Product Liability Economic Loss Rule and “Other Property” Damage
November 28, 2022 —
David Adelstein - Florida Construction Legal UpdatesOne of the best defenses a manufacturer has, particularly in non-personal injury cases, is the economic loss rule. Lo and behold, a recent opinion out of the Middle District of Florida, Dero Roofing, LLC v. Triton, Inc., 2022 WL 14636884 (M.D.Fla. 2022), touches on this very subject with cogent analysis regarding “other property” damage for purposes of the economic loss rule.
In Dero Roofing, a roofing contractor repaired hurricane damage to roofs of condominium buildings. The roofing contractor became a certified applicator of the manufacturer Triton’s products. After the roofer applied certain products with a sprayer, the products “streaked down the roof tiles onto ‘the exterior and interior of the [Condos], including penetration of the residents’ screens, gutters, and other related areas.” Dero Roofing, supra, at *1. The roofing contractor obtained an assignment of the condominium’s claims and sued the manufacturer and distributor of the (Triton manufactured) products.
The defendants moved to dismiss under the economic loss doctrine.
The economic loss doctrine “prohibits tort recovery when a product damages itself, causing economic loss, but does not cause personal injury or damage to any property other than itself.” Dero Roofing, supra, at *3 (quotation and citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Eighth Circuit Affirms Finding of Bad Faith, Award of Costs and Prejudgment Interest
October 25, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Eighth Circuit affirmed the district court's finding of bad faith and award to the insured of taxable costs and prejudgment interest. Selective Ins. Co. v. Sela, 2021 U.S. App. LEXIS 26062 (8th Cir. Aug. 30, 2021).
The insured suffered two hail storms that damaged his home. In 2010, the first storm caused over half a million dollars in loss. Before submitting a claim to his original insurer or beginning any repairs, the insured secured a new policy with Selective. The policy did not exclude pre-existing damage, it did preclude coverage if the insured "willfully and with intent to defraud, concealed or misrepresented any material fact or circumstance relating to the insurance."
Before issuing the policy, Selective appraised the property and assigned a $1.6 million value to the home. The insured then filed a claim with his original insurer and received $510,787.23 for actual cash value of his loss. Neither the terms of this settlement nor this new policy with Selective required the insured to repair all of the 2010 damage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Pensacola Bridge Halted Due to Alleged Construction Defects
July 21, 2018 —
David Suggs – Bert L. Howe & Associates, Inc.The Pensacola News Journal reported that cracks were discovered again in the Pensacola Bay Bridge, which caused construction of said bridge to be halted once more: “Cracks found in a portion of the concrete in the Pensacola Bay Bridge project have twice halted construction in the last several months, raising concerns about oversight and disclosure from the state, particularly in light of the Miami bridge collapse earlier this year.”
The Florida Department of Transportation stated “that the cracks were found during a routine visual inspection of newly placed concrete in March,” according to the Pensacola News Journal. The $400 million project began in 2017 and was scheduled to be completed by 2020.
Read the court decisionRead the full story...Reprinted courtesy of
Include Contract Clauses for Protection Against Ever-Evolving Construction Challenges
May 30, 2022 —
Michael Henry & Kevin J. Riexinger - Construction ExecutiveThe first quarter of 2022 provided a valuable glimpse into some of the major issues the construction industry can expect to continue impacting jobsites for the rest of the year.
Early in the pandemic, construction was not immune from the shut-downs that swept across market sectors. Workers were staying home to shield themselves and their families from the COVID-19 virus (and variants). This caused delays with construction projects and failures to meet negotiated benchmarks or deadlines. Contractors were left to wonder whether they remained obligated to perform under their contracts, or whether COVID-19 allowed them to invoke force majeure clauses. Over the past two years, there has been much debate about whether force majeure clauses encompass COVID-19 risks.
Traditionally, force majeure is only invoked for significant weather events or natural disasters. Unsurprisingly, outcomes of legal actions regarding COVID-19 and force majeure varied by state and by contract. It didn’t take long for contractors to seek a more predictable and certain solution.
Reprinted courtesy of
Michael Henry & Kevin J. Riexinger, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Riexinger may be contacted at kriexinger@gllawgroup.com
Mr. Henry may be contacted at MbHenry@tcco.com
Read the court decisionRead the full story...Reprinted courtesy of
Fifth Circuit Certifies Questions to Texas Supreme Court on Concurrent Causation Doctrine
August 07, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Fifth Circuit certified unanswered questions on the concurrent causation doctrine to the Texas Supreme Court. Overstreet v. Allstate Vehicle & Prop, Ins. Co., 2022 U.S. App. LEXIS 13582 (5th Cir. May 19, 2022).
The insured alleged that a hail storm damaged his roof. The roof was three years old when he purchased a policy from Allstate. An adjuster sent by Allstate valued the loss at $1,263.123, less than the policy deductible. Allstate contended that the roof damage was due to uncovered causes, namely a combination of wear and tear and earlier hail storms that hit the roof before the insured purchased the policy. The insured disagreed because the roof had never leaked before the hail storm, but only after the storm. The insured's expert inspected the roof and determined it had been damaged by hail. The district granted Allstate's motion for summary judgment because the insured had not carried his burden of proving how much damages came from the hail storm alone.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
No Coverage Under Property Policy With Other Insurance and Loss Payment Provisions
September 17, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that the other insurance and loss payment provisions relieved the insurer of coverage obligations. Moroney Body Works, Inc. v. Central Ins. Co., 2015 Mass. App. LEXIS 97 (Aug. 6, 2015).
A fire destroyed Moroney's custom-built bookmobile that had just been completed. Moroney had two policies: a commercial property policy issued by Central, and a garage insurance policy issued by Pilgrim Insurance Company. Central denied liability for the bookmobile. Pilgrim covered the cost of repairing the bookmobile. It paid $12,449.82 based on the appraiser's estimate of the repair costs. Moroney thought this amount was inadequate given its own estimate of the repair costs.
Moroney sued both insurers. Pilgrim settled by paying Moroney an additional amount which, when added to Pilgrim's earlier payment, resulted in Moroney receiving more than the repair cost. Moroney and Central both moved for summary judgment. The trial court granted Moroney's motion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Limiting Services Can Lead to Increased Liability
December 16, 2019 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday Musings, we welcome Nick Pacella. Nick is an architect licensed in New York, New Jersey and Connecticut. His practice has spanned several economic swings and he has been able to reposition the eggs in his basket to make the most of each recovery. He is currently focusing on adapting existing commercial buildings to take advantage of materials and processes that promote improved energy efficiency for both the owner and the tenants. For a more colorful rendition of projects you can visit his company’s website.
I remember as a kid when the attendant at gas stations would not only clean your windows but also check the oil level of your vehicle as it was filling up with $0.25 per gallon gas. (I did say that I have seen several economic swings) These services have mostly disappeared, and to no great effect to your car since most cars go much longer between oil changes. Other than a slightly dirtier windshield it hasn’t affected your ability to drive and maintain your car.
This is not so with professional services. Architects used to include many services that are now sourced to others. Project Management, Owner’s Representatives and Program Managers now populate the landscape. In many cases they came to be because architects either did not provide the service their client’s were looking for or they allowed themselves to be put into an adversarial relationship with their clients. They were likened to foxes watching the chicken coop, especially for project management and owners representative services. Client’s have had others buzzing in their ears “are architects really going to look out for my interests above theirs?’” Of course the clients never ask if the new wave will do any better at rallying behind their interests.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Musk’s Cousins Battle Utilities to Make Solar Rooftops Cheap
April 15, 2015 —
John Lippert and Christopher Martin – BloombergIn September 2013, Hawaiian Electric Co. told thousands of customers they couldn’t connect their new solar panels to its distribution grid. In some neighborhoods, HECO said, its system couldn’t absorb any more unused energy from home solar arrays. The moratorium, which lasted 13 months, made Hawaii a central battleground in the effort by utilities to control the rapid growth of independent solar companies across the U.S. And it was a big deal to people such as Robert Gould, a retired Northwest Airlines pilot living near Honolulu. He’d just paid $53,000 to have solar panels installed.
Gould and other customers protested loudly to state officials. They finally got help from Lyndon Rive, the CEO of SolarCity. The San Mateo, California, company is the biggest installer of rooftop solar panels in the U.S. and has 10,000 Hawaiian customers, Bloomberg Markets magazine reports in its May issue. Rive studied the situation and zeroed in on a key fact: HECO had never directly measured how much solar its grid could handle, relying on computer simulations instead. “Because the technology is brand-new, no one had ever done this in the field before,” says Colton Ching, HECO’s vice president for energy delivery.
Reprinted courtesy of
John Lippert, Bloomberg and
Christopher Martin, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of