Energy Company Covered for Business Interruption Losses Caused by Fire and Resulting in Town-Ordered Shutdown
February 15, 2021 —
David G. Jordan - Saxe Doernberger & Vita, P.C.In the case of NextSun Energy Littleton, LLC v. Acadia Ins. Co., the United States District Court of Massachusetts held that once direct physical damage from a covered peril causes a covered business interruption loss, any increase in the duration of such business interruption, due to the enforcement of an ordinance or law, extends the coverage period provided for lost income. The Court further held that a policy exclusion for business interruption due to the enforcement of any ordinance or law not in force at the time of the loss only applies when the ordinance or law itself, not the enforcement action that it authorizes, was not in force at the time of the loss.
The case involved a solar panel company, NextSun Energy Littleton (NextSun), that operated solar panel arrays providing electricity to the town of Littleton, Massachusetts. Due to a fire, 88 of the solar panels were damaged, and the Town immediately issued a “red-tag” order halting all energy-generating activity pending a safety inspection. The plaintiff purchased insurance for its panels along with “Energy Generating Income” (EGI) coverage, from the defendant, Acadia Ins. Co. (Acadia). The EGI policy covered “direct physical loss or damage” to “renewable energy generating equipment” and also covered the actual loss of surplus power income incurred during the interruption period. However, it excluded interruption of energy-generating income “caused by the enforcement of any ordinance, law, or decree … not in force at the time of loss.”
Read the court decisionRead the full story...Reprinted courtesy of
David G. Jordan, Saxe Doernberger & VitaMr. Jordan may be contacted at
DJordan@sdvlaw.com
San Diego Appellate Team Prevails in Premises Liability Appeal
December 06, 2021 —
Corinne Bertsche, Jeffry Miller & Tracy Forbath - Lewis BrisboisSan Diego, Calif. (October 28, 2021) - San Diego Appellate Practice Partners Jeffry A. Miller and Corinne C. Bertsche, along with Associate Tracy D. Forbath, recently obtained a win on appeal when California's Court of Appeal for the Second Appellate District, Division Four affirmed the trial court’s grant of a client homeowners association’s motion for summary judgment. In the underlying matter, the plaintiff alleged claims for premises liability and negligence for injuries he sustained when tripping over an uplift of two misaligned adjacent slabs of concrete sidewalk, measuring 1.25 inches and located next to a condominium complex.
The appellate court agreed that the defect in question was a trivial defect as a matter of law, despite the plaintiff’s arguments that there was a triable issue of material fact as to whether the uplift’s dangerousness was exacerbated by the presence of aggravating factors. The appellate court found that the plaintiff’s expert declaration did not support the alleged aggravating factors with admissible evidence, and that the trial court did not abuse its discretion in excluding it.
Reprinted courtesy of
Corinne Bertsche, Lewis Brisbois,
Jeffry Miller, Lewis Brisbois and
Tracy Forbath, Lewis Brisbois
Ms. Bertsche may be contacted at Corinne.Bertsche@lewisbrisbois.com
Mr. Miller may be contacted at Jeff.Miller@lewisbrisbois.com
Ms. Forbath may be contacted at Tracy.Forbath@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Beware of Personal-Liability Clauses – Even When Signing in Your Representative Capacity
January 31, 2018 —
David R. Cook Jr. – Autry, Hall & Cook, LLPWhen a contract is drafted by a party, the other party expects some level of one-sidedness in favor of the drafter. But there are times when a contract goes too far. There are certain provisions that most persons in the construction industry would find unacceptable, unfair, and beyond the pale – even for a one-sided contract. Such a provision was arguably found in an electrical subcontract at issue in a 2014 opinion by a three-judge panel of the Georgia Court of Appeals. Unfortunately, due to long-standing Georgia law, the panel was forced to apply the provision as written.
In the case, a contractor hired a subcontractor to perform the electrical scope of work. When the subcontractor failed to pay a sub-subcontractor, the sub-subcontractor filed suit against the subcontractor, contractor, and the payment-bond surety. The contractor asserted a claim of indemnity against the subcontractor based on the sub-subcontractor’s claim.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Quick Note: Attorney’s Fees and the Significant Issues Test
November 03, 2016 —
David Adelstein – Florida Construction Legal UpdatesAttorney’s fees become a component of damages that parties seek to recover whenever there is a contractual or statutory basis for them to recover their fees. Parties want to be able to recover all or substantially most of the attorney’s fees they incurred in pursuing their claim. (In my experience, recovering all of the fees incurred is very challenging.) But, to be entitled to attorney’s fees, a party has to be deemed the
prevailing party. There is the sentiment that as long as you recover a positive net judgment (even if it is for $100 when your claim was for $50,000) then you will be able to recover your attorney’s fees which will likely exceed the amount that was ever in dispute.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Building and Landscape Standards Enacted in Response to the Governor's Mandatory Water Restrictions Dealing with the Drought and Possible Effects of El Niño
January 06, 2016 —
Clayton T. Tanaka – Newmeyer & Dillion, LLPEarlier this year, with California facing one of the most severe droughts on record, Governor Edmund G. Brown, Jr. issued Executive Order B-29-15 (the “Executive Order”) aimed at conserving water supplies and reducing water waste throughout the State of California. For the first time in California’s history, this Executive Order directed state agencies to implement immediate measures to save water, increase enforcement against water waste, invest in new technologies, and streamline government response to ongoing drought conditions.
In response, various state agencies proposed emergency changes to existing building and landscape standards in the California Green Building Standards Code (California Code of Regulations, title 24, part 11) (“CALGreen”) and the Model Water Efficient Landscape Ordinance (California Code of Regulations, title 23, part 11) (“Model Ordinance”) pertaining to the use of potable water. In July, the California Building Standards Commission and the California Water Commission adopted the proposed changes after public review and comment.
Read the court decisionRead the full story...Reprinted courtesy of
Clayton T. Tanaka, Newmeyer & Dillion, LLPMr. Tanaka may be contacted at
clay.tanaka@ndlf.com
Feds Outline Workforce Rules for $39B in Chip Plant Funding
April 10, 2023 —
James Leggate - Engineering News-RecordSemiconductor chip producers must pay their construction workforce prevailing wages and will be “strongly encouraged” to use project labor agreements if they want a piece of the $39 billion available in federal funding to support fabrication plant construction, expansion or modernization projects, U.S. Commerce Secretary Gina Raimondo says.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
It’s Not What You Were Thinking!
December 10, 2024 —
Daniel Lund III - LexologyAt least it is not what the lower court was thinking… but the same result for a general contractor seeking to have its comprehensive general liability insurer pay the GC’s defense related to claims for physical damage on a construction project.
In reviewing the Massachusetts federal district court’s ruling in favor of the insurer, the United States First Circuit Court of Appeals posited: “The principal question is whether a general contractor’s CGL insurance policy covers damage to a non-defective part of the contractor’s project resulting from a subcontractor’s defective work on a different part of that project.”
The district court had held under Massachusetts law that the insurer had no duty to defend because the lawsuit “did not allege ‘property damage’ caused by an ‘ occurrence,’ as required for coverage” under the policy (a defense that was urged by the insurer). The Court of Appeals affirmed, “albeit for different reasons.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Grupo Mexico Spill Sparks Public Scrutiny of $150 Million Mop-Up
September 17, 2014 —
Nacha Cattan – BloombergMexico is sending federal officials to Sonora state to oversee Grupo Mexico SAB (GMEXICOB)’s $150 million cleanup of a copper mine spill that the government says contaminated the water supplies of at least 24,000 people.
The special commission of environmental and agriculture ministry officials will monitor the company’s pledge to clean Mexico’s worst mining spill, which occurred Aug. 6 in the northern state that borders Arizona.
Grupo Mexico said last week it would create a $150 million trust after its Buenavista del Cobre operation dumped 11 million gallons of copper sulfate solution into two Sonora rivers. Industrias Bachoco SAB de CV and Ford Motor Co. (F) operate plants in Hermosillo, south of the contaminated waterways.
Read the court decisionRead the full story...Reprinted courtesy of
Nacha Cattan, BloombergMs. Cattan may be contacted at
ncattan@bloomberg.net