Is the Event You Are Claiming as Unforeseeable Delay Really Unforeseeable?
September 26, 2022 —
David Adelstein - Florida Construction Legal UpdatesIs the item or event you are claiming as an unforeseeable, excusable delay really unforeseeable? This is not a trick question.
Just because your construction contract identifies items or events that constitute unforeseeable, excusable delay does not mean those items can be used as a blanket excuse or crutch for the contractor. That would be unfair.
For instance, it is not uncommon for a construction contract to list as unforeseeable, excusable delay the following events or items: “(i) acts of God or of the public enemy, (ii) act of the Government in either its sovereign or contractual capacity, (iii) acts of another Contractor in the performance of a contract with the Government, (iv) fires, (v) floods, (vi) epidemics, (vii) quarantine restrictions, (viii) strikes, (ix) freight embargoes, (x) unusually severe weather, or (xi) delays of subcontractors or suppliers at any tier arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers.” See, e.g., F.A.R. 52.249-10(b)(1). While the itemization of excusable delay may be worded differently, the point is there may be a listing as to what items or events constitute excusable delay. An excusable delay would justify additional time and, potentially, compensation to the contractor.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Foreclosing Junior Lienholders and Recording A Lis Pendens
July 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen you foreclose on a construction lien, there are a couple of pointers to remember.
First, you want to make sure you include junior lienholders or interests you are looking to foreclose (or you want to be in a position to amend the foreclosure lawsuit to identify later). The reason being is you want to foreclose their interests to the property. “[J]unior interest holders are a narrow class of mortgagees whose interest in the underlying property is recorded after the foreclosing contractor’s claim of lien is filed. This class is routinely joined to the construction lien enforcement action under section 713.26 to allow the construction lienor to foreclose out the junior lienholder’s interest in the property encumbered by the construction lien.” See Decks N Sunch Marine, infra.
Second, you want to record a lis pendens with the lien foreclosure lawsuit. Failure to do so could be problematic because Florida Statute s. 713.22(1) provides in part, “A lien that has been continued beyond the 1-year period by the commencement of an action is not enforceable against creditors or subsequent purchasers for a valuable consideration and without notice, unless a notice of lis pendens is recorded.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Res Judicata Bars Insured from Challenging Insurer's Use of Schedule to Deduct Depreciation from the Loss
June 10, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe insured was barred by res judicata from filing a second lawsuit challenging the insurer's method of establishing the amount of the loss. Burke v. GeoVera Spec. Ins. Co., 2024 U.S. App. LEXIS 9186 (5th Cir, April 16, 2024).
On August 29, 2021, Hurricane Ida caused wind damage to the Burkes' home. They filed a claim with their insurer, GeoVera Specialty, and received payment. In calculating the payment, GeoVera Specialty adjusted the damage claim pursuant to its Roof System Payment Schedule, which lists the criteria used in reducing roof damage claims based on depreciation. Based on that schedule, GeoVera Specialty reduced the roof damage component of the Burkes' claim by forty-eight percent.
In March 2022, the Burkes filed suit alleging that GeoVera Specialty undervalued their claim. On September 8, 2022, the parties filed a joint motion to dismiss the lawsuit after reaching a settlement, which the district court granted.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
‘I’m a Scapegoat,’ Says Former CEO of Dubai Construction Firm
September 30, 2019 —
Layan Odeh & Zainab Fattah - BloombergThe former chief executive officer of Drake & Scull International PJSC said the company’s accusations of financial violations against him are an attempt to find a “scapegoat” for rising losses.
Khaldoun Tabari said the Dubai-based contractor has filed 15 complaints against him to the public prosecutor last year. He said the allegations prompted authorities in the United Arab Emirates to order banks to freeze his bank accounts in June 2018. He denies any wrongdoing.
Read the court decisionRead the full story...Reprinted courtesy of
Layan Odeh & Zainab Fattah, Bloomberg
Insurers May Not Be Required to Defend Contractors In a Florida §558 Proceeding
November 06, 2018 —
Erik Simpson - Gordon & Rees Construction Law BlogIn recent holding, the Florida Supreme Court held that an insurer may not have a duty to defend a contractor in a Florida §558 proceeding.
Chapter 558 of the Florida Statutes sets forth procedural requirements which must be met before a claimant may file a construction defect action. These requirements include serving a contractor, subcontractor or supplier with written notice of the claim. The contractor, in turn, must serve a written response to the notice of claim in which the contractor provides either an offer to repair the alleged construction defect at no cost to the claimant, resolution of the claim through a monetary payment, a statement disputing the claim, or a statement that any monetary payment will be determined by the recipient’s insurer. The claimant may file suit if the contractor disputes the claim and refuses to remedy the alleged defect or provide monetary compensation.
Read the court decisionRead the full story...Reprinted courtesy of
Erik Simpson, Gordon & ReesMr. Simpson may be contacted at
esimpson@grsm.com
FEMA Fire Management Assistance Granted for the French Fire
July 08, 2024 —
The Federal Emergency Management AgencyOAKLAND, Calif. – The Federal Emergency Management Agency's (FEMA) Region 9 Administrator authorized the use of federal funds on July 4 at 11:37 p.m. PDT / 2:37 a.m. EDT to assist the state of California to combat the French Fire burning in Mariposa County.
On July 4, the state of California submitted a request for a Fire Management Assistance Grant (FMAG). At the time of the request, the fire threatened approximately 1,019 homes in and around Mariposa, CA, population 1,300. 95% of the threatened homes are primary residences and 5% are secondary residences.
The fire started on July 4, 2024 and had burned more than 790 acres of State and private land. The fire was 0% contained. There are five large fires burning uncontrolled within the State.
FMAGs provide federal funding for up to 75 percent of eligible firefighting costs. The Disaster Relief Fund provides allowances for FMAGs through FEMA to assist in fighting fires that threaten to become a greater incident.
Eligible costs covered by FMAGs can include expenses for field camps, equipment use, materials, supplies and mobilization, and demobilization activities attributed to fighting the fire.
For more information on FMAGs, visit https://www.fema.gov/assistance/public/fire-management-assistance.
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Nearly Triples Damages Caps for Cases Filed in 2025, Allows Siblings to File Wrongful Death Claims
July 22, 2024 —
Amy Johnson - Lewis BrisboisDenver, Colo. (June 13, 2024) - On June 3, 2024, Colorado Governor Jared Polis signed HB24-1472 to increase the damages caps for personal injury and wrongful death claims. The law nearly triples the amounts available to plaintiffs, which will continue to increase for inflationary adjustments beginning in 2028 and every two years thereafter. These new damages caps affect not only claims that accrue in 2025 and beyond, but they also change the caps for any civil cases filed on or after January 1, 2025. This law was enacted as a compromise to a ballot measure that would have removed any cap on damages. The new caps are as follows:
- The cap on noneconomic damages for personal injuries will be $1.5 million.
- The cap on noneconomic damages for wrongful death will be $2.125 million.
Plaintiffs are likely to delay filing new actions through the rest of 2024 as long as they are not up against a statute of limitations deadline.
Read the court decisionRead the full story...Reprinted courtesy of
Amy Johnson, Lewis BrisboisMs. Johnson may be contacted at
Amy.Johnson@lewisbrisbois.com
Extreme Flooding Overwhelms New York Roadways, Killing 1 Person
July 24, 2023 —
Associated Press - BloombergNEW YORK (AP) — Heavy rain spawned extreme flooding in New York’s Hudson Valley that killed at least one person, swamped roadways and forced road closures on Sunday night, as much of the rest of the Northeast U.S. braced Monday for potentially punishing rains.
As the storm moved east, the National Weather Service extended flash flood warnings into Connecticut, including the cities of Stamford and Greenwich, before creeping into Massachusetts. Forecasters said some areas could get as much as 5 inches (12 centimeters) of rain.
In New York's Hudson Valley, rescue teams found the body of a woman in her 30s who drowned after being swept away while trying to evacuate her home, Orange County Executive Steven Neuhaus told WABC-TV. Officials were waiting for the medical examiner's office to arrive, he said.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg