UPDATE: Texas Federal Court Permanently Enjoins U.S. Department of Labor “Persuader Rule” Requiring Law Firms and Other Consultants to Disclose Work Performed for Employers on Union Organization Efforts
December 08, 2016 —
Aaron C. Schlesinger & Gregory R. Begg – Peckar & Abramson, P.C.As an update to our prior alert, on November 16, 2016, a federal judge in Texas issued a permanent injunction blocking the U.S. Department of Labor’s (“DOL”) “persuader rule” – a preliminary injunction had been granted this past June.
In rendering the permanent injunction, the court adopted the reasoning of its prior June 27, 2016 decision that granted a nationwide preliminary injunction on the rule. In the earlier decision, the court held that a temporary injunction was appropriate because the parties challenging the rule were likely to succeed on the merits of their claim […].
Reprinted courtesy of
Aaron C. Schlesinger, Peckar & Abramson, P.C. and
Gregory R. Begg, Peckar & Abramson, P.C.
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Mr. Begg may be contacted at gbegg@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Efficient Proximate Cause Doctrine Bars Coverage for Collapse of Building
July 31, 2013 —
Tred Eyerly, Insurance Law HawaiiThe court rejected the insured's argument that there was coverage for the collapse of a building caused by water leakage (a covered peril) and landslide (an uncovered peril). Stor/Gard, Inc. v. Strathmore Ins. Co., 2013 U.S. LEXIS App. 11015 (1st Cir. May 31, 2013).
A severe rain storm caused soil to slide down a hill and over a retaining wall, thereby damaging a building owned by the insured. Investigators hired by Strathmore Insurance Company determined that rain had soaked into the soil, causing the landslide. Although the investigators found some water leakage, they determined the leakage was not a cause or contributing factor, and was negligible compared to the rain amount.
The insured's policy with Strathmore was an all-risk policy. Loss caused by a landslide was excluded. Further, loss caused by collapse was excluded from coverage except as set forth in the policy's "additional coverage for collapse" section. This section provided coverage for a collapse caused by water damage or a leakage of water. Another exclusion barred coverage for loss caused by weather conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Your Bad Faith Jury Instruction Against an Insurer is Important
March 09, 2020 —
David Adelstein - Florida Construction Legal UpdatesA statutory bad faith claim against an insurer is derived from Florida Statute s.
624.155. A bad faith claim against a first party insurer, such as a property insurer, must be statutory. Check out the hyperlink of the statute, but a party must first file a Civil Remedy Notice identifying the statutory violations to preserve the statutory bad faith claim giving the insurer an opportunity to cure.
In a noteworthy case, Cooper v. Federated National Insurance Company, 44 Fla. L. Weekly D2961a (Fla. 5th DCA 2019), the Fifth District Court of Appeal dealt with the jury instruction for an insured’s statutory bad faith claim against their property insurer. The insured filed a bad faith claim predicated on the property insurer violating the provisions of Florida Statute s.
626.9541(1)(i)3, which involves unfair claim settlement practices. The insured had a jury trial and submitted a proposed jury instruction regarding bad faith that tracked the very essence of their bad faith claim and was modeled after s. 626.9541(1)(i)(3). The trial court, however, denied this jury instruction, instead adopting a standard jury instruction for bad faith. The jury returned a verdict in favor of the property insurer and the insured appealed arguing it was reversible error for the trial court NOT to present to the jury their bad faith jury instruction. The Fifth District agreed and ordered a new trial finding that the trial court’s failure to present the jury instruction amounted to a miscarriage of justice.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Design Firm Settles over Construction Defect Claim
July 31, 2013 —
CDJ STAFFA Pennsylvania township has announced that it has reached a settlement with the architectural firm that designed its administration building. Cee Jay Frederick Associates will be paying than $1.05 million to settle claims of defects in the design of the building.
West Whiteland’s administration building was completed in July 2007. The first leaks were noticed in November and December 2008. In response, the township stopped payments to the contractor, Magnum, Inc. Magnum sued, claiming that their work was not to blame for the leaks. Magnum joined the township in suing the design firm.
Although Cee Jay Frederick Associates will be paying the township to settle the claim, West Whiteland will be paying $75,000 of that back to the firm to settle outstanding bills that had been withheld during litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “A Close Call?”
August 05, 2024 —
Daniel Lund III - LexologyNot really, said a Florida state appellate court when a public construction project owner sued a defaulted general contractor after recovering from the general contractor’s surety.
The general contractor, Close Construction, entered into a contract for a lift station rehabilitation construction project with the City of Riviera Beach in Florida. During the course of the work the public owner terminated the contract, whereupon the GC and the owner brought claims against each other in court. A jury ultimately held against the general contractor and in favor of the public owner in the amount of approximately $1.9 million. The general contractor appealed.
On appeal, the general contractor noted that the public works surety which it was required by the contract to obtain for the project had hired another company to complete the work when the general contractor was terminated and had otherwise “settled with the District under its bond for $1,000,000.” Based on that settlement, the general contractor had moved, unsuccessfully, in the trial court for a post-trial setoff because the “settlement covered the same damages that the jury assessed” against the GC, and because the surety was “jointly and severally liable” with the GC – pursuant to the terms of the bond – for those damages. In essence, the general contractor sought to avoid having the public owner “obtain a double recovery.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Reminder: Pay if Paid Not All Encompassing (but Could it be?)
December 09, 2019 —
Christopher G. Hill - Construction Law MusingsOn numerous occasions, I have discussed the need to be careful with so called “pay if paid” clauses in construction contracts. While such clauses are enforceable in Virginia (when phrased correctly), there are exceptions and limitations (for instance in the Miller Act context).
One such exception (that I frankly would have thought to be obvious) is that such clauses do not protect a general contractor from paying all subcontractors. Such a clause only protects a general contractor from payment to those subs for whose work the general contractor has not been paid. In other words, if a general contractor has been paid by an owner for a particular subcontractors work, it cannot use the pay if paid clause to deny payment even in the event that other subcontractors were deficient in their work or the owner has failed to pay the general contractor in full.
In Precision Contractors Inc. v. Masterbuilt Companies Inc. (PDF) the Fairfax, VA Circuit Court reiterated this principal stating that nothing in the contract suggests that either party to the lawsuit had any intention to shift the risk of non-payment by the owner or non-performance of other subcontractors to the plaintiff (Precision).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Collapse of Improperly Built Deck Not An Occurrence
August 17, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe court found that the insured's faulty construction of an outside deck did not arise from an occurrence. Employers Mut. Cas. Co. v. West, 2017 U.S. Dist. LEXIS 113951 (N.D. Miss. July 21, 2017).
D.L. Action Construction Company (DLA) constructed multifamily dwellings. They were sued by the homeowners after a deck collapsed at one of the dwellings. Also sued was the subcontractor, Littrell Construction, who installed the deck. The homeowners alleged that Littrell knew that college students would be residing in the units and that the decks would be heavily used. The decks were attached to the building structure using only nails instead of bolts.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insurer's Motion for Summary Judgment to Reject Collapse Coverage Denied
November 24, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer unsuccessfully moved for summary judgment seeking to reject the insured's collapse claim. Gnannn v. United Servs. Auto, Ass'n, 2019 Conn. Super. LEXIS 1955 (Conn. Super Ct. July 11, 2019).
The insureds' home was built in 1985 and they purchased their home in 1993. A home inspection reported that some settlement and curing related cracks existed in the slab floor, but no signs of abnormal settlement were noticed. The concrete walls were in overall good condition.
In 2015, the insureds became aware of abnormal cracking in the basement. USAA was informed of the claim but denied coverage in October 2015. The insureds sued USAA. After suit was filed, the insureds hired an engineer, David Grandpre, to inspect their home. He observed severe cracking in the basement walls caused by an expansive chemical reaction within the concrete. The structure was not in imminent peril of falling down, and it continued as insureds' residence. But Mr. Grandpre noticed bulging and bowing, evidence that the concrete basement walls had failed and had begun to move inward due to the lateral pressure of the soil outside the home.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at