Brief Overview of Rights of Unlicensed Contractors in California
September 10, 2014 —
William M. Kaufman – Construction Lawyers BlogUnder California Contractor’s State License Law enumerated in Business and Professions Code Sections 7000 to 7191, a contractor may not “bring or maintain” any action for compensation for performing any act or contract for which a license is required unless the contractor was duly licensed “at all times” during performance. Bus & Prof Code Section 7031(a).
What does this mean and who does it include?
This is a question that often has to be answered on a case by case basis. Basically, California does not want unlicensed contractors to be able to get paid for work that should be performed by a licensed contractor. The law has set forth some general parameters. General contractors, subcontractors, and master developers must be licensed. However, suppliers, manufacturers, laborers and equipment lessors are exempt and do not need a contractor’s license. Essentially, those parties that merely furnish material or supplies without fabricating them into, or consuming them in the performance of work, do not need to be licensed. Bus & Prof Code Section 7052.
There are sever fines and penalties for those who improperly perform construction work without a license. A contract between any contractor and an unlicensed subcontractor is a misdemeanor. Lack of a license bars all actions in law or in equity for collection of compensation for the performance of work requiring a license. There are very few exceptions to this rule. A “savvy” unlicensed contractor cannot simply avoid these requirements by “subbing” out all the work to licensed contractors. Any person who uses the services of an unlicensed contractor may file a court action or cross-complaint to recover all payments made to the unlicensed contractor. In addition, a person who uses the services of an unlicensed contractor is a victim of a crime and eligible for restitution of economic losses regardless of whether that person had knowledge that the contractor was unlicensed. Bus. & Prof Code Sections 7028, 7028.16. It goes without saying that performing work without a license on projects is a bad idea.
Reprinted courtesy of
William M. Kaufman, Lockhart Park LP
Mr. Kaufman may be contacted at wkaufman@lockhartpark.com, and you may visit the firm's website at www.lockhartpark.com
Read the court decisionRead the full story...Reprinted courtesy of
HHMR is pleased to announce that David McLain has been selected as a 2020 Super Lawyer
June 29, 2020 —
David M. McLain – Colorado Construction LitigationDavid McLain is a founding member of Higgins, Hopkins, McLain & Roswell. Mr. McLain has over 22 years of experience and is well known for his work in the defense of the construction industry, particularly in the area of construction defect litigation. He is a member of the Executive Committee of the CLM Claims College - School of Construction, which is the premier course for insurance, industry, and legal professionals. Law Week Colorado recently named Mr. McLain as the 2019 People’s Choice for Best Construction Defects Lawyer for Defendants.
HHMR is highly regarded for its expertise in construction law and the litigation of construction-related claims, including the defense of large and complex construction defect matters. Our attorneys provide exceptional service to individuals, business owners, and Fortune 500 companies. The firm is experienced in providing legal support throughout trials and alternative dispute resolution such as mediations and arbitrations.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Show Me the Money: The Good Faith Dispute Exception to Prompt Payment Penalties
March 13, 2023 —
Garret Murai - California Construction Law BlogCalifornia has a number of
prompt payment penalty statutes on the books. Among them is Civil Code section 8800 which requires project owners on private works projects to pay progress payments to direct contractors within 30 days after demand for payment pursuant to contract or be subject to prompt payment penalties of two percent (2%) per month on the amount wrongfully withheld. Like California’s other prompt payment penalty statutes, however, there is an important carve out: If there is a good faith dispute between the project owner and the direct contractor the project owner may withhold up to 150% of the dispute amount and not be subject to prompt payment penalties. And that, my friends, is a higher-tiered party’s “get out of jail free” card.
In a case of first impression, the 1st District Court of Appeals, in
Vought Construction Inc. v. Stock (2022) 84 Cal.App.5th 622, examined whether a project owner’s claim for liquidated damages constitutes a good faith dispute under Civil Code section 8800.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Equipment Costs? It’s a Steal!
July 08, 2011 —
CDJ STAFFKCBD reports on the problems of a Lubbock, Texas contractor. It’s hard to do the job when your tools keep getting stolen. Corey Meadows, owner of Top Cut Interiors, told KCBD that he had chained an air compressor to a table saw. Since the thieves couldn’t cut the chain, they cut the table saw “and just took the air compressor and the chain.” Meadows estimates the thieves cost him $2,000 in damaged or stolen equipment and time lost.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Differing Site Conditions: What to Expect from the Court When You Encounter the Unexpected
September 05, 2022 —
Margarita Kutsin - Ahlers Cressman & Sleight[
1]Seattle Tunnel Partners (“STP”), a joint venture of Dragados USA and Tutor Perini, entered into a $1.4 billion contract with the Washington State Department of Transportation (“WSDOT”) to replace the Highway 99 viaduct. In December 2013, a tunnel boring machine (“TBM”) bearing the moniker “Bertha,” then the largest TBM ever built, measuring 425 feet long and 57 feet in diameter, struck an underground pipe. Shortly after the impact, Bertha overheated and eventually could no longer make forward progress. A massive repair effort ensued causing a 2.5-year delay in reaching substantial completion.
WSDOT sued STP for the delay, seeking liquidated damages of $57 million. In response, STP argued its delay was excusable because it was caused by Bertha’s impact with the pipe, and the steel well casing was a Differing Site Condition (DSC) undisclosed in the contract documents. STP asserted counterclaims against WSDOT, alleging breach of contract and seeking $300 million in damages. Ultimately, a jury found that the steel well casing on the pipe was not a DSC, foreclosing STP’s excusable delay defense and counterclaims, and resulting in a $57 million verdict, plus interest, in favor of WSDOT.
Read the court decisionRead the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & SleightMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
Defective Panels Threatening Profit at China Solar Farms: Energy
January 21, 2015 —
Bloomberg NewsFlaws found in some Chinese solar panels can drastically eat into their efficiency, reducing how much power the panels will produce as the country races to meet aggressive goals to hold the line on fossil fuel emissions.
The defects, found in products set to be used only in China, are in a coating that suppresses reflections on glass, allowing the panels to capture more light. About 23 percent of samples taken from dozens of Chinese companies failed to meet requirements, according to regulators in China. For samples from Jiangsu, the eastern province where much of the glass is made, the rate was as high as 40 percent.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg News
Eliminating Waste in Construction – An Interview with Turner Burton
June 29, 2020 —
Aarni Heiskanen - AEC BusinessI had the pleasure of interviewing Turner Burton, President of Hoar Construction. We discussed waste in construction and how his company is on a mission to eliminate it.
Can you say a few words about yourself and your company?
I grew up around construction and this company, hearing about the business from both my grandfather and my father. I started working on job sites in high school forming concrete, continued working on projects throughout college, and since graduating from college, I’ve taken on different roles in the company to ensure I understand all aspects of the business.
Hoar Construction was founded 80 years ago, and throughout our history, we’ve been committed to learning from every project to improve our processes and deliver the best building experience possible for our clients and partners. But it’s the relentless pursuit of improvement that really sets us apart as builders – to always strive to be the best and do the right thing for our customers and partners. There’s something to be said for setting a goal that you’ll always be working toward. It fosters hard work, collaboration, and productive effort. If we’re always working to find a better way, then we will always be improving. That effort drives better results for our owners and everyone we work with. Essentially, we’re always working toward something. Always improving. Always in process.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
ASCE Statement on Passage of the Water Resources Development Act (WRDA) of 2022
December 26, 2022 —
Maria Lehman - American Society of Civil EngineersWASHINGTON, D.C. – ASCE applauds Congress for passing the bipartisan Water Resources Development Act (WRDA) for 2022, which was included in the National Defense Authorization Act. The legislation authorizes construction for 25 new and existing U.S. Army Corps of Engineers (USACE) water infrastructure projects, including those related to dams, ports and inland waterways, flood risk management, and storm risk reduction. We are encouraged that the biannual reauthorization of WRDA continues to be a congressional priority.
ASCE applauds Congress for WRDA 2022 authorizing and establishing several programs dedicated to ensuring that our nation's water resources infrastructure benefits communities across the country. These accomplishments include reauthorizing the National Levee Safety Program; authorizing dredging activity in underserved community harbors; authorizing the USACE to recruit individuals more actively for careers in science, technology, engineering, and math (STEM); and enhancing infrastructure resilience, such as allowing the USACE to incorporate resilience measures into federally authorized hurricane or shore protection projects when performing emergency repairs. ASCE is also pleased to see that WRDA 2022 makes the current federal cost share formula for Inland Waterways Trust Fund projects permanent, with 65 percent coming from the general fund and 35 percent from the Inland Waterways Trust Fund (IWTF). ASCE strongly supports this provision, as it was a key recommendation to raise the nation's "D+" inland waterways grade in the 2021 Report Card for America's Infrastructure.
Additionally, ASCE strongly supports provisions in WRDA 2022 that will enhance the safety of the nation's dams and levees, which each received a "D" grade in the 2021 report card. The bill requires the Corps to establish a new National Low-Head Dam Inventory to account for the nation's low-head dams, which can pose significant public hazards. Identifying and monitoring these types of dams nationwide will contribute to the overall safety of the nation's dams and help to save lives.
Finally, the reauthorization of WRDA works hand-in-hand with the additional investments made in the Bipartisan Infrastructure Law. This reauthorization shows that infrastructure remains a bipartisan priority. We thank Congress for passing this legislation and look forward to translating these investments to critical water infrastructure system improvements nationwide.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of