Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Must Defend Faulty Workmanship Claims
May 02, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that the insurer improperly denied a defense for construction defect claims made against the insured. Amerisure Mut. Ins. Co. v. McMillin Tex. Homes, 2022 U.S. Dist. LEIS 40363 (W.D. Texas March 8, 2022).
McMillin was a developer, general contractor and home seller. It constructed multiple homes in various communities in the San Antonio area. After the homes were completed, homeowners observed defects in the artificial stucco exterior finish. After claims were lodged against McMillin, the various claims were tendered to Amerisure. Amerisure filed for declaratory judgment that it had to duty to defend or indemnify and moved for summary judgment.
Amerisure first argued the homeowners' faulty workmanship claims did not allege "property damage" under the policies. It argued there were no allegations that any property damage existed, but merely that the stucco suffered from construction defects. The court disagreed. Among the allegations was the statement that due to the construction defects, the homes suffered damage "not only to the exterior stucco, but also to the underlying wire lath, paper backing, house wrap, flashing, water resistive barriers, sheathing, interior walls, interior floors and/ or other property." Consequently, the underlying claims amounted to property damage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
San Francisco International Airport Reaches New Heights in Sustainable Project Delivery
November 21, 2022 —
Aileen Cho - Engineering News-RecordTen years ago, Geoff Neumayr decided he was tired of “doing design and construction by combat.” San Francisco International Airport had completed a master plan for the complex and the front of the airport facilities doing things the traditional way.
Reprinted courtesy of
Aileen Cho, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
SB800 CONFIRMED AS EXCLUSIVE REMEDY FOR CONSTRUCTION DEFECT CLAIMS
January 24, 2018 —
Jeffrey Brower and Nathan Owens - Newmeyer & Dillion, LLPIn
McMillin Albany LLC v. Superior Court (Cal. Ct. App., Aug. 26, 2015) 2015 Daily Journal D.A.R. 9931 (“
McMillin”), the Fifth Appellate District Court of Appeal in California published a resounding win for builders, general contractors, and others entities seeking the protections of the Right to Repair Act, Civil Code sections 895, et seq. (“SB800”). The
McMillin Court firmly rejected the reasoning and outcome of both
Liberty Mutual Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98 (“
Liberty Mutual”) and
Burch v. Superior Court (2014) 223 Cal.App.4th 1411 (“
Burch”), and held that:
the Legislature intended that all claims arising out of defects in residential construction, involving new residences sold on or after January 1, 2003 (§ 938), be subject to the standards and the requirements of the Act; the homeowner bringing such a claim must give notice to the builder and engage in the prelitigation procedures in accordance with the provisions of Chapter 4 of the Act prior to filing suit in court.
(
McMillin, Opinion, p. 15.) The
McMillin Court further held that even if the claimant’s counsel intentionally pleads around SB800 by asserting only tort causes of action, SB800 still applies to all defect claims and a stay of the action to require SB800 compliance is appropriate.
Newmeyer & Dillion has strongly supported builders’ efforts to enforce the Right to Repair Act since its inception. The firm filed an amicus brief in
McMillin on behalf of Leading Builders of America (“LBA”), an association of the leading residential homebuilders in the United States. For years, LBA members developed their warranty and dispute resolution procedures according to the Right to Repair Act and performed prelitigation repairs to the satisfaction of thousands of homeowners.
Liberty Mutual and
Burch undermined the Right to Repair Act by allowing plaintiffs’ attorneys to circumvent the prelitigation procedures to the detriment of homeowners and builders, resulting in confusion and increased litigation. The
McMillin decision breathes new life into the Right to Repair Act and sets the stage for future review by the California Supreme Court.
The
McMillin Court focused on the express language of the Right to Repair Act to arrive at its conclusion that Civil Code sections 896, 897, 943 and 944 demonstrate a clear Legislative intent to occupy the field of construction defect litigation – a belief held by nearly all in the construction industry and the California Superior Courts before
Liberty Mutual. The
McMillin Court found further support for SB800’s comprehensive nature in the Legislative history, which consistently described the Act as “groundbreaking reform” and a “major change” in construction defect litigation, designed to “significantly reduce the cost of construction defect litigation and make housing more affordable.” (
McMillin, Opinion, pp. 18-19.) The
McMillin Court found it inescapable that the Right to Repair Act exclusively governs construction defect litigation involving homes sold on or after January 1, 2003.
The
McMillin, decision will have a significant impact on construction litigation moving forward in two respects. First,
McMillin, is the only appellate decision to date to address whether a builder has the right to enforce SB800 when the claimant’s counsel deliberately attempts to plead around SB800 by asserting only tort claims. Second, the decision provides trial courts with the authority and precedent to ensure compliance with the Right to Repair Act. Trial courts may also find it necessary to revisit prior rulings against builders that relied on
Liberty Mutual.
Newmeyer & Dillion will continue to advocate in support of builders and general contractors by working vigorously to gain further support for the
McMillin, decision and setting the stage for review by the California Supreme Court.
Jeffrey R. Brower is an associate at the Newport Beach office of Newmeyer & Dillion, LLP. His practice focuses on business and construction litigation. Jeffrey can be reached at jeffrey.brower@ndlf.com.
Nathan Owens is the managing partner of the Las Vegas office for Newmeyer & Dillion, LLP. He represents businesses and individuals operating in a wide array of economic sectors including real estate, construction, insurance and health care in all stages of litigation in state and federal court. Nathan can be reached at nathan.owens@ndlf.com.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit
www.ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “Based on New Information …”
August 01, 2023 —
Daniel Lund III - LexologyBased on new information … your arbitration award is thrown out!
So said the United States Eleventh Circuit Court of Appeals, affirming a district court’s vacatur of the award based upon the award having been procured by fraud.
The lower court ruled as it did notwithstanding the fact that the action seeking to have the arbitration award vacated was filed and served beyond the three months allowed by the Federal Arbitration Act, 9 U.S.C. 12.
The party attacking arbitration award alleged that during the course of the arbitration hearing, a witness whose testimony was been handled remotely by videoconference was being inappropriately aided: the witness was being instructed remotely – by texting – by the corporate representative for his company, who was entitled to sit in on all portions of the arbitration hearing.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
State-Fed Fight Heats Up Over Building Private Nuclear Disposal Sites
August 03, 2022 —
Mary B. Powers & Debra K. Rubin - Engineering News-RecordThe U.S. Nuclear Regulatory Commission and Interim Storage Partners, a joint venture that gained a federal license last year to build an interim storage facility for spent commercial nuclear fuel at a Texas site, have until Aug. 3 to answer a federal lawsuit claim by state officials that a new U.S. Supreme Court decision eliminates the federal agency’s licensing authority.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record and
Debra K. Rubin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Unbilled Costs Remain in Tutor Perini's Finances
October 23, 2018 —
Scott Van Voorhis – Engineering News-RecordTutor Perini is struggling to shake off long-running concerns over the hundreds of millions in unbilled costs that have been on the contractor’s balance sheet for years. The Sylmar, Calif.-based construction giant reported more than $1 billion in unbilled costs or receivables at the end of the second quarter, up by more than $100 million from the start of the year, according to the company’s federal filings. That was $100 million higher than at the end of 2016, when the amount was $832 million.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENRENR may be contacted at
ENR.com@bnpmedia.com
School District Client Advisory: Civility is not an Option, It is a Duty
May 13, 2014 —
Gregory J. Rolen - Haight Brown & Bonesteel LLP“I could not but wonder at the Queen’s unprecedented civility, until I realized with a flush of shame that it was my own improved behavior that motivated hers. So it is that we in life determine our own treatment.” - Catherine Gilbert Murdock
I. We Must Actively Encourage Board Civility
Over 20 years of experience representing public entities has taught me there is nothing more important than civility. On April 11, 2014, I was a featured presenter on, "How to Keep School Boards Out Of Trouble!" My initial focus was to educate the board members about open meeting laws, public records, and conflict provisions. Instead, I began by addressing board "civility." The discussion became animated. The audience was transfixed, appalled, and even amused at my examples of how uncivilized board behavior led to lawsuits, bad press, wasted resources and low morale. One attendee asked me to define civility. I meekly responded, "The Golden Rule?" "Disagreeing without being disagreeable?" My answers were inadequate. I then had a humbling epiphany. As an education law specialist, and the General Counsel of one of the largest, most diverse school districts in California, I needed to do more to foster civility among the board members I served. I had underestimated the destructive effects of incivility on my district, my colleagues, and my community.
On some level I realized that the coarsening of the discourse was taking its toll. However, I was so involved in performing my duties; I forgot to do my job. I should have taken a step back and implemented training, policies, initiatives and protocols to promote civility. I realize that it is unfortunate that we have to establish standards for adult interactions, especially for people who have promised to place service over self. As I learned, you can never fully anticipate human interactions or the complexities of the human condition. That is why I believe proactive measures to promote civility are so critical. This is not being nice for the sake of being nice. But instead, it is an absolutely vital component of effective governance. Therefore, in this essay I will discuss civility and its importance to school boards and districts. I will address the deleterious effects of board incivility. More importantly, I hope to present no-nonsense methods to cultivate civility. It is my sincere desire that others will learn from my experiences, and this time I want to do better!
Read the court decisionRead the full story...Reprinted courtesy of
Gregory J. Rolen, Haight Brown & Bonesteel LLPMr. Rolen may be contacted at
grolen@hbblaw.com