Fundamental Fairness Trumps Contract Language
September 24, 2014 —
Craig Martin – Construction Contractor AdvisorThe Texas Supreme Court recently ruled that a “no-damages-for-delay” clause would not be enforced where the delay was caused by the owner. The court’s ruling flies squarely in the face of the contract language that attempted to insulate the owner from any delay claims, even those it caused.
In the case of Zachary Construction v. Port of Houston underlying contract, proposed by the Port of Houston, was heavy handed, to say the least. The contract provided:
“[Contractor] shall receive no financial compensation for delay or hindrance to the Work. In no event shall the Port Authority be liable to [Contractor] … for any damages arising out of or associated with any delay or hindrance to the Work, regardless of the source of the delay or hindrance, including events of Force Majeure, AND EVEN IF SUCH DELAY OR HINDRANCE RESULTS FROM, ARISES OUT OF OR IS DUE IN WHOLE OR IN PART, TO THE NEGLIGENCE, BREACH OF CONTRACT OR OTHER FAULT OF THE PORT AUTHORITY. [Contractor’s] sole remedy in any such case shall be an extension of time.”
Wow, that’s some one-sided language. If the contract was enforced, the contractor could not get any damages for delay, even those damages caused by the active interference of the Port of Houston.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Subcontractors Have a Duty to Clarify Ambiguities in Bid Documents
August 19, 2015 —
Craig Martin – Construction Contractor AdvisorSeveral months ago, I wrote about an escalator subcontractor that sued a general contractor, demanding payment for work completed based on approved shop drawings. The trial court agreed with the subcontractor, but the general contractor appealed. Ten months later, the Court of Appeals reversed, finding that the subcontractor had a duty to bring to the general contractor’s attention major discrepancies or errors they detect in the bid documents.
“The subcontractor failed to disclose ambiguities in the plans and must suffer the peril.”
Construction Difficulties
The subcontractor installed 32 inch escalators throughout the project, but the plans called for 40 inch escalators. The general contractor and subcontractor could not reach agreement on how the dispute should be resolved. The subcontractor sued the general to get paid for replacing the escalators and the general sued to subcontractor for concessions it had to pay to the owner.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Ninth Circuit Holds Efficient Proximate Cause Doctrine Applies Beyond All-Risk Policies
April 20, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Ninth Circuit held that the efficient proximate cause doctrine is not limited to all-risk policies. Olin Corp. v. Continental Cas. Co., 2016 U.S. App. LEXIS 4905 (9th Cir. March 17, 2016).
Olin operated a plant that produced industrial chemicals. Continental issued a policy covering the plant's boilers and machinery. In late 2008, the machinery was damaged. Continental denied coverage for damage to Olin's diaphragm cells, which were tanks containing metal cathodes covered by asbestos diaphragms. Continental argued that the damage to the cells was not covered because it was not caused by an "accident." The jury returned a verdict in favor of Olin.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Techniques for Resolving Construction Disputes
September 16, 2019 —
Jason Lambert - Construction ExecutiveWith most construction projects involving dozens, if not hundreds, of companies and individuals, it is no surprise that conflicts arise that are not always able to be resolved on the jobsite. But these conflicts need not always reach the court room or cost thousands (or much more) to resolve. With some planning, contractors can build faster and less expensive dispute resolution options into their project so they can spend more time keeping the project moving and less time arguing over who is right.
Even for modest-sized projects, a multi-tiered approached to dispute resolution can be helpful. As a first level of dispute resolution, consider requiring the relevant parties to attend informal or formal mediation. The benefits of even an informal mediation is that it can get stalemated parties to the table to talk again. Formal mediation adds the benefit of a neutral third-party who can help get talks moving or help antagonistic parties communicate.
Further, mediation allows each side an opportunity to hear what the other side is looking for to resolve the dispute. Not only is this valuable in reaching a compromise, but it also gives each side an idea of what the other will bring to the table in any subsequent litigation. Finally, there are many ways to implement these procedures. General contractors can require pre-suit mediation with their subcontractors to resolve one-on-one disputes but should also consider requiring subcontractors to use pre-suit mediation to resolve disputes between subcontractors or between subcontractors and sub-subcontractors or material suppliers if the dispute threatens the progress at the project.
Reprinted courtesy of
Jason Lambert, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
4 Lessons Contractors Can Learn From The COVID-19 Crisis
May 25, 2020 —
Patrick Hogan - Handle.comAt the start of 2020, the industry outlook in construction was positive. Many contractors were optimistic about what the year had in store for construction businesses in terms of profit, expansion of operations, and even payment issues. That was until the COVID-19 pandemic put a wrench in everyone’s business plans.
There’s no question about how huge the impact of the novel coronavirus crisis is on business operations. With the federal and state governments implementing strict measures to slow down the spread of COVID-19, construction businesses are experiencing significant delays and disruptions in their operations. Because of the lockdowns and stay-at-home orders, many construction projects are forced to postpone operations or, worse, cancel them altogether.
Nevertheless, there are lessons in the COVID-19 pandemic that contractors can learn. Here are some of them.
1. Contractors need to be proactive in meeting preliminary notice requirements
Cash is tight in times of crisis. As the economy comes to a standstill, construction businesses will need to deal with decreasing profits. They may even have to dip into their own cash reserves to cover fixed expenses and their employees’ salaries.
In times like this, it is crucial that contractors perform due diligence in protecting their right to get paid. The first step in doing so is to prepare
preliminary notices. These notices are an important step in the mechanics lien process and without them, chances contractors will not be able to recover the unpaid compensation for the materials they furnished and services they rendered.
2. Force majeure provisions are crucial parts of a contract
The novel coronavirus pandemic has highlighted the importance of force majeure provisions in construction contracts. Before the COVID-19 crisis hit business operations, force majeure provisions were typically considered as simple boilerplate clauses. This means they were just there as a standard part of contracts.
However, the same force majeure clauses, as well as impossibility of performance provisions, have become crucial in the current crisis. As many construction businesses experience difficulties with their operations, they may not be able to fulfill their contractual responsibilities. The said clauses can give contractors a much-needed reprieve.
As the current crisis continues, contractors should review contracts as these provisions can give them more time to finish the job. And in the hopefully near future when the crisis ends, business owners should review the contract creation process and ensure that these clauses included in contracts will be able to address the impact of situations similar to COVID-19.
3. Having solid internal communication is crucial
There’s a lot of uncertainty with the COVID-19 situation. With work operations temporarily stopping, the circumstances can be quite stressful for employees. There will be doubts and fears within your workforce on whether work will be back to normal as soon as possible or not.
Keeping your workforce well-informed and trusting of your organization is crucial, especially in this time of uncertainty. That is why it is paramount that you have a solid internal communication infrastructure to disseminate information about the current work situation and the next steps that the business will take. In addition, only through proper employee communication can the implementation of social distancing and hygiene measures be effective.
4. Contractors can benefit from flexible work arrangements
As the coronavirus crisis has made it necessary for everyone to stay at home, construction businesses should look for ways to continue operations. Expanded work arrangements such as work-from-home setups may just be the solution.
Of course, most of the physical work that is needed to be done on-site will be impossible to do at home, but office-based functions such as sales, client relations, design, and administrative roles can still continue. This can even have additional benefits to productivity and health. And when the crisis is over, business owners should consider incorporating these work arrangements into their operations permanently.
The COVID-19 crisis is not showing any sign of stopping soon, and even when it ends, it will take quite a long time before we can be back to business as usual. As the crisis continues, however, business owners should take the situation as a learning experience.
Once the COVID-19 crisis is over, it will take a long time for things to go back to normal. In fact, things may not end up going back to the way they were before and businesses will need to adapt to the new normal. However the situation evolves, business owners should take this opportunity to learn new things and maintain resilience in trying times.
About the Author:
Patrick Hogan is the CEO of Handle.com, where they build software that helps contractors, subcontractors, and material suppliers with late payments. Handle.com also provides funding for construction businesses in the form of invoice factoring, material supply trade credit, and mechanics lien purchasing.
Read the court decisionRead the full story...Reprinted courtesy of
Breaking Down Homeowners Association Laws In California
April 03, 2019 —
Lauren Hickey - Bremer Whyte Brown & O'Meara LLPPurpose of HOAs
Property ownership often combines elements of individual and common ownership interests. For example, a property owner may individually own his or her living quarters, but also own a common interest in amenities that are considered too expensive for a single homeowner to purchase individually (such as a pool, gym, or trash collection service). Properties with such elements usually take the form of apartments, condominiums, planned developments, or stock cooperatives (together known as “common interest developments” or “CIDs”). Whenever a CID is built, California law requires the developer to organize a homeowner association (or “HOA), which can take several different names, including “community association”. Initially, the developer relies on the HOA to market the development to prospective buyers. Once each unit in the development is sold, management of the HOA is passed to a board of directors elected by the homeowners. At that point, the primary purpose of the HOA shifts to maintenance of common amenities and enforcement of community standards.
Dues/Assessments
HOAs generally charge each homeowner monthly or annual dues to cover the cost of their services. HOAs may also charge special assessments to cover large, abnormal expenses, such as the cost of upgrades or improvements. The amount charged in dues and assessments is established by the HOA’s board of directors, within the limits set by the HOA’s governing documents and California Civil Code section 1366. Section 1366 provides that HOA dues may not be increased by more than 20 percent of the amount set in the previous year, and the total amount of any special assessments charged in a given year generally may not exceed 5 percent of the HOA’s budgeted expenses.
Read the court decisionRead the full story...Reprinted courtesy of
Lauren Hickey, Bremer Whyte Brown & O'Meara LLP
A Landlord’s Guide to the Center for Disease Control’s Eviction Moratorium
October 05, 2020 —
Colton Addy - Snell & Wilmer Real Estate Litigation BlogThe Center for Disease Control and Prevention (the “CDC”) and the Department of Health and Human Services (the “HHS”) has issued an order to temporarily halt a landlord’s right to evict certain residential tenants to prevent the further spread of COVID-19 (the “CDC Order”).
The CDC Order is effective through December 31, 2020.
Applicability of the CDC Order. The CDC Order does not apply in jurisdictions that have a moratorium on residential evictions in effect that provides the same or greater level of protection than the CDC Order, and the CDC Order permits local jurisdictions to continue to pass more restrictive eviction moratoriums. To invoke the protection provided by the CDC Order, a landlord’s tenants must deliver an executed declaration (a “CDC Declaration”) form to the landlord that includes the following statements: (i) the tenant has used best efforts to obtain all available government assistance for rent or housing; (ii) expects to earn no more than $99,000 in annual income in 2020 (or $198,000 if filing joint tax returns), was not required to report income in 2019, or received an Economic Impact Payment under the CARES Act; (iii) the tenant is unable to pay the full rent due to substantial loss of household income, loss of work or wages, or extraordinary out-of-pocket medical expenses; (iv) the tenant is using best efforts to make partial payments that are as close to the full rental payments as the tenant’s circumstances permit; and (v) the eviction would likely render the individual homeless or force the individual to move into and live in close quarters or shared living space.
Effect of the CDC Order The CDC Order prevents landlords from evicting tenants for the non-payment of rent or similar housing-related payments that have sent their landlord a CDC Declaration. The CDC Order does not relieve tenants of the obligation to pay rent or other charges owed under their leases and does not preclude a landlord from charging late fees, penalties, or interest for missed payments.
Read the court decisionRead the full story...Reprinted courtesy of
Colton Addy, Snell & WilmerMr. Addy may be contacted at
caddy@swlaw.com
Port Authority Approves Subsidies for 2 World Trade Project
December 10, 2015 —
David M. Levitt – BloombergThe Port Authority of New York and New Jersey approved subsidies to help expedite the construction of lower Manhattan’s 2 World Trade Center, where Rupert Murdoch’s 21st Century Fox Inc. and News Corp. companies have a tentative deal to move their headquarters from midtown.
Developer Silverstein Properties Inc., which leases the sites for 2 World Trade Center and two other towers from the Port Authority, would receive a rent break that amounts to $9 million over the life of the lease, Authority Director Patrick Foye said, just before the agency board unanimously approved the proposal.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Levitt, Bloomberg