Top Five General Tips for All Construction Contracts
October 26, 2020 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings we welcome Spencer Wiegard. Spencer is a Partner with Gentry Locke Rakes & Moore, LLP. He is a member of the firm’s Construction Law and Commercial Litigation practice groups. Spencer focuses his practice in the areas of construction law and construction litigation. Spencer is a member of the Board of Governors for the Virginia State Bar Construction Law and Public Contracts Section, and a member of the Legislative Committee of the Associated General Contractors of Virginia and the Executive Committee for the Roanoke/SW Virginia District of the Associated General Contractors of Virginia.
I would like to thank Chris for inviting me to author today’s guest post. Over the past few days, I have found myself wading through the terms and conditions of a lengthy and complicated construction contract, while at the same time aggressively negotiating for Houston house leveling cost readjustments. As I slogged through the legalese, I was reminded of a presentation that I gave earlier this year to the Roanoke District of the Virginia Associated General Contractors. The district’s executive committee asked me to speak to its members concerning the broad topic of “Construction Contracts 101.” At the beginning of my presentation, I passed along my top five general tips for all construction contracts. Although some of these tips may sound like common sense, I often encounter situations where these basic rules are violated by experienced contractors, subcontractors, suppliers and design professionals. My top five general tips for all construction contracts are:
- Reduce the terms of the agreement to writing.
- The written agreement should include all important and relevant information and terms. If it was important enough to discuss prior to signing the contract, it is important enough to include in the written contract;
- At a minimum, include who, what, when, where, how, and how much;
- Both parties should sign the written agreement; and
- Don’t ignore handwritten changes to the contract, as these changes may either mean that you don’t have a deal, or they may become part of the contract when you sign it.
Read the court decision
Read the full story...
Reprinted courtesy of The Law Office of Christopher G. Hill
Mr. Hill may be contacted at chrisghill@constructionlawva.com
TLSS Partner Burks Smith and Associate Katie Keller Win Summary Judgment on Late Reported Water Seepage Case in South Florida
November 18, 2019 — Burks A. Smith, III & Kathryn Keller - Traub Lieberman
On July 9, 2019, Traub Lieberman Straus & Shrewsberry LLP Partner, Burks A. Smith, III and Associate, Kathryn A. Keller, secured Summary Judgment on behalf of a major homeowners’ insurer in a breach of contract action in the United States District Court for the Southern District of Florida. See Lehrfield v. Liberty Mutual Fire Insurance Company, 2019 WL2994270 (S.D. Fla. 2019). The underlying claim involved a water loss at the Plaintiffs’ residence allegedly resulting in $91,147.32 worth of damage to their home. The claim was reported eight (8) months after the alleged date of loss, and during the inspection, the adjuster observed rot, decay, mold, and warping wood, prompting the carrier to deny the claim based on the Seepage Endorsement. The Plaintiffs filed a breach of contract action alleging that the insurer breached the Policy by denying the claim.
Mr. Smith and Ms. Keller argued that Plaintiffs’ Policy with the insurer imposes a duty on the Plaintiffs to comply with the Duties After Loss conditions of the Policy, including the requirement to provide prompt notice of the loss and show the damaged property. As mentioned above, the Plaintiffs provided notice of the claim eight (8) months late, and performed various repairs prior to notifying the insurer of the claim. After the close of discovery, Mr. Smith and Ms. Keller filed a Motion for Summary Judgment on behalf of the insurer based on the late reporting, and further argued that the Plaintiffs had the burden of proving direct physical loss to property within the first 13 days of the loss, given the recent decision of Hicks v. American Integrity Insurance Company of Florida, 241 So.3d 925 (Fla. 3d DCA 1018). In Florida, when an insured fails to comply with their Duties After Loss, a presumption of prejudice to the insurer arises. Bankers Ins. Co. v. Macias, 475 So. 2d 1216, 1218 (Fla. 1985)). In order to recover, the Plaintiffs bear the burden of overcoming the presumption, and must prove that no prejudice existed. Id. Mr. Smith and Ms. Keller’s comprehensive arguments successfully proved to the Court that the Plaintiffs’ failure to timely report the claim prejudiced the insurer by prohibiting the insurer from being able to independently validate the loss, or distinguish between multiple causes of loss. Mr. Smith and Ms. Keller further argued that Plaintiffs did not meet their burden to prove that the insurer was not prejudiced by the Plaintiffs’ failure to comply with the Duties After Loss provision of the Policy. The Motion cited numerous cases and extensive analysis supporting the insurer’s position.
