No Coverage Under Installation Policy When Read Together with Insurance Application
January 16, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent case out of the Eleventh Circuit denied an underground contractor’s claim under what appears to be a commercial property installation floater policy (inland marine coverage) that covers the contractor’s materials. Whereas a builder’s risk policy is more expansive, an installation floater is narrower and can provide protection to a contractor for materials and equipment in transit, stored, or being installed subject to the terms of the installation floater policy. It can provide coverage to a trade subcontractor for materials that aren’t covered by builder’s risk.
In Travelers Property Casualty Company of America v. Talcon Group, LLC, 2023 WL 8798053 (11th Cir. 2023), an underground utility contractor that had a general contractor’s license had an installation policy that provided coverage “only for underground utility operations and the site development work tied to those operations.” Talcon Group, supra, at *1. The utility contractor was constructing two residential homes that was on land owned by an affiliated family entity. During construction of the residential homes, a wildfire destroyed the homes prior to the issuance of certificates of occupancy. The utility contractor submitted a notice of loss to its insurance carrier that provided the installation policy. The carrier denied the claim because the construction of the homes was NOT the same type of work as the installation of underground utilities which was covered. An insurance coverage lawsuit ensued.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Prime Contractor & Surety’s Recovery of Attorney’s Fees in Miller Act Lawsuit
February 02, 2017 —
David Adelstein - Florida Construction Legal UpdatesCan a claimant recover attorney’s fees in a Miller Act payment bond dispute even though the Miller Act does not contain a prevailing party attorney’s fee provision? Yes, if the underlying contract that formed the basis of the suit provided for attorney’s fees.
What about a prime contractor and surety—can they recover their attorney’s fees if they prevail in a Miller Act payment bond claim and the underlying contract provides a basis for fees? The Eleventh Circuit Court of Appeals in U.S.A. f/u/b/o RMP Capital Corp. v. Turner Construction Co., 2017 WL 244066 (11th Cir. 2017) seemingly just answered this question in the affirmative when it reversed a lower court’s ruling that precluded a prime contractor and surety that prevailed in a Miller Act claim from recovering their attorney’s fees[.]
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Build, Baby, Build. But Not Like This, Britain.
March 04, 2024 —
Matthew Brooker - BloombergThe UK needs to do a lot more building. A lack of access to physical and digital connections is holding back the economy, the government says. Besides tackling the housing crisis, the country has to construct more roads, railways, wind farms and reservoirs to open up opportunity and drive productivity. The only problem is that Britain is notoriously inept at delivering infrastructure projects on time and within budget.
The advantage of doing things badly is that at least you get to learn from your mistakes — in theory. Updates this month have offered some illuminating insights into two of the biggest civil-engineering undertakings in the country: High-Speed Rail 2, better known as HS2, and Hinkley Point C, which will be Britain’s first new nuclear power station since 1995. Here are five lessons that can be drawn from the issues encountered by two projects with a combined bill that’s likely to exceed £100 billion ($127 billion):
Don't take budgets too seriously — especially at the start. Fixing an initial budget that was too low may have done much to feed later perceptions that HS2’s costs were spiraling out of control. The original estimate for the expanded train network was set too early and based on “very immature data,” Jon Thompson, appointed executive chair of High Speed 2 Ltd. in February last year, told the House of Commons transport committee. Numbers get more accurate and reliable as work progresses and the quality of information improves. What were viewed as cost blowouts partly reflected this process. The effect was unfortunate, undermining political support for HS2 and providing cover for cutbacks that have reduced the network to a single line between London and Birmingham that fails to fulfill most of its original purpose. To avoid this problem: Stick to a range rather than a single figure, and make sure people understand the uncertainties inherent in early-stage estimates.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew Brooker, Bloomberg
The Condominium Warranty Against Structural Defects in the District of Columbia
September 07, 2017 —
Nicholas D. Cowie - Maryland Condo Construction Defect Law BlogThe District of Columbia Condominium Act contains a statutory warranty that protects condominium associations and their unit owner members from structural defects in newly constructed and newly converted condominiums. The warranty is backed by a condominium developer’s bond, letter of credit, or other form of security from which monies can be drawn upon if the developer fails to make warranty repairs.
This article discusses how the warranty against structural defect works and how to make claims against the developer’s security to fund warranty repairs.
THE CONDOMINIUM WARRANTY AGAINST STRUCTURAL DEFECTS
Condominium developers in Washington DC are required by statute to warrant against structural defects in the condominium common elements and each condominium unit. District of Columbia Condominium Act (“DC Condo Act”) 42-1903.16(b).
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas D. Cowie, Cowie & Mott, P.A.Mr. Cowie may be contacted at
ndc@cowiemott.com
It Has Started: Supply-Chain, Warehouse and Retail Workers of Essential Businesses Are Filing Suit
June 22, 2020 —
Robert G. Devine, James Burger & Douglas Weck - White and Williams LLPSupply-chain businesses that are appropriately characterized as “essential” have remained open for the delivery of critical supplies while everyone else has been told to close up shop and stay home. Now essential-business employees are contracting COVID-19 and filing suit. Following up on our earlier piece — “Is a Violation of a COVID-19 Order the Basis For Civil Liability?” — it is important to recognize that government directives, oftentimes couched as “recommendations,” can come to define what it means to provide a reasonably safe workplace that protects employees from COVID-19. While common law negligence defenses consider the reasonableness of conduct, these directives will likely become the standard.
The cases that have been filed are overwhelmingly premised upon the timeless negligence construct. The negligence construct, simply put, imposes a duty to act as a reasonable person would under the circumstances. Nonetheless, while the negligence construct lives in the ordinary world of “reasonableness,” infection-control guidance lives in the rapidly developing world of the science of COVID-19. Guidance on seemingly basic questions, such as the methods of transmission (e.g., personal contact, mucus membrane only, airborne transmission) or even the virus’s shelf life on different surfaces, of particular interest packaging and material handling equipment, can change by the day. All of this provides challenges for the supply-side business looking to protect its workforce.
Reprinted courtesy of White and Williams LLP attorneys
James Burger,
Robert Devine and
Douglas Weck
Mr. Burger may be contacted at burgerj@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Weck may be contacted at weckd@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Be Careful with “Green” Construction
March 18, 2019 —
Christopher G. Hill - Construction Law MusingsAs readers of Construction Law Musings can attest, I am an enthusiastic (if at times skeptical) supporter of sustainable (or “green”) building. I am solidly behind the environmental and other benefits of this type of construction. However, I have likened myself to that loveable donkey Eeyore on more than one occasion when discussing the headlong charge to a sustainable future. While I see the great benefits of a privately built and privately driven marketplace for sustainable (I prefer this term to “green” because I find it less ambiguous) building stock and retrofits of existing construction, I have felt for a while that the glory of the goal has blinded us somewhat to the risks and the need to consider these risks as we move forward.
Another example reared it’s ugly head recently and was pointed out by my pal Doug Reiser (@douglasreiser) at his Builders Counsel Blog (a great read by the way). Doug describes a project that I mentioned previously here at Musings and that is well described in his blog and in a recent newsletter from Stuart Kaplow (@stuartkaplow), namely, the Chesapeake Bay Foundation’s Philip Merrill Environmental Center project. I commend Doug’s post for a great description of the issues, but suffice it to say that the Chesapeake Bay Foundation sued Weyerhauser over some issues with a sustainable wood product that failed. While the case was dismissed on statute of limitations grounds, the case illustrates issues that arise in the “new” sustainable building world.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Quick Note: Mitigation of Damages in Contract Cases
October 02, 2018 —
David Adelstein - Florida Construction Legal UpdatesIn an earlier article, I discussed an owner’s measure of damages when a contractor breaches the construction contract. This article discussed a case where the contractor elected to walk off a residential renovation job due to a payment dispute when he demanded more money and the owners did not bite. This case also discussed the commonly asserted defense known as mitigation of damages, i.e., the other party failed to properly mitigate their own damages.
In the breach of contract setting, mitigation of damages refers to those damages the other side could have reasonably avoided had he undertaken certain (reasonable) measures. This is known as the doctrine of avoidable consequences.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Traub Lieberman Attorneys Recognized as 2022 New York – Metro Super Lawyers®
October 17, 2022 —
Traub LiebermanTraub Lieberman is pleased to announce that seven Partners from the Hawthorne, NY Office have been selected to the 2022 New York - Metro Super Lawyers list.
2022 New York – Metro Super Lawyers
- Copernicus Gaza – Insurance Coverage
- Jonathan Harwood – Professional Liability
- Lisa Rolle – Construction Litigation
- Christopher Russo – Professional Liability
- Lisa Shrewsberry – Professional Liability
- Stephen Straus – Insurance Coverage
- Richard Traub – Insurance Coverage
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman