Colorado Court of Appeals Confirms Senior Living Communities as “Residential Properties” for Purposes of the Homeowner Protection Act
November 06, 2023 —
Hal Baker - Colorado Construction Litigation BlogThe Third Division of the Colorado Court of Appeals recently interpreted the Homeowner Protection Act of 2007 (the “HPA”) in Heights Healthcare v. BCER, 2023 COA 44, decided on May 25, 2023. The Court held that a senior living community that is located on a parcel zoned “commercial” or “mixed use” constitutes “residential property” that is protected by the HPA, regardless of the zoning designation.
The claims in Heights Healthcare arose from a contract between BCER and Heights Healthcare for BCER to provide mechanical and electrical services relating to the installation of Packaged Terminal Air Conditioner units at the senior living community. The contract between the parties included a limitation of liability clause, limiting BCER’s liability to a total of $22,500 for the total cost of services rendered. After the installation, Heights Healthcare discovered that the air conditioner units were malfunctioning, causing too few of the eighty-four units to run and tripping the breaker—shutting down the entire system—when the outdoor temperature dropped too low. Following the discovery of the malfunction, Heights Healthcare filed suit against BCER for breach of contract under the Construction Defect Action Reform Act (“CDARA”).
Read the court decisionRead the full story...Reprinted courtesy of
Hal Baker, Higgins, Hopkins, McLain & Roswell, LLCMr. Baker may be contacted at
baker@hhmrlaw.com
Construction Contracts and The Uniform Commercial Code: When Does it Apply and Understanding the Pre-Dominant Factor Test
November 01, 2022 —
Keith Sparks - Ahlers Cressman & Sleight PLLCThe Uniform Commercial Code (“UCC”) replaces the common law in many commercial transactions, providing provisions and a framework governing the conduct of business. The UCC attempts to develop uniformity among state laws on commercial matters as many of these contracts involve parties from different states. The UCC has been adopted in almost all states, including Washington, and substantially mirror each other throughout the country.
The question that is most commonly presented, in the Construction law context, is when does the UCC apply and control?
Read the court decisionRead the full story...Reprinted courtesy of
Keith Sparks, Ahlers Cressman & Sleight PLLCMr. Sparks may be contacted at
keith.sparks@acslawyers.com
How Construction Contracts are Made. Hint: It’s a Bit Like Making Sausage
October 07, 2016 —
Garret Murai – California Construction Law BlogConstruction can be a messy affair. In a sense, that’s to be expected when you’re building a complex structure, involving the coordination of several parties and numerous persons, in the natural environment and in the elements, subject to an increasing array of laws, regulations, ordinances and codes, and often at the cost of hundreds if not billions of dollars.
So too can construction contracts.
There’s the plans, the specifications, the general conditions, the special conditions, the addenda, the prime contract, the subcontracts, the purchase orders, and the change orders, to name just a few of the documents which bind parties, which should ideally be consistent and complimentary with one another, when the reality is that the parties bound to those contracts often have very different interests.
Perhaps the analogy goes a little too far afield, but it makes the point, that it can sometimes be a bit like making sausage.
The next case,
Watson Bowman Acme Corporation v. RGW Construction, Inc., California Court of Appeals for the Fifth District, Case No. F070067 (August 9, 2016), highlights the problems which can arise from the numerous documents which make up the typical construction contract today and the lengths that juries and judges must go to interpret what those agreements mean.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Force Majeure Under the Coronavirus (COVID-19) Pandemic
March 29, 2021 —
Lindsay T. Watkins - Ahlers Cressman & Sleight PLLCAs COVID-19 disrupts work and life as we know it, the question many contractors have is what protections are available against the inevitable project impacts and delays? Generally, construction contracts require a contractor to timely perform work until project completion or potentially face damages (liquidated or actual) and possible termination. When events occur, however, that are beyond our control (such as a national pandemic), it is important to review and understand what contract provisions or avenues are available for potential relief.
- Review Your Contract For A Force Majeure Provision.
