Waiver of Subrogation and Lack of Contractual Privity Bars Commercial Tenants’ Claims
May 08, 2023 —
Melissa Kenney - The Subrogation StrategistIn United States Automatic Sprinkler Corporation v. Erie Insurance Exchange, et al., No. 2SS-CT-264, 2023 Ind. LEXIS 105, the Supreme Court of Indiana (Supreme Court) reversed an order of the trial court that denied a motion for summary judgment filed by a sprinkler contractor. At issue was whether commercial tenants – one who contracted with the sprinkler contractor and others who did not – could recover for their respective property damages. The court held that under the contract’s subrogation waiver and agreement to insure, the contracting tenant waived its insurer’s rights to recover through subrogation. With respect to the non-contracting tenants, who sought to recover only property damages, the court held that the absence of contractual privity barred their recovery.
The case centered around a sprinkler system that malfunctioned and flooded the Sycamore Springs Office Complex (Landlord), causing extensive property damage to four commercial tenants. Surgery Center, one of the four tenants, requested permission from the Landlord to install a sprinkler system inside the building. Landlord agreed, in exchange for Surgery Center agreeing to be solely responsible for maintaining the sprinkler system. Surgery Center hired United States Automatic Sprinkler (Automatic Sprinkler) to both install and conduct periodic inspection and testing of the sprinkler system. The contract terms outlined the scope of work to be performed by Automatic Sprinkler and the work was limited to the inspection and testing of the sprinkler system. Although repairs and emergency services were excluded from the contract, each could be performed upon the request and authorization of Surgery Center for an additional cost. The contract also contained certain risk allocation provisions including a waiver of subrogation and an agreement to insure.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Kenney, White and Williams LLPMs. Kenney may be contacted at
kenneyme@whiteandwilliams.com
How the Cumulative Impact Theory has been Defined
November 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesLargely in the federal contract arena, there is a theory referred to as “cumulative impacts” used by a contractor to recover unforeseeable costs associated with a multitude of changes that have an overwhelming ripple effect on its efficiency, particularly efficiency dealing with its original, base contract work. In other words, by dealing with extensive changes, there is an unforeseeable impact imposed on the contractor relative to its unchanged or base contract work. Under this theory, the contractor oftentimes prices its cumulative impact under a total cost approach with an examination on its cost overrun. However, this is not an easy theory to prevail on because there needs to be a focus on the sheer number of changes, causation supporting the impact, and whether there were concurrent impacts or delays that played a role in the ripple effect. See, e.g., Appeals of J.A. Jones Const. Co., ENGBCA No. 6348, 00-2 BCA P 31000 (July 7, 2000) (“However, in the vast majority of cases such claims are routinely denied because there were an insufficient number of changes, contractor-caused concurrent delays, disruptions and inefficiencies and/or a general absence of evidence of causation and impact.”).
To best articulate how the cumulative impact theory has been defined, I want to include language directly from courts and board of contract appeals that have dealt with this theory. This way the contractor knows how to best work with their experts with this definition in mind–and, yes, experts will be needed–to persuasively package and establish causation and damages stemming from the multitude of changes. While many of these definitions are worded differently, you will see they have the same focus dealing with the unforeseeable ripple effect of the extensive changes.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
No Coverage for Installation of Defective Steel Framing
June 26, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe California Court of Appeal affirmed the trial court's holding that the insurer had no duty to defend claims arising out of the insureds' installation of defective steel framing in an apartment building. Regional Steel Corp. v. Liberty Surplus Ins. Corp., No. B245961(Cal. Ct. App. May 16, 2014) [decision here].
Regional Steel was a subcontractor for providing reinforced steel to the columns, walls, and floors of an apartment building under construction. Regional used 90 degree and 135 degree seismic hooks as approved by the general contractor, JSM Construction, Inc. The City building inspector issued a correction notice, however, requiring the exclusive use of the 135 degree hooks. Levels one through three had defective tie hooks and required repair. JSM refused to pay Regional's invoices and withheld $545,000. JSM had to make repairs that required opening up numerous locations in the concrete walls, welding reinforcements to the steel placed by Regional, and otherwise strengthening the inadequate installation.
Regional sued JSM for the withheld payment. JSM cross-claimed, asserting breach of contract and breach of express and implied warranties.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
U.S. State Adoption of the National Electrical Code
August 24, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPWhat is the National Electrical Code?
Did you know that as of 2017, there have been 15 revisions of The National Electrical Code since 1975, the year the average American home was built?
The National Electrical Code codifies the minimum requirements for the safe electrical installations in a single, standardized source. While the NEC is not itself a law, the NEC is commonly mandated by state or local law. Where the NEC is adopted, anything less than the standards set by the NEC are illegal. The NEC revision is an open process that produces a new code every three years. The process includes:
- Public Input
- Public Commentary
- NFPA Technical Session
- Standards Council Action – Appeals and Issuance of the NEC
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Bank Sues over Defective Windows
July 31, 2013 —
CDJ STAFFThe Federal Reserve Bank of St. Louis replaced 498 windows in its building in 2008. According to a consultant, they all have to be replaced again. The bank estimates that the damages will exceed $1.5 million, and they are suing the contractor who installed them, the window manufacturer, and others.
The windows were replaced to provide greater blast protection. But in 2011, the bank found that the special glass used was beginning to delaminate. The Federal Reserve is seeking to have all of the windows replaced “with windows that meet the specifications of the contract.”
McCarthy Building Construction says that it is attempting to resolve things. The contractor noted that it is “continuing to work with the Federal Reserve and other parties and hope we can resolve this matter in a timely manner.”
Read the court decisionRead the full story...Reprinted courtesy of
N.J. Voters Approve $116 Million in School Construction
March 19, 2014 —
Stacie Sherman – BloombergNew Jersey voters in 11 of 13 school districts with bond referendums this week approved $116.1 million of construction.
The largest project, out of a total of $180 million proposed, failed. Voters in the Greater Egg Harbor Regional High School District rejected $37 million in renovations to three schools. The work would have increased property taxes as much as $36 a year, according to the district, which serves four towns at the Jersey Shore.
Read the court decisionRead the full story...Reprinted courtesy of
Stacie Sherman, BloombergMs. Sherman may be contacted at
sbabula@bloomberg.net
Confidence Among U.S. Homebuilders Declines to Eight-Month Low
March 19, 2015 —
Bloomberg News(Bloomberg) -- Confidence among U.S. homebuilders unexpectedly fell in March to an eight-month low as prospective buyers were in little rush to shop for properties ahead of the busier spring selling season.
The National Association of Home Builders/Wells Fargo sentiment gauge dropped to 53 from 55 in February, figures from the Washington-based group showed Monday. The median forecast in a Bloomberg survey called for a gain to 56.
Sales of single-family homes declined to a five-month low and builder optimism about the outlook failed to improve, the report also showed. Low mortgage rates and job creation may help spur homebuyer interest in coming months.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg NewsMichelle Jamrisko may be contacted at
mjamrisko@bloomberg.net
The Contingency Fee Multiplier (For Insurance Coverage Disputes)
September 10, 2018 —
David Adelstein - Florida Construction Legal UpdatesThe contingency fee multiplier: a potential incentive for taking a case on contingency, such as an insurance coverage dispute, where the insured sues his/her/its insurer on a contingency fee basis.
In a recent property insurance coverage dispute, Citizens Property Ins. Corp. v. Agosta, 43 Fla.L.Weekly, D1934b (Fla. 3d DCA 2018), the trial court awarded the insured’s counsel a contingency fee multiplier of two times the amount of reasonable attorney’s fees. The insurer appealed. The Third District affirmed the contingency fee multiplier.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com