Insureds Survive Motion to Dismiss Civil Authority Claim
September 29, 2021 —
Tred R. Eyerly - Insurance Law HawaiiAfter suffering business losses due to a hurricane, the insured's Civil Authority claim survived the insurer's motion to dismiss. Pathology Lab. v. Mt. Hawley Ins. Co., 2021 U.S. Dist. LEXIS 145129 (W.D. La. Aug. 3, 2021).
Hurricane Laura devastated Lake Charles, Louisiana causing severe damage to the insured property as well as other properties within a mile of the insured property. All seven electrical transmission line corridors feeding Lake Charles were catastrophically damaged causing an extensive power outage. Government shutdown Orders prohibited the insureds' access to the Lab. The Orders were issued by the respective civil authorities both in anticipation of and as a result of damage and dangerous physical conditions expected from and actually resulting from Hurricane Laura and the continuation thereof. When the hurricane arrived, all businesses that were not essential to the recovery were ordered closed until electricity, water and sewer services were restored. As a result, the Lab was closed from August 27, 2020 toSeptember 8, 2020.
The Lab sued for business income under the policy's Civil Authority provisions. Mt. Hawley moved to dismiss. Mt. Hawley argued that the Orders did not by their explicit terms close the Lab's business because closure was entirely dependent on the conditions of the described premises itself and whether it was safe to occupy. Mt. Hawley further argued that the mandatory Evacuation Order was issued in anticipation of property damage and therefore did not trigger coverage under the Civil Authority provision.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Build, Baby, Build. But Not Like This, Britain.
March 04, 2024 —
Matthew Brooker - BloombergThe UK needs to do a lot more building. A lack of access to physical and digital connections is holding back the economy, the government says. Besides tackling the housing crisis, the country has to construct more roads, railways, wind farms and reservoirs to open up opportunity and drive productivity. The only problem is that Britain is notoriously inept at delivering infrastructure projects on time and within budget.
The advantage of doing things badly is that at least you get to learn from your mistakes — in theory. Updates this month have offered some illuminating insights into two of the biggest civil-engineering undertakings in the country: High-Speed Rail 2, better known as HS2, and Hinkley Point C, which will be Britain’s first new nuclear power station since 1995. Here are five lessons that can be drawn from the issues encountered by two projects with a combined bill that’s likely to exceed £100 billion ($127 billion):
Don't take budgets too seriously — especially at the start. Fixing an initial budget that was too low may have done much to feed later perceptions that HS2’s costs were spiraling out of control. The original estimate for the expanded train network was set too early and based on “very immature data,” Jon Thompson, appointed executive chair of High Speed 2 Ltd. in February last year, told the House of Commons transport committee. Numbers get more accurate and reliable as work progresses and the quality of information improves. What were viewed as cost blowouts partly reflected this process. The effect was unfortunate, undermining political support for HS2 and providing cover for cutbacks that have reduced the network to a single line between London and Birmingham that fails to fulfill most of its original purpose. To avoid this problem: Stick to a range rather than a single figure, and make sure people understand the uncertainties inherent in early-stage estimates.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew Brooker, Bloomberg
Flood Sublimits Do Not Apply to Loss Caused by Named Windstorm
May 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe New Jersey Superior Court considered whether recovery for storm surge was limited by the policy's sublimit for loss caused by flood. Public Serv. Enter. Group, Inc. v. Ace Am. Ins. Co., 2015 N. J. Super. Unpub. LEXIS 620 (N.J. Super. Ct. Law Div. March 23, 2015).
Storm surge from Superstorm Sandy inundated and damaged Public Service Enterprise Group, Inc.'s (PSEG) property, including eight large generating stations. PSEG had coverage of $1 billion under policies with defendant carriers. There was no sublimit in the policies for "named windstorms," other than named windstorms in Florida. A $250 million sublimit appeared in the policies for losses caused by "flood."
The carriers paid only a portion of PSEG's claim. The total damages exceeded $500 million.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Landmark Montana Supreme Court Decision Series: The Duty to Defend
February 28, 2022 —
Lorelie S. Masters, Patrick M. McDermott & Rachel E. Hudgins - Hunton Insurance Recovery BlogThis post in our
Landmark Montana Supreme Court Decision Series discusses the Montana Supreme Court’s consideration of an insurer’s duty to defend in
National Indemnity Co. v. State, 499 P.3d 516 (Mont. 2021).
For 67 years, W.R. Grace & Company’s mining operations spread asbestos through the town of Libby, Montana,
causing elevated rates of asbestosis and asbestos-related cancer in Libby residents – even among those who never worked in the mine. The Environmental Protection Agency deemed the Libby Mine the
“most significant single source of asbestos exposure” in US history.
In 2000, Libby residents began filing lawsuits against the State of Montana, alleging that the State had failed to warn them about the mine’s danger, and this failure contributed to their bodily injuries. Id. at 521-22. The Libby plaintiffs’ asbestos exposures and related injuries had occurred decades earlier, and so the State searched its storage units for records of any potentially applicable insurance policies.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth,
Patrick M. McDermott, Hunton Andrews Kurth and
Rachel E. Hudgins, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. McDermott may be contacted at pmcdermott@HuntonAK.com
Ms. Hudgins may be contacted at rhudgins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (5/1/24) – IMF’s Data on Housing, REITs Versus Private Real Estate, and Suburban Versus Urban Office Property Market
May 28, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, apartment sales fall for seventh straight quarter, raising real estate capital proves challenging, aspiring homeowners face strong obstacles, and more!
- Rent increases have softened across the U.S. over the last year, and the combination of high home prices, elevated mortgage rates and low housing inventory creates strong obstacles for aspiring homeowners. (Alex Gailey, Bankrate)
- The housing market is showing innovative efforts to combat the inventory crisis with initiatives including repurposing commercial properties into residential units. (Angel Smith, Yahoo)
- Apartment sales fell for the seventh straight quarter in Q1, dropping 25% year over year to $20.6 billion. (Leslie Shaver, Multifamily Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Hawaii Federal District Court Denies Title Insurer's Motion for Summary Judgment
February 01, 2022 —
Tred R. Eyerly - Insurance Law HawaiiIn a rare title insurance dispute before the federal district court in Hawaii, the court denied the insurer's motion for summary judgment while granting the insured's motion for summary judgment. First Am. Title Ins. Co. v. GS Industries, LLC, 2021 U.S. Dist. LEXIS 240601 (D. Haw. Dec. 16, 2021).
GS Industries, LLC took ownership of a parcel of real property located fronting Waipa Lane in Honolulu. The property used four buildings and a parking area for 50 cars. GS obtained a title insurance policy from First American. The policy insured GS' fee simple interest in the property in the amount of $3,500,000. The policy insured GS "against loss or damage, not exceeding $3,500,000, sustained or incurred by GS by reason of . . . not right of access to and from the land,." The policy did not identify any issues with access to the property and did not define "access."
A portion of Waipa Lane was owned by the City and County of Honolulu. Parcel 86 and Parcel 91 on Waipa Lane were privately owned. (Private Waipa Lane Parcels). Vehicular access to (ingress) and from (egress) the property was via Waipa Lane. Ingress was made via the publicly owned portion of Waipa Lane. Vehicular egress was made via the Private Waipa Lane Parcels. The City of Honolulu maintained the Private Waipa Lane Parcels and considered them to be pubic. None of the owners of Parcels 86 or 91 notified GS of their intent to block the use of Waipa Lane.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Update: Where Did That Punch List Term Come From Anyway?
December 21, 2016 —
Duane Craig – Construction InformerI’ve often wondered just where the term “punch list” came from, and I’ve found a few sources that seem to make sense, while others not so much.
Enter the Realm of Conjecture and Opinion
One person claims it came from the telephone installer process of “punching down” terminals on a block. That seems a bit of a stretch though. A blog writer said it had to do with the term ‘punch’ since it means to “punch something up” as in fix it.
Another blog writer thought it had something to do with a long forgotten practice. Apparently subcontractors used to each have their own hole punches that would punch a hole with a shape unique to them. They would use these punches to indicate they had corrected the deficiency that was their responsibility.
Read the court decisionRead the full story...Reprinted courtesy of
Duane Craig, Construction InformerMr. Craig may be contacted at
dtcraig@constructioninformer.com
Indiana Court of Appeals Rules Against Contractor and Performance Bond Surety on Contractor's Differing Site Conditions Claim
April 03, 2013 —
Brian M. Falcon - Frost Brown Todd LLCEarlier this year, the Indiana Court of Appeals issued an important opinion that impacts contractors and sureties alike. The decision should give contractors in Indiana pause before ceasing work while a dispute with the owner is pending. Sureties also have been placed on notice that strict compliance with the terms of their bonds is amongst their best defenses to claims made by owners and bond claimants.
In Dave's Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana, 959 N.E.2d 369 (Ind. Ct. App. 2012), the contractor (“Dave’s”) was the successful bidder on a public sanitary sewer and water main extension project. Dave's procured a performance bond from Liberty Mutual to guarantee its performance obligations to the owner (the "City"). After encountering what it deemed different subsurface conditions—and indeed after having been previously granted a change order to use excavated materials as backfill in light of the subsurface conditions on site—Dave’s placed the project engineer on notice of a differing site conditions claim. The total claim amounted to an 84% increase in the total contract price. With the claim, Dave's advised the project engineer it was ceasing further work until the project engineer provided direction.
While the project engineer reviewed the claim, it reminded Dave's of its contractual obligation to "carry on the work and adhere to the progress schedule during all disputes or disagreements with the OWNER." A dispute immediately occurred regarding whether Dave's was required to continue to work while the project engineer resolved the differing site condition claim. After Dave's maintained its position that it was not required to continue to work, the project engineer placed it on notice of default and copied the letter to Liberty Mutual.
Read the court decisionRead the full story...Reprinted courtesy of
Brian M. FalconBrian M. Falcon can be contacted at http://www.frostbrowntodd.com/contact.html