Court Reminds Insurer that the Mere Possibility Of Coverage at the Time of Tender Triggers a Duty to Defend in a Defect Action
October 04, 2021 —
Jatin Patel - Newmeyer DillionIt has long been the law in California that an insurer’s duty to defend is broader than the duty to indemnify and that the mere possibility of coverage triggers a duty to defend. Nevertheless, insurers still periodically ignore this clear principle and attempt to narrow the scope of the duty to defend. Recently, a Federal District Court issued a reminder to a wayward insurer.
In Pacific Bay Masonry, Inc., v. Navigators Specialty Insurance Company, (N.D. Cal., Sept. 16, 2021, No. C 20-07376 WHA, 2021 WL 4221747 (“Pacific”)), the Court was asked to assess whether a tender of defense by a concrete masonry subcontractor to its insurer for a construction defect action required a defense. Pacific Bay Masonry, Inc. (“PBM”) installed concrete masonry units (also known as “CMUs”) at a new retail shopping center in Oakland, California. The subsequent owner of the retail center filed suit against the general contractor for alleged construction defects, including “efflorescence of roof deck at CMU wall” and “improper waterproofing and flashing of the CMU block wall." The general contractor filed a cross-complaint against PBM.
PBM tendered the defense of the case to Navigators Specialty Insurance Company (“Navigators”) along with copies of a preliminary defect list, a description of defects, interrogatory responses and an expert witness damage analysis. Navigators denied coverage and a duty to defend citing to the work product exclusion of the policy. PBM asked Navigators to reconsider. Navigators held firm on its denial. Two years later, PBM filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Jatin Patel, Newmeyer DillionMr. Patel may be contacted at
jatin.patel@ndlf.com
Beyond the Disneyland Resort: Special Events
May 03, 2018 —
Beverley BevenFlorez-CDJ STAFFWant to exchange your mouse ears for a baseball cap? The
Los Angeles Angels of Anaheim are home May 13th through the 20th. See the Angels play Houston on the 16th or Tampa Bay on the 17th or 18th.
The
House of Blues of Anaheim has moved out of Downtown Disney. Concerts you may want to attend there include VHS Collection on 5/16 at 7pm, Party Like It’s 1999! A Prince Tribute Party at 7pm on 5/18 or Life of Agony also at 5/18 at 7pm. If you’re still in town on Saturday, 5/19, you can check out School of Rock Tustin at 10am.
Soulfly & Nile will be playing at the
City National Grove of Anaheim on Friday, 5/18 at 6:30pm.
Read the court decisionRead the full story...Reprinted courtesy of
The General Assembly Seems Ready to Provide Some Consistency in Mechanic’s Lien Waiver
March 14, 2018 —
Christopher G. Hill – Construction Law MusingsBack in 2015, the
Virginia General Assembly amended the mechanic’s lien statute (Va. Code 43-3) here in Virginia to preclude any contractual provision that diminishes a subcontractor or supplier’s “lien rights in a contract in advance of furnishing any labor, services, or materials.” However, this amendment was only applicable to subcontractors and suppliers. For political and other reasons, general contractors in Virginia were left out of this change. This omission by the legislature put Virginia general contractors in the position of potentially being forced by project owners to waive their mechanic’s lien rights without the ability to run that risk downstream to their subcontractors and suppliers.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Construction Law Alert: Concrete Supplier Botches Concrete Mix, Gets Thrashed By Court of Appeal for Trying to Blame Third Party
January 21, 2015 —
Steven M. Cvitanovic and Whitney L. Stefko – Haight Brown & Bonesteel LLPOn January 8, 2015, the Second Appellate district affirmed judgment of the lower court in State Ready Mix Inc. v. Moffatt & Nichol, and barred a concrete supplier from blaming a third party consultant for the concrete supplier's failure to deliver concrete that met project specifications.
In 2012, Major Engineering Marine, Inc. was hired by a project manager to construct a harbor pier in the Channel Islands Harbor. Major hired State Ready Mix, Inc. to supply the concrete for the project. State wrote and submitted a concrete mix design and, at the request of Major, civil engineer Moffatt & Nichol reviewed and approved State's mix design at no charge.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Five Years of Great Legal Blogging at Insurance Law Hawaii
December 09, 2011 —
CDJ STAFFOur congratulations to Tred Eyerly who has been blogging at Insurance Law Hawaii for five years now. Over the years, he has posted more than five hundred posts and has provided us all with fascinating insights into the laws on insurance coverage. He describes his blog as “a commentary on insurance coverage issues in Hawaii and beyond.” We are grateful that the “beyond” has just in the last few weeks included Colorado, Illinois, Washington, Minnesota, and Rhode Island (about as far from the island of Hawaii as you can get).
You can read his blog at Insurance Law Hawaii.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Advisory: Mechanical Contractor Scores Victory in Prevailing Wage Dispute
September 03, 2014 —
Steven M. Cvitanovic & Jessica M. Lassere Ryland - Haight Brown & Bonesteel LLPOn August 27, 2014, the First District Court of Appeal weighed in on whether prevailing wages are required for public contracts in situations where work is performed in furtherance of the project but at a permanent offsite manufacturing facility that is not exclusively dedicated to the project. In Sheet Metal Workers' International Association, Local 401 v. John C. Duncan and Russ Will Mechanical, the project at issue was for a community college district where Russ Will was the HVAC subcontractor. The contract documents required contractors to pay prevailing wages but they did not limit where or how Russ Will would fabricate sheet metal required for the job. Russ Will used its existing fabrication facility to form the sheet metal.
An employee of Russ Will filed a complaint with the DIR alleging he should have been paid prevailing wages for work related to the project. The worker fabricated sheet metal for the project but at Russ Will’s Hayward facility, not at the site. The DIR issued a coverage determination in which it concluded that Russ Will was required to pay prevailing wages for the offsite fabrication work associated with the project. The DIR's determination turned on whether Russ Will was exempt from the prevailing wage law as a material supplier. To qualify for the material supplier exemption, the employer must sell supplies to the general public and its fabrication or manufacturing facility must not be established for the particular public works contract or be located at the site of the public work.
Following the DIR determination, Rush Will filed an administrative appeal. The department reversed its initial coverage determination, concluding that the offsite fabrication performed by Russ Will was not subject to the prevailing wage law.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Jessica M. Lassere Ryland, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Ryland may be contacted at jlassere@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
HOA Has No Claim to Extend Statute of Limitations in Construction Defect Case
October 28, 2011 —
CDJ STAFFThe California Court of Appeals ruled on September 20, 2011 in the case of Arundel Homeowners Association v. Arundel Green Partners, a construction defect case involving a condominium conversion in San Francisco. Eight years after the Notice of Completion was filed, the homeowners association filed a lawsuit alleging a number of construction defects, including “defective cabinets, waterproofing membranes, wall-cladding, plumbing, electrical wiring, roofing (including slope, drainage and flashings), fire-rated ceilings, and chimney flues.” Three years of settlement negotiations followed.
Negotiations ended in the eleventh year with the homeowners association filing a lawsuit. Arundel Green argued that the suit should be thrown out as California’s ten-year statute of limitations had passed. The court granted judgment to Arundel Green.
The homeowners then filed for a new trial and to amend its complaint, arguing that the statute of limitations should not apply due to the doctrine of equitable estoppel as Arundel Green’s actions had lead them to believe the issues could be solved without a lawsuit. “The HOA claimed that it was not until after the statute of limitations ran that the HOA realized Arundel Green would not keep its promises; and after this realization, the HOA promptly brought its lawsuit.” The trial court denied the homeowners association’s motions, which the homeowners association appealed.
In reviewing the case, the Appeals Court compared Arundel to an earlier California Supreme Court case, Lantzy. (The homeowners also cited Lantzy as the basis of their appeal.) In Lantzy, the California Supreme Court set up a four-part test as to whether estoppel could be applied. The court applied these tests and found, as was the case in Lantzy, that there were no grounds for estoppel.
In Arundel, the court noted that “there are simply no allegations that Arundel Green made any affirmative statement or promise that would lull the HOA into a reasonable belief that its claims would be resolved without filing a lawsuit.” The court also cited Lesko v. Superior Court which included a recommendation that the plaintiffs “send a stipulation?Ķextending time.” This did not happen and the court upheld the dismissal.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Why You Make A Better Wall Than A Window: Why Policyholders Can Rest Assured That Insurers Should Pay Legal Bills for Claims with Potential Coverage
March 14, 2018 —
Alan Packer and Graham Mills - Newmeyer & Dillion, LLPUnfortunately, policyholders, such as manufacturers and contractors, routinely face the unnecessary challenge of how to access all of the insurance coverage which they have purchased. Frequently, the most pressing need is to get the insurance company to pay the legal bills when the policyholders have been sued. The recent Iowa federal district court opinion in
Pella Corporation v. Liberty Mutual Insurance Company should help a policyholder in a dispute to require its insurance company to pay those legal bills sooner rather than later by highlighting that the duty to defend arises from the potential for coverage, and the insurer may not force the policyholder to prove the damage to obtain a defense.
In
Pella, a window manufacturer purchased several years of insurance coverage from Liberty Mutual. Similar to many companies, Pella had many “layers” of insurance coverage in any given year. These layers collectively function like a tower. The general idea is that each layer provides a certain amount of coverage after the insurance policy below it had paid its money. The Liberty Mutual insurance policies provided excess coverage.
After the
Pella window manufacturer made and sold its windows, it was sued in numerous lawsuits alleging that its windows were defective and that those defective windows caused a wide variety of damage to the structures in which they were installed. The window manufacturer tendered those lawsuits to its insurance companies in its tower of coverage, asking that the insurance companies pay its legal bills incurred in its defense. As to Liberty Mutual, the window manufacturer argued that the Liberty Mutual insurance policies were triggered, and so obligated to reimburse it, if a window was installed during the years that those policies provided coverage or if there was a mere allegation that a window was installed during the years that those policies provided coverage. Liberty Mutual opposed, arguing that the date of installation of the windows was insufficient to trigger the policies, and that the manufacturer was required to demonstrate the date that damage actually occurred to trigger a defense.
The key issue before the
Pella Court in this decision was a simple one: which insurance policies, if any, issued by Liberty Mutual had an obligation to pay the window manufacturer’s legal bills? The answer to that question is critical and financially significant. Getting an insurance company to honor its obligations and start paying the legal bills as soon as possible is very important for a policyholder because of the cost of defending oneself in a lawsuit; often the key reason why an insurance policy is even purchased is to provide the policyholder with the right to call upon the insurance company’s financial resources to defend it should it be sued.
In a ruling that will be welcomed by policyholders, the
Pella Court held that Liberty Mutual’s multiple insurance policies were triggered, and so obligated to pay for the window manufacturer’s defense, if one of two events occurred during the years in which those insurance policies provided coverage: (1) a window was actually installed during a year when the insurance policy provided coverage or (2) the window was alleged to be installed in the year that the insurance policy provided coverage. The Court agreed with the policyholder that once the windows were installed, property damage was alleged and “may
potentially have occurred” from that point on, thus the policies on the risk from that point forward. The practical effect of this ruling meant that Liberty Mutual had to reimburse the window manufacturer for the defense fees and costs that it had paid.
While
Pella was decided under Iowa law, the principles upon which it relied are similar to those applied under California law. Importantly, both California and Iowa law hold that an insurance company must provide a defense in response to a claim that is, or could be, covered by the insurance policy. The mere potential that the claim might be covered is enough for the insurance company to be obligated to pay for policyholder’s legal fees and costs.
Establishing that an insurance company must pay legal fees and costs as soon as possible allows a policyholder to save its own money. Why should a policyholder pay legal bills when it purchased an insurance policy as protection to ensure that it did not have to pay those bills? The answer is that a policyholder should not and, under
Pella, the policyholder does not have to. Rather, the insurance company must start paying for that defense from a very early date. Pella confirms for policyholders the position that their insurance companies should pay legal bills earlier rather than later.
Alan Packer is a partner in the Walnut Creek office for Newmeyer & Dillion, LLP, representing homebuilders, property owners, and business clients on a broad range of legal matters, including risk management, insurance matters, wrap consultation and documentation, efforts to counter solicitation of homeowners, subcontract documentation, as well as complex litigation matters. Alan can be reached at alan.packer@ndlf.com.
Graham Mills is a partner in the Walnut Creek offce of Newmeyer & Dillion, LLP, representing clients in the area of complex insurance law with an emphasis on insurance recovery, construction litigation, real estate litigation, and business litigation. He regularly examines and analyzes a wide variety of insurance policies. Graham can be reached at graham.mills@ndlf.com.
ABOUT NEWMEYER & DILLION LLP
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review’s AV Preeminent® highest rating.
For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of