Reprinted courtesy of Burks A. Smith, III, Traub Lieberman and Kathryn Keller, Traub Lieberman
Mr. Smith, may be contacted at bsmith@tlsslaw.com
Ms. Keller may be contacted at kkeller@tlsslaw.com
Read the court decision
Read the full story...
Reprinted courtesy of
Musings: Moving or Going into a New Service Area, There is More to It Than Just…
July 16, 2023 — Christopher G. Hill - Construction Law Musings
For this week’s Guest Post Friday here at Construction Law Musings, we would like to welcome back (again) Sean Lintow Sr. (@The_HTRC) Sean has over 20 years in the construction and project management fields. As many know he pulled up stakes and moved to the State of Illinois almost a year ago where he still focuses on the “green” / energy efficiency markets by helping builders & trade professionals to improve their methods not only locally but nationally. Currently he is RESNET Rater, AEE CEA (Certified Energy Auditor), ENERGY STAR partner & verifier, EPA Indoor airPLUS verifier, Level 2 Infrared Thermographer, Volunteer Energy Rater for Habitat for Humanity, and Builders Challenge Partner & Verifier.
I would like to thank Chris for inviting me back as a guest poster. One item that struck a bell with me lately was his recent post for contractors considering work in another state is to check that states contractor licensing laws. Part of me was just saying – ahh if it were just that simple… With that in mind, here are some additional thoughts of mine along with advice picked up and given to others considering a move to greener pastures in another state, another town or maybe even taking that sweet little project outside of your current area that seems too good to pass up.
Licensing:
Yep this is a no-brainer – but unfortunately, as I pointed out in a 2012 piece it isn’t always that simple as in some cases the state may not require licensing and instead leave it to the towns which can be real fun to figure out. How long will it take to obtain? Ahh, but what about other licenses that a township may require? Working on a pre-78 house – is the state a self-managed one or is your current EPA certificate and training good enough? (Living in a self-managed state but working on an Indian Reservation? Well you will need to be EPA certified) Does the area require a specialty Storm Water Certificate or??? Read the court decision
Read the full story...
Reprinted courtesy of The Law Office of Christopher G. Hill
Mr. Hill may be contacted at chrisghill@constructionlawva.com
Generally, What Constitutes A Trade Secret Is A Question of Fact
February 01, 2021 — David Adelstein - Florida Construction Legal Updates
In construction, contractors maintain competitiveness by compiling, combining, utilizing, or developing proprietary and unique systems. The systems can be from a cost standpoint (determining general conditions or general requirement costs and percentages including percentages for insurance) or can be with respect to certain construction assembly or delegated design components. Such proprietary and unique systems are trade secrets to the contractors and efforts are taken to identify such information as confidential when proposing on a project. Contractors would not want such systems disclosed to others because it would dilute and impact what they believe is valuable and makes them competitive in the marketplace.
Florida’s Uniform Trade Secret Act (“FUTSA”) creates a statutory cause of action for the misappropriation of trade secrets. (FUTSA is set forth in Florida Statute s. 688.001 en seq.) FUTSA displaces or “preempts all claims [such as common law claims] based on misappropriation of trade secrets.” Alphamed Pharmaceuticals Corp. v. Arriva Pharmaceuticals, Inc., 391 F.Supp.2d 1148, 1167 (S.D.Fla. 2005). See also Fla. Stat. s. 688.008.
Florida Statute s. 688.002 (found here) defines the terms “trade secret” and “misappropriation.” Read the court decision
Read the full story...
Reprinted courtesy of David Adelstein, Kirwin Norris, P.A.
Mr. Adelstein may be contacted at dma@kirwinnorris.com
Oregon Construction Firm Sued for Construction Defects
July 31, 2013 — CDJ STAFF
Home Forward, the housing authority in Multnomah County, Oregon, is suing Tom Walsh & Company over allegations of construction defects in low-income housing projects the firm built for the county. Walsh’s firm was hired about ten years ago to construct apartments in Portland and adjacent Gresham. But the housing authority claims that the buildings are suffering water damage.
The authority requested that Tom Walsh & Company repair the problems. Walsh claimed that the problems were not due to construction defects, but to the agency’s failure to maintain the properties.
Home Forward has gone forward with lawsuits of a combined $3.8 million. If the case goes to trial, according to Walsh, it will be only the second time for him in 50 years of business.
Read the court decision
Read the full story...
Reprinted courtesy of
The One New Year’s Resolution You’ll Want to Keep if You’re Involved in Public Works Projects
January 07, 2015 — Garret Murai- California Construction Law Blog
New Year’s resolutions are hard to keep.
In fact, studies (which I have a sneaking suspicion may have been paid for by the tobacco, donut and vacation timeshare lobbies) have found that only 8% of New Year’s resolutions are kept.
But, here’s one you’ll want to make sure you keep.
Mandatory Registration and Notice Requirements
If you’re a public works contractor or subcontractor you only have until March 1, 2015 to register through the California Department of Industrial Relations (“DIR”) to bid and enter into public works contracts on state and local public works projects.
And if you’re a state or local public agency you must provide notice of the DIR’s new registration requirements in all call for bids and contract documents beginning January 1, 2015.
Read the court decision
Read the full story...
Reprinted courtesy of Garret Murai, Wendel Rosen Black & Dean LLP
Mr. Murai may be contacted at gmurai@wendel.com
Environmental Suit Against Lockheed Martin Dismissed
August 13, 2014 — Beverley BevenFlorez-CDJ STAFF
A federal judge dismissed an environmental suit against Lockheed Martin, finding that contamination levels on the plaintiffs’ Moorestown, New Jersey properties were not high enough to pose a health threat, according to the New Jersey Law Journal.
Two owners who live across the street from the plant had “sued under the Resource Conservation & Recovery Act, the Comprehensive Environmental Response, Compensation & Liability Act and various state statutes.” However, “while the suit was pending, the New Jersey Department of Environmental Protection raised the threshold for concentration levels of substances such as TCE and PCE to warrant additional testing.” Read the court decision
Read the full story...
Reprinted courtesy of
Is Solar the Next Focus of Construction Defect Suits?
June 28, 2013 — CDJ STAFF
There’s been a rapid growth in the sale of solar panels, and that’s lead some industry observers to wonder if manufacturers have been cutting back on quality. Current use of solar is six times what it was in 2008, with more than forty percent of that in the last year. The growth shows no sign of stopping, either. The Solar Energy Industry Association expects the amount of power generated by solar to increase by more than two-thirds in 2013.
With the oversupply, some fear that companies are relaxing their quality control. The New York Times found that there were widespread problems of defective units in solar cells, chiefly those manufactured in China. The Times article noted that at two solar plants in Spain, defect rates reached 34.5 percent.
Some industry observers disagree. The Insurance Journal quoted Andy Klump, the CEO of Clean Energy Associates, a Shanghai firm that provides quality assurance in the solar industry, who said that if a business had a 34 percent failure rate, “they would be out of business in a heartbeat.” Mr. Klump described the Times article as “not realistic.”
If the Times is right, Scott Turner, a construction insurance attorney, feels that the industry should ready itself for “a wave of large lawsuits.” Turner feels that “this litigation wave could make the battles over liability and insurance coverage for Chinese drywall seem like a small claims dispute.”
Read the court decision
Read the full story...
Reprinted courtesy of