Bob Henry - Snell & Wilmer Real Estate Litigation BlogIn September 2018, in Baumgartner v. Timmins, 245 Ariz. 334, 429 P.3d 567, the Arizona Court of Appeals provided further clarification on what constitutes an “encumbrance” on a property for purposes of Arizona’s statutory scheme prohibiting the recording of “false documents.” The statute, A.R.S. § 33-420, prohibits the recording of documents that a person knows to be forged, are groundless, or that contain material misstatements (or false claims). A person who claims an “interest in, or a lien or encumbrance against” real property who records such documents can be held liable for $5,000 or treble the actual damages caused by the recording (whichever is greater), A.R.S. § 33-420(A), and perhaps even be found guilty of a class 1 misdemeanor, A.R.S. § 33-420(E).
At issue in Baumgartner were neighbors fighting about CC&Rs—a typical neighborhood fight. In 2015, some of the neighbors filed suit against the Timminses for violating the CC&Rs. The Timminses did not contest the lawsuit, resulting in a default judgment. In what the Court of Appeals characterized as a lawsuit filed by the Timminses “in apparent response to the [first] lawsuit and resulting default judgment,” the Timminses created, signed, and recorded affidavits contending that the Plaintiffs in the original lawsuit were themselves “in violation of several provisions of the CC&Rs.” The Plaintiffs then filed suit again against the Timminses, this time contending that the Timminses had violated A.R.S. § 33-420 by recording the affidavits because the affidavits, the Plaintiffs contended, created encumbrances on their properties. The Apache County Superior Court agreed, and issued a final judgment nullifying the recorded documents and awarding the Timminses damages, along with their attorneys’ fees and costs.
Read the court decisionRead the full story...Reprinted courtesy of
Bob Henry, Snell & WilmerMr. Henry may be contacted at
bhenry@swlaw.com
Insurance Policies and Indemnity Provisions Are Not the Same
October 19, 2020 —
Garret Murai - California Construction Law BlogJust because you own a pair of Air Jordans doesn’t make you Michael Jordan. In the next case, Carter v. Pulte Home Corporation, Case No. A154757 (July 23, 2020), the 1st District Court of Appeal denied an insurance carrier’s equitable subrogation claim explaining that an insurer’s obligations under its insurance policy are not the same as an idemnitee’s obligations under an indemnity provision. Or, as aptly put by the Court of Appeal, while a “subrogated insurer is said to ‘stand in the shoes’ of its insured, because it has no greater rights than the insured. Here . . . [the insurer] is seeking to stand in a different, more advantageous set of shoes.”
Carter v. Pulte Home Corporation
Pulte Home Corporation was sued for construction defects by 38 homeowners in two housing developments. Various subcontractors had worked on the projects, but under their subcontracts, each subcontractor agreed to indemnify Pulte from and against “all liability, claims, judgments, suits, or demands for damages to persons or property arising out of, resulting from, or relating to Contractor’s performance of work under the Agreement (‘Claims’) unless such Claims have been specifically determined by the trier of fact to be the sole negligence of Pulte . . . ”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Matthew Graham Named to Best Lawyers in America
September 10, 2018 —
Garret Murai - California Construction Law BlogWendel Rosen’s very own
Matt Graham has been selected for inclusion in The Best Lawyers in America© 2019 in the area of Construction Law. First published in 1983, Best Lawyers is the oldest and most respected peer-review publication in the legal profession.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Energy Company Covered for Business Interruption Losses Caused by Fire and Resulting in Town-Ordered Shutdown
February 15, 2021 —
David G. Jordan - Saxe Doernberger & Vita, P.C.In the case of NextSun Energy Littleton, LLC v. Acadia Ins. Co., the United States District Court of Massachusetts held that once direct physical damage from a covered peril causes a covered business interruption loss, any increase in the duration of such business interruption, due to the enforcement of an ordinance or law, extends the coverage period provided for lost income. The Court further held that a policy exclusion for business interruption due to the enforcement of any ordinance or law not in force at the time of the loss only applies when the ordinance or law itself, not the enforcement action that it authorizes, was not in force at the time of the loss.
The case involved a solar panel company, NextSun Energy Littleton (NextSun), that operated solar panel arrays providing electricity to the town of Littleton, Massachusetts. Due to a fire, 88 of the solar panels were damaged, and the Town immediately issued a “red-tag” order halting all energy-generating activity pending a safety inspection. The plaintiff purchased insurance for its panels along with “Energy Generating Income” (EGI) coverage, from the defendant, Acadia Ins. Co. (Acadia). The EGI policy covered “direct physical loss or damage” to “renewable energy generating equipment” and also covered the actual loss of surplus power income incurred during the interruption period. However, it excluded interruption of energy-generating income “caused by the enforcement of any ordinance, law, or decree … not in force at the time of loss.”