A “force majeure” contract provision is commonly included in construction contracts, service agreements, purchase orders, etc. It typically covers events or conditions that can be neither anticipated nor controlled. These provisions, however, will vary greatly from contract to contract and may not include the language “force majeure” but rather may be included in general delay or impact clauses. For example, some common provisions include:
- Washington State Department of Transportation Clause (2018 Standard Specifications for Road, Bridge and Municipal Construction): The Contractor shall rebuild, repair, restore, and make good all damages to any portion of the permanent or temporary Work occurring before the Physical Completion Date and shall bear all the expense to do so, except damage to the permanent Work caused by: (a) acts of God, such as earthquake, floods, or other cataclysmic phenomenon of nature, or (b) acts of the public enemy or of governmental authorities; or (c) slides in cases where Section 2-03.3(11) is applicable; Provided, however, that these exceptions shall not apply should damages result from the Contractor’s failure to take reasonable precautions or to exercise sound engineering and construction practices in conducting the Work.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay T. Watkins, Ahlers Cressman & Sleight PLLCMs. Watkins may be contacted at
Lindsay.Watkins@acslawyers.com
Court Holds That Public Entity Can Unilaterally Replace Subcontractor Under California’s Subletting and Subcontracting Fair Practices Act
July 22, 2019 —
Garret Murai - California Construction Law BlogThe Subletting and Subcontracting Fair Practices Act (Public Contract Code section 4100 et seq.), also known as the Listing Law, is intended to prevent direct contractors on public works projects from “bid shopping” and “bid peddling.”
Bid Shopping: Bid shopping is when a direct contractor discloses a subcontractor’s bid to other subcontractors in an attempt to obtain a lower bid than the one in which it based its bid to the owner.
Bid Peddling: Bid peddling is the other side of the equation. It is when a subcontractor whose bid was not selected, lowers its bid in an attempt to induce the direct contractor to substitute it for another subcontractor after the prime contractor’s bid has been awarded.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Colorado Court of Appeals’ Ruling Highlights Dangers of Excessive Public Works Claims
August 26, 2024 —
David M. McLain – Colorado Construction LitigationIn the case of Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners (2024 COA 78), the Colorado Court of Appeals reviewed a complex contract dispute related to the design and construction of a transit rail line. The project, commissioned by the Regional Transportation District (“RTD”), involved a collaboration between Regional Rail Partners and Ralph L. Wadsworth Construction Company (“Wadsworth”) to build the North Metro Rail Line between Denver Union Station and Thornton.
Key Facts:
- Contracts and Payments: Regional Rail Partners contracted with Wadsworth to perform specific construction tasks with a total contract value of $60,210,783. By the time of the trial, Regional Rail had paid almost $58 million of this amount.
- Disputes and Delays: The project faced numerous delays and disputes, leading to Wadsworth claiming significant financial damages attributed to these disruptions. In April 2018, Wadsworth’s expert estimated that Regional Rail owed them $12,408,496.60.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Citigroup Reaches $1.13 Billion Pact Over Mortgage Bonds
April 09, 2014 —
Dakin Campbell – BloombergCitigroup Inc. (C) agreed to pay $1.13 billion to settle claims from mortgage-bond investors as it seeks to curb liabilities tied to the financial crisis. It took a $100 million first-quarter charge.
The 68 securitization trusts covered by the settlement issued a combined $59.4 billion in mortgage-backed securities from 2005 to 2008, the New York-based bank said yesterday in a statement. The agreement covers 18 investors represented by Gibbs & Bruns LLP and trustees have until June 30 to accept the deal, the law firm said in a separate statement. The accord must be approved by the Federal Housing Finance Agency.
Citigroup, the third-biggest U.S. bank, is resolving a portion of liabilities tied to mortgages it packaged and sold to investors in the run-up to the 2008 crisis. JPMorgan Chase & Co. (JPM) and Bank of America Corp. (BAC), the two largest U.S. lenders, previously agreed to multibillion-dollar settlements with Gibbs & Bruns clients.
Read the court decisionRead the full story...Reprinted courtesy of
Dakin Campbell, BloombergMr. Campbell may be contacted at
dcampbell27@bloomberg.net
Reinsurer's Obligation to Provide Coverage Determined Under English Law
July 24, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe Second Circuit turned to English law to determine the obligations of the reinsurer. Ins. Co. of the State of Pa. v. Equitas Ins. Ltd., 2023 U.S. App. LEXIS 12461 (2nd Cir. May 22, 2023).
Insurance Company of the State of Pennsylvania (ICSOP) provided an umbrella policy to a predecessor of Dole Food Company for a policy period from October 1968 to October er 1971. Equitas then reinsured part of ICSOP's exposure for the same three-year period. English law governed the reinsurance policy.
In 2009, homeowners in Carson, California sued Dole for polluting their soil and groundwater. Dole and ICSOP settled these claims and allocated $20 million of the settlement liability to the ICSOP-Dole policy, even thought the homeowners' property damage and personal injuries continued to accrue after the ICSOP-Dole policy period ended. In doing so, the settlement followed The California law for allocation, known as the "all sums rule." This rule treated any insurer whose policy was in effect during any portion of the time during which the continuing harm occurred as jointly and severally liability for all property damages or personal injuries caused by a pollutant.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at