Will Claims By Contractors on Big Design-Build Projects Ever End?
February 27, 2023 —
Richard Korman - Engineering News-RecordIn the annals of construction disputes, it is a blip, not a blast.
After a Flatiron Construction-Zachry Group joint venture struck out on most of its arbitrated claims against engineering firm partners on the I-85/385 design-build interchange project in Greenville, S.C., and had others dismissed in court, the contractors had one more source from which to try to cover unexpected project costs: a contractor protective professional policy. Flatiron-Zachry filed a lawsuit last October in San Antonio federal court to try to force payment from Steadfast, a subsidiary of Zurich American Insurance Co.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
While Construction Permits Slowly Rise, Construction Starts and Completions in California Are Stagnant
December 05, 2022 —
John Kazanovicz & Jason Feld - Kahana FeldThere is an interesting phenomenon happening in the California construction market since the Summer of 2022. There is a steady but slow rise in the construction building permits being issued throughout California. According to the U.S. Census and the U.S. Department of Housing and Urban Development’s joint announcement (https://www.census.gov/construction/nrc/pdf/newresconst.pdf) of new residential construction statistics for September 2022, privately‐owned housing units authorized by building permits in September were at a seasonally adjusted annual rate of 1,564,000. This is 1.4 percent above the revised August rate of 1,542,000. While this is slightly lower than a year ago (3.2 percent below the September 2021 rate of 1,615,000), the trend for obtaining new home permits was reportedly ahead of the projected rates given the market conditions and inflation throughout the country. Interestingly, single‐family authorizations in September were at a rate of 872,000 which was also 3.1 percent below the revised August 2022 figure of 900,000. Authorizations of units in buildings with five units or more were at a rate of 644,000 in September. Overall, while slowly recovering from the record lows during the height of the pandemic, the economic forecast for new home construction in California is positive, but cautious.
The flip side of this coin is the construction starts in California, which continue to remain stagnant despite additional building permits being issued. Privately‐owned housing starts in September were at a seasonally adjusted annual rate of 1,439,000. This is 8.1 percent (±14.9 percent) below the revised August estimate of 1,566,000 and is 7.7 percent (±11.5 percent) below the September 2021 rate of 1,559,000. Single‐family housing starts in September were at a rate of 892,000; this is 4.7 percent (±10.7 percent) below the revised August figure of 936,000. The September rate for units in buildings with five units or more was 530,000.
Reprinted courtesy of
John Kazanovicz, Kahana Feld and
Jason Feld, Kahana Feld
Mr. Kazanovicz may be contacted at jkazanovicz@kahanafeld.com
Mr. Feld may be contacted at jfeld@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Vallagio v. Metropolitan Homes: Colorado Supreme Court Upholds Declarant Consent Provision to Amend Arbitration Out of Declarations
June 15, 2017 —
Jean Meyer - Colorado Construction LitigationOn June 5, 2017, the Colorado Supreme Court announced the Vallagio at Inverness Residential Con. Ass’n v. Metro. Homes, Inc., No. 15SC508, 2017 CO 69 (Colo. June 5, 2017) decision. In short, the Colorado Supreme Court upheld the validity of declarant “consent-to-amend” provisions and expressly held that claims under the Colorado Consumer Protection Act are arbitrable.
By way of background, the Vallagio at Inverness Residential Condominiums were developed by Metro Inverness, LLC, (“Declarant”) which also served as the declarant for its homeowners association. Metropolitan Homes was Metro Inverness’ manager and the general contractor on the project. Greg Krause and Peter Kudla served as declarant-appointed members of the Association’s board during the period of declarant control.
When it set up the Association, the Declarant included within the Association’s declaration a mandatory arbitration provision specifically for construction defect claims. This provision stated that it “shall not ever be amended without the written consent of Declarant and without regard to whether Declarant owns any portion of the Real Estate at the time of the amendment.”
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
Forcible Entry and Detainer Actions: Courts May Not Consider Tenant’s Hardship
December 08, 2016 —
Erica Stutman – Snell & Wilmer Real Estate Litigation BlogIf you own property and a tenant wrongfully refuses to vacate the premises (for example when the lease expires or after proper written notice of termination), you may have a quick and easy remedy to have the tenant removed. Arizona’s forcible entry and detainer (FED) statute allows a person to bring a speedy, summary action to obtain an order that the person must leave the property immediately. See A.R.S. § 12-1171 – 1183. To allow for quick resolution, the only question a court may consider in a FED action is who has the right of possession of the property. A.R.S. § 12-1177(A) (“On the trial of an action of forcible entry or forcible detainer, the only issue shall be the right of actual possession and the merits of title shall not be inquired into.”). Counterclaims and cross-claims are not permitted in a FED action, and must be addressed in a separate civil action between the parties. If factual questions bear on the right of possession, they will also need to be resolved in a regular civil action.
Read the court decisionRead the full story...Reprinted courtesy of
Erica Stutman, Snell & Wilmer Ms. Stutman may be contacted at
estutman@swlaw.com
Texas Public Procurements: What Changed on September 1, 2017? a/k/a: When is the Use of E-Verify Required?
October 11, 2017 —
Timothy D. Matheny – Peckar & Abramson, P.C.Every contractor that does business with the federal government is familiar with the requirement to use of E-Verify in order to document the employability of a contractor’s employees. But, when is a contractor required to use E-Verify in Texas? And, does this requirement to use E-Verify extend to the contractor’s subcontractors? All contractors and each of their subcontractors will be required to use E-Verify for a variety of goods and services contracts with state agencies. Failure to understand these requirements could lead to your company losing out on the award of the next Texas public procurement contract.
Read the court decisionRead the full story...Reprinted courtesy of
Timothy D. Matheny, Peckar & Abramson, P.C.Mr. Matheny may be contacted at
tmatheny@pecklaw.com
Owners Should Serve Request for Sworn Statement of Account on Lienor
August 10, 2017 —
David Adelstein - Florida Construction Legal UpdatesWhen an owner receives a construction lien, an owner should serve the lienor with a Request for Sworn Statement of Account. The Request for Sworn Statement is authorized by Florida Statute s. 713.16(2) and should be in the following form:
REQUEST FOR SWORN STATEMENT OF ACCOUNT
WARNING: YOUR FAILURE TO FURNISH THE REQUESTED STATEMENT, SIGNED UNDER OATH, WITHIN 30 DAYS OR THE FURNISHING OF A FALSE STATEMENT WILL RESULT IN THE LOSS OF YOUR LIEN.
To: (Lienor’s name and address)
The undersigned hereby demands a written statement under oath of his or her account showing the nature of the labor or services performed and to be performed, if any, the materials furnished, the materials to be furnished, if known, the amount paid on account to date, the amount due, and the amount to become due, if known, as of the date of the statement for the improvement of real property identified as (property description) .
(name of contractor)
(name of the lienor’s customer, as set forth in the lienor’s Notice to Owner, if such notice has been served)
(signature and address of owner)
(date of request for sworn statement of account)
From both an owner and lienor’s perspective, the bolded, capitalized language is key. It states that if the lienor fails to respond under oath within 30 days, it will LOSE its lien. That is a very punitive measure for a lienor’s failure to respond, meaning a lienor should absolutely respond, no questions asked. Plus, a lienor’s response to a Request for Sworn Statement of Account is not a burdensome ordeal.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Who is Responsible for Construction Defect Repairs?
August 24, 2017 —
Laura Parsons-CDJ STAFFAn appellate court has ruled that the sponsor and not the condo board is responsible for repairing construction defects at 50 Madison Avenue, a multi-story apartment building in New York City across from Madison Square Park, Habitat reported. Plaintiff’s Simon and Ludmilla Lorne have brought upon three lawsuits in a legal battle lasting a decade.
The first came in 2007, two years after the Lorne’s purchased their $3 million seventh-floor apartment. At that time, the sponsor offered to repair the concrete slab under the hardwood floors that had not been properly leveled. However, the Lorne’s and the condo board disagreed about who and how the repairs would be accomplished. The second lawsuit wherein the court ruled that repairing the construction defects was the responsibility of the sponsor occurred in 2009. However, the Lorne’s sued the board yet again in 2015, citing failure to maintain and repair the building. Since the 2015 suit was based on the same allegations as the 2007 suit, it was dismissed by the judge.
Read the court decisionRead the full story...Reprinted courtesy of
Reasonableness of Denial of Requests for Admission Based Upon Expert’s Opinions Depends On Factors Within Party’s Understanding
February 27, 2019 —
Stephen M. Tye & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPIn Orange County Water District v. The Arnold Engineering Company (D070763), the Fourth Appellate District examined the criteria for evaluating the reasonableness of a parties’ denial of requests for admission (RFA’s) based upon their expert’s opinions and the proof required to recover costs for unreasonable denials.
In Orange County Water District, the Orange County Water District (the District) sued several current and former owners and operators of industrial sites, including The Arnold Engineering Company (Arnold), to recover expenses associated with groundwater cleanup efforts intended to address groundwater contamination caused by volatile organic compounds (VOC’s) and other chemicals. Over six years, the parties conducted extensive discovery, including document productions, depositions, and soil sampling and monitoring.
Reprinted courtesy of
Stephen M. Tye, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Mr. Tye may be contacted at stye@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of