negligence for $1.1 million for costs incurred due to delays and untimely performance. Mechanical sought dismissal of the negligence claim based upon the Economic Loss Doctrine. Finding that the Economic Loss Doctrine applies to purely economic losses, the trial court dismissed Venture’s negligence claim. Venture appealed to the Court of Appeals of Wisconsin.
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at