Read the court decisionRead the full story...Reprinted courtesy of
David G. Jordan, Saxe Doernberger & VitaMr. Jordan may be contacted at
DJordan@sdvlaw.com
Should a Subcontractor provide bonds to a GC who is not himself bonded? (Bonding Agent Perspective)
May 03, 2017 —
Christopher G. Hill - Construction Law MusingsGuest Post Friday is back, and for this week, Construction Law Musings welcomes Steve Moore. Steve has been the Construction & Surety Manager for Towne Insurance Agency-Invincia, in Chesterfield, VA since 2010. Steve’s experience in the Virginia surety bonding marketplace started in 1985 with USF&G. His underwriting travels took him from USF&G to starting National Grange Mutual’s mid-Atlantic bond department over Virginia, Maryland, Delaware, North & South Carolina, to being Reliance Surety’s “Firemark” bond manager in Virginia. Reliance was purchased by Travelers, where Steve continued to grow the surety book of business and build expertise and relationships. Experience with Travelers and Zurich had Steve handling surety bonds for some of Virginia’s largest and best-of-class contractors. Recently, he was contracted by the Commonwealth’s Attorney’s office to serve as a contract surety expert witness on behalf of the state. He is a 1985 graduate of Virginia Tech with double-major B.S. degrees in Finance and Marketing.
Today, Steve has business and relationships with Travelers, The Hartford, Westfield, CNA, CBIC, Selective, Liberty Mutual, Ohio Casualty, Cincinnati, and many other companies. Steve’s strong foundation of insurance knowledge and in bonding principles and practices allow him to serve as a great resource for his clients.
An old Aesop fable comes to mind when I am asked whether a Sub should bond to an unbonded GC:
"A woodsman entered the forest and asked the trees to give him a handle made of the best wood. After giving the woodsman a stave of hickory, the forest watched the woodsman fashion an axe onto the handle. In a flash, the woodsman began to chop down the various oaks and maples in the forest. The oak then said to a pine, “It serves us right, since we gave our adversary the very thing that contributes to our doom…"
When a subcontractor client of mine asks about bonding to an un-bonded general contractor, a number of questions immediately come to mind. Why isn’t the GC bonded? What is the existing relationship between the GC and Sub? How well is the job financed? While wanting to help my subcontractor procure work, and surely enjoying the commissions from writing a bond, I also want to help my sub client manage unforeseen risk. What are the risks to a sub, when posting a bond to an unbonded GC?
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
August 06, 2019 —
William L. Porter - Porter Law GroupThe “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Non-Responsibility will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
CSLB Reminds California Public Works Contractors to Renew Their Public Works Registration
October 02, 2015 —
Garret Murai – California Construction Law BlogA friendly reminder from the Contractors State License Board . . .
CSLB Urges Public Works Contractors to Renew Dept. of Industrial Relations Registration before October 1 to Avoid Hefty Penalty
SACRAMENTO — A mandatory renewal deadline is approaching for licensees who work on public works projects. Contractors whose registration with the California Department of Industrial Relations (DIR) expired June 30, 2015, and have ongoing public works projects or plan to bid on new ones, must pay the $300 renewal fee
before October 1, 2015, or face an additional $2,000 late penalty after that date.
As a result of
Senate Bill (SB) 854, all contractors have been required since April 1, 2015, to register with DIR to be awarded a public works contract, even if the project did not go out to bid.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
North Carolina Appeals Court Threatens Long-Term Express Warranties
April 09, 2014 —
Beverley BevenFlorez-CDJ STAFFJonathan Massell of the firm Nexsen Pruet explained how a “recent holding by the North Carolina Court of Appeals is threatening to render many long-term express warranties ineffective,” in the online publication Lexology.
In Christie v. Hartley Construction, Inc., “the court held that the six-year North Carolina statute of repose for improvements to real property trumps the bargained-for duration terms of an express warranty.” In the Christie case, this meant that even though the homeowners had a twenty year warranty, because of the statute of repose, the warranty effectively expired after six years.
Massell stated to “be mindful of jurisdiction.” If the express warranty is in a state other than North Carolina, it’s possible that the claim could be filed in that state instead of North Carolina. For instance, according to Massell, South Carolina’s “statue of repose does not expire until eight years after the date of substantial completion for an improvement to real property.” Furthermore, “long-term warranties are not trumped by the South Carolina statute of repose.”