New York’s Highest Court Weighs in on N.Y. Labor Law
September 23, 2024 —
Bill Wilson - Construction Law ZoneN.Y. Labor Law § 241(6) requires owners and contractors to provide reasonable and adequate protection and safety to persons employed at or lawfully frequenting a construction site. If a worker is injured on a construction site and establishes a violation of a specific and applicable Industrial Code regulation, both the owner and contractor will be held vicariously liable for the worker’s injury, without regard to their fault and even in the absence of control or supervision of the worksite. The Court of Appeals of New York recently addressed the broad scope of the Labor Law in the context of slipping hazards.
In Bazdaric v. Almah Partners, LLC, 41 N.Y.3d 310 (2024), the plaintiff, an injured painter, slipped and fell on a plastic covering placed over an escalator in an area he was assigned to paint. The plaintiff claimed that the plastic covering was a foreign substance for purposes of Industrial Code 12 NYCRR 23-1.7(d) because it was not part of the escalator. Industrial Code 12 NYCRR 23-1.7(d) states:
Slipping hazards. Employers shall not suffer or permit any employee to use a floor, passageway, walkway, scaffold, platform or other elevated working surface which is in a slippery condition. Ice, snow, water, grease and any other foreign substance which may cause slippery footing shall be removed, sanded or covered to provide safe footing.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Ex-Turner Exec Gets 46 Months for Bloomberg Construction Bribes
July 11, 2021 —
Eydie Cubarrubia - Engineering News-RecordA third New York City-based construction executive was sentenced to federal prison June 15, receiving 46 months, as part of the $15-million bribery scheme involving interiors work for financial giant Bloomberg LLP at its Manhattan headquarters.
Reprinted courtesy of
Eydie Cubarrubia, Engineering News-Record
Ms. Cubarrubia may be contacted at cubarrubiae@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Steven L. Heisdorffer Joins Higgins, Hopkins, McLain & Roswell
March 27, 2019 —
Steve Heisdorffer - Colorado Construction LitigationHiggins, Hopkins, McLain & Roswell is pleased to announce that Steve Heisdorffer has joined the firm as Special Counsel. Steve joins the firm after having been a partner at Godin & Baity, LLC for the last twenty-five years.
Mr. Heisdorffer represents construction professionals in construction defect disputes and advises them regarding risk mitigation and transfer. Mr. Heisdorffer is an experienced trial lawyer that has tried commercial disputes and construction defect cases in arbitration forums and courts over the last 28 years. In addition, he has successfully represented large and small companies in commercial disputes, including computer software performance and intellectual property disputes, taking several to trial. Steve has also acted as a counselor to technology companies. Steve has expertise drafting and negotiating development agreements, distributor agreements, license agreements, and service agreements for his technology clients.
Mr. Heisdorffer graduated with high honors from both the University of Northern Iowa and University of Iowa, College of Law and is an AV ® Preeminent™ Peer Review Rated attorney by Martindale-Hubbell and has presented to a variety of trade groups including technology, construction, and insurance industries.
Read the court decisionRead the full story...Reprinted courtesy of
Steve Heisdorffer, Higgins, Hopkins, McLain & RoswellMr. Heisdorffer may be contacted at
heisdorffer@hhmrlaw.com
Condo Collapse Spurs Hometown House Member to Demand U.S. Rules
July 19, 2021 —
Parker Purifoy - BloombergA Florida congresswoman called for stricter federal building-safety standards on Thursday to prevent a repeat of the condominium collapse that killed at least 60 people and left dozens more missing in her state.
Representative Debbie Wasserman Schultz, a Democrat whose congressional district includes the condo development in Surfside, said more buildings could collapse or break down as they age and the federal government needed to have a “minimum floor” of safety requirements.
“We do have standards that are tangentially related at the federal level and so I do think it’s important to look into what standards should be adopted at the national level, at a minimum, because this is a tragedy of epic proportions,” she said on Bloomberg Television’s “Balance of Power” with David Westin. “We can’t allow this to ever happen again.”
Read the court decisionRead the full story...Reprinted courtesy of
Parker Purifoy, Bloomberg
United States Supreme Court Limits Class Arbitration
May 13, 2019 —
Jeffrey K. Brown & Raymond J. Nhan - Payne & FearsOn April 24, 2019, the United States Supreme Court held that the Federal Arbitration Act ("FAA") bars orders requiring class arbitration when an agreement is ambiguous about the availability of such a procedure. Lamps Plus v. Varela, 587 U.S. __ , 2019 WL 1780275, (2019). In Lamps Plus, the Court clarified a 2010 case in which it held that a court may not compel arbitration on a class-wide basis when an agreement is silent on the availability of class arbitration. Stolt-Nielsen S.A. v. Animal Feeds Int'l Corp., 559 U.S. 662, 687 (2012).
In Lamps Plus, a 5-4 decision authored by Chief Justice Roberts, the Court explained that because the FAA envisions the use of traditional individualized arbitration, a party cannot be forced under the FAA to submit to class arbitration unless the parties explicitly agreed to do so. Because class arbitration does not share the benefits of traditional arbitration -- lower costs, greater efficiency and speed, and the parties' choice of a neutral -- the FAA requires more than an "ambiguous" agreement to show that the parties bound themselves to arbitrate on a class-wide basis. Unlike individualized arbitration, or even traditional class actions, class arbitration raises serious due process concerns because absent class members will have limited judicial review. Based on these critical differences between individual and class arbitration, the Court reiterated in Lamps Plus that "courts may not infer consent to participate in class arbitration absent an affirmative contractual basis for concluding that the party agreed to do so."
Reprinted courtesy of
Jeffrey K. Brown, Payne & Fears and
Raymond J. Nhan, Payne & Fears
Mr. Brown may be contacted at jkb@paynefears.com
Mr. Nhan may be contacted at rjn@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Don’t Kick the Claim Until the End of the Project: Timely Give Notice and Preserve Your Claims on Construction Projects
December 10, 2015 —
Christopher G. Hill – Construction Law MusingsFor this week’s Guest Post Friday, we welcome
Tara L. Chadbourn. Tara is an attorney with
ReavesColey PLLC in Chesapeake, VA, where she concentrates her practice on construction law, litigation and commercial litigation. Tara counsels owners, contractors, subcontractors and materials suppliers in various government and commercial construction matters. Tara can be reached at tara.chadbourn@reavescoley.com.
You may have experienced and have certainly heard of the scenario in which a contractor waits to address a claim as part of project closeout, only to realize the applicable deadline has already passed. While there may have been discussions about claims during the course of the project, contractors cannot rely upon oral conversations about outstanding claims. Instead, contractors must be vigilant in satisfying notice requirements and preserving claims. While entitlement must still be proven, a contractor’s chances of recovery increase greatly if the contractor abides by notice requirements and consciously preserves claims in the following ways.
Contractors Must Acquaint Themselves with Contractual Notice Provisions:
Many prime and subcontract agreements contain stringent notice provisions that require the contractor to give notice within a certain time period or else the claim is expressly waived. The deadline for notice is often only a few days after the occurrence giving rise to the claim or the contractor becoming aware of the claim. To avoid waiver, contractors must carefully review their contracts for provisions requiring notice of a claims for adjustment for a variety of situations to include unforeseen site conditions, trade sequencing changes, project delay or scope of work changes.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
OSHA Issues COVID-19 Guidance for Construction Industry
July 13, 2020 —
Garret Murai - California Construction Law BlogThis past month, after remaining relatively quiet following the coronavirus outbreak, OSHA began issuing industry-specific guidance on how to deal with the coronavirus in the workplace.
Until this month, the only construction industry specific guidance issued by OSHA was an OSHA Alert entitled COVID-19 Guidance for the Construction Workforce, a one page document providing little more guidance than that workers should stay home if sick, wear masks and frequently wash hands to prevent spreading and catching the coronavirus, and to sanitize tools and work areas.
Early this month, OSHA issued more comprehensive guidance for the construction industry. The guidance, as noted in the preface by OSHA is simply guidance, “is not a standard or regulation” and “creates no legal obligations. The guidance supplements general guidance applicable to all workplaces issued earlier by OSHA.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Quick Note: Attorney’s Fees and the Significant Issues Test
November 03, 2016 —
David Adelstein – Florida Construction Legal UpdatesAttorney’s fees become a component of damages that parties seek to recover whenever there is a contractual or statutory basis for them to recover their fees. Parties want to be able to recover all or substantially most of the attorney’s fees they incurred in pursuing their claim. (In my experience, recovering all of the fees incurred is very challenging.) But, to be entitled to attorney’s fees, a party has to be deemed the
prevailing party. There is the sentiment that as long as you recover a positive net judgment (even if it is for $100 when your claim was for $50,000) then you will be able to recover your attorney’s fees which will likely exceed the amount that was ever in dispute.